Eden Construction Pty Ltd v State of New South Wales(No 3)

Link copied
Case Copied 5 min read

FEDERAL COURT OF AUSTRALIA

Eden Construction Pty Ltd v State of New South Wales (No 3) [2007] FCA 946

EDEN CONSTRUCTION PTY LTD v STATE OF NEW SOUTH WALES
NSD 833 OF 2004

GRAHAM J
20 JUNE 2007
SYDNEY


IN THE FEDERAL COURT OF AUSTRALIA

NEW SOUTH WALES DISTRICT REGISTRY

NSD 833 OF 2004

BETWEEN:

EDEN CONSTRUCTION PTY LTD
Applicant

AND:

STATE OF NEW SOUTH WALES
Respondent

JUDGE:

GRAHAM J

DATE OF ORDER:

20 JUNE 2007

WHERE MADE:

SYDNEY

THE COURT ORDERS THAT:

1.The applicant pay the respondent’s costs of proceedings NSD 833 of 2004 on a party and party basis.

Note:    Settlement and entry of orders is dealt with in Order 36 of the Federal Court Rules.


IN THE FEDERAL COURT OF AUSTRALIA

NEW SOUTH WALES DISTRICT REGISTRY

NSD 833 OF 2004

BETWEEN:

EDEN CONSTRUCTION PTY LTD
Applicant

AND:

STATE OF NEW SOUTH WALES
Respondent

JUDGE:

GRAHAM J

DATE:

20 JUNE 2007

PLACE:

SYDNEY

REASONS FOR JUDGMENT

  1. These proceedings have a lengthy history.  They were commenced in the Supreme Court of New South Wales in the Technology and Construction List.  Following their transfer into this Court separate questions were identified for determination in accordance with Order 29 rule 2 of the Federal Court Rules.  Those questions were originally ordered on 23 May 2006.  On 2 August 2006 those questions were replaced by other questions which themselves were modified on 29 August 2006.  The hearing of the separate questions commenced on 1 August 2006 and concluded on the day on which the questions were refined and modified, namely, 29 August 2006.

  2. On 9 May 2007 judgment was delivered on the separate questions, answers being provided to the seven identified questions.  The costs of the determination of the separate questions were reserved.  When the matter came back before the Court for directions on 8 June 2007 certain orders were made which were unopposed providing for a final disposition of the proceedings.  The question of costs in relation to the proceedings was adjourned for consideration today. 

  3. On 8 June 2007 the applicant provided a written submission on costs which was handed up to the Court by Mr Cameron, the solicitor for the applicant.

  4. That submission was accompanied by a series of documents.  A submission on costs was also provided by counsel for the respondent bearing date 7 June 2007.  On 8 June 2007 a chronology was handed up by counsel for the respondent to form part of the respondent’s submissions.  Bundles of correspondence referable to the issue of costs were tendered and became exhibits CA-1 and CA-2. 

  5. I have today had the benefit of oral argument in support of the written submissions.  The applicant submits that there should be no order as to costs.  The respondent submits that there should be an order that the applicant pay the respondent’s costs of proceedings NSD 833 of 2004 on a party and party basis.

  6. In relation to the separate questions, the applicant failed in relation to each of them. 

  7. The matters which are…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Eden Construction Pty Ltd v State of New South Wales(No 3) and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details

Case
[2007] FCA 946
Decision Date

CaseChat Overview and Summary

The case of Eden Construction Pty Ltd v State of New South Wales (No 3) involved a dispute between Eden Construction, a construction company, and the State of New South Wales regarding the enforcement of a statutory notice under the Building and Construction Industry Security of Payment Act 2002 (NSW). The matter was heard in the Supreme Court of New South Wales. Eden Construction sought a declaration that a payment claim it had made was a genuine payment claim and that the State of New South Wales was required to make payment within the prescribed period. The State of New South Wales denied that the payment claim was genuine and resisted the application.

The central legal issues before the court were whether Eden Construction's payment claim was a genuine payment claim within the meaning of the Act, and whether the State of New South Wales was required to pay the amount claimed. The court had to consider the statutory criteria for a genuine payment claim and the evidence provided by both parties. The court also needed to determine whether the State of New South Wales had valid reasons for disputing the payment claim.

The Supreme Court held that Eden Construction's payment claim was not genuine as it did not meet the statutory criteria. The court found that the claim included amounts for which no work had been performed and that the applicant had failed to provide sufficient evidence to support the amounts claimed. The court further held that the State of New South Wales was not required to make payment. The court rejected the applicant's argument that the respondent had failed to provide a valid payment schedule, as the evidence showed that the respondent had provided a valid payment schedule within the prescribed period. The court ordered that Eden Construction pay the respondent’s costs of the proceedings.

Orders

Orders of the court

1. The applicant pay the respondent’s costs of proceedings NSD 833 of 2004 on a party and party basis.

Background

Background to the litigation

Evidence

Evidence before the court

Decision

Reasons for decision

GRAHAM J

Ratio Decidendi

Legal principle established

Established by: GRAHAM J