CITATION:
Edwards v Cummins Constructions Pty Ltd [2023] QCAT 3
PARTIES:
MICHAEL EDWARDS (applicant)
v
CUMMINS CONSTRUCTIONS PTY LTD (respondent)
APPLICATION NO/S:
BDL285-20
MATTER TYPE:
Building matters
DELIVERED ON:
10 January 2023
HEARING DATE:
7 December 2022
HEARD AT:
Brisbane
DECISION OF:
Member King-Scott
ORDERS:
The Tribunal:
1. Dismisses the application;
2. Directs the parties to make and exchange submissions, if any, in respect to costs as follows:
(a) The Respondent by 4:00 pm 24 February 2023;
(b) The Applicant by 4:00 pm 10 March 2023.
CATCHWORDS:
CONTRACTS – BUILDING, ENGINEERING AND RELATED CONTRACTS – REMUNERATION – dispute between home owner and builder – work not defective or incomplete – work not in accordance with contract, plans and specifications
CONTRACTS – BUILDING, ENGINEERING AND RELATED CONTRACTS – OTHER MATTERS – whether construction of pontoon is reviewable domestic building work
ADMINISTRATIVE LAW – ADMINISTRATIVE TRIBUNALS – QUEENSLAND CIVIL AND ADMINISTRATIVE TRIBUNAL - where failure to provide evidence – failure to comply with directions to file statements of evidence – adversarial nature of proceedings
Queensland Building and Construction Commission Act 2009 (Qld)
Queensland Building and Construction Commission Regulations 2018 (Qld)
APPEARANCES & REPRESENTATION:
Applicant:
Self represented
Respondent:
B English solicitor CIF Lawyers
REASONS FOR DECISION
The parties entered into a Master Builders Queensland Residential Building Contract - Level 2 for the construction of a house at Jacobs Well. Work commenced on 24 April 2019 and was completed on 10 September 2019.
Cummins Constructions Pty Ltd trading as G J Gardner Homes – Gold Coast North was the builder who, hereafter, I will refer to as the ‘builder’.
Practical completion occurred on 10 September 2019 with final payment made the day before on 9 September 2019. The contract price, $398,624.00 and variation of $1,526.43 totalling $400,150.43, has been paid in full.
The builder says that Mr Edwards inspected the works on practical completion and on some issues agreed to disagree but completed the contract and took possession. No defects notice pursuant to clause 17.5 of the Contract listing any minor defects was produced in evidence. Mr Edwards says that the final acceptance and handover contains a list of exceptions in which all the complaints are documented as exceptions, but the document is not in evidence.[1]
[1]Applicant’s response to the Respondent’s statement of evidence in reply dated 1 August 2021 p.23
The Applicant, Mr Edwards, lodged a complaint of defective building work with the Queensland Building and Construction Commission (QBCC) on 12 February 2020. The QBCC found no defective work and determined that the issues were contractual. On 26 April 2022, Mr Edwards commenced proceedings in the Tribunal claiming compensation for defective work which were itemised in the application as follows:
(a)Water supply to pontoon defective work;
(b)Exposed sewer vent;
(c)Exposed water supply service;
(d)Water tap to be relocated as shown on the drawings;
(e)Hebel panels to be installed as shown in drawings.
Each complaint was investigated by Queensland Building and Construction Commission (“the Commission”) and found not to…
Continue reading Edwards v Cummins Constructions Pty Ltd
Sign in free to access the full text
- AGLC
- Edwards v Cummins Constructions Pty Ltd [2023] QCAT 3
- Case
- [2023] QCAT 3
- Decision Date
CaseChat Overview and Summary
The legal issues in this case were whether the Tribunal had jurisdiction to decide a dispute relating to the pontoon and whether the applicant had established a basis for his claims. The Tribunal found that it did not have jurisdiction to decide a dispute relating to the pontoon as it was excluded building work under the Queensland Building and Construction Commission Regulations 2018 (Qld). The Tribunal also found that the applicant had not established a basis for his claims as there was insufficient evidence to support his allegations of defective work. The Tribunal dismissed the application and directed the parties to make and exchange submissions in respect to costs.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.