FEDERAL COURT OF AUSTRALIA
Eden Construction Pty Ltd v State of New South Wales [2008] FCA 376
CONTRACT – inducing breach of contract – principal intending to accept tender hears adverse comments from informant on tenderer’s past performance – whether principal owes tenderer implied contractual obligation not to decline to accept tender without first giving tenderer opportunity to be heard – whether informant induces principal to breach an implied contractual obligation owed by principal to tenderer - Held: no implied obligation made out.
TORT – inducing breach of contract – principal intending to accept tender hears adverse comments from informant on tenderer’s past performance – whether principal owes tenderer implied contractual obligation not to decline to accept tender without first giving tenderer opportunity to be heard – whether informant induces principal to breach an implied contractual obligation owed by principal to tenderer - Held: no implied obligation made out.
Cubic Transportation Systems Inc v State of New South Wales [2002] NSWSC 656 referred to
Hughes Aircraft Systems International v Airservices Australia (1997) 76 FCR 151 distinguishedEDEN CONSTRUCTION PTY LTD v STATE OF NEW SOUTH WALES
NSD 102 OF 2008
LINDGREN J
20 MARCH 2008
SYDNEY
IN THE FEDERAL COURT OF AUSTRALIA
NEW SOUTH WALES DISTRICT REGISTRY
NSD 102 OF 2008
BETWEEN:
EDEN CONSTRUCTION PTY LTD
ApplicantAND:
STATE OF NEW SOUTH WALES
Respondent
JUDGE:
LINDGREN J
DATE OF ORDER:
20 MARCH 2008
WHERE MADE:
SYDNEY
THE COURT ORDERS THAT:
1.The application be dismissed.
2.The applicant pay the respondent’s costs of the proceeding.
Note: Settlement and entry of orders is dealt with in Order 36 of the Federal Court Rules.
IN THE FEDERAL COURT OF AUSTRALIA
NEW SOUTH WALES DISTRICT REGISTRY
NSD 102 OF 2008
BETWEEN:
EDEN CONSTRUCTION PTY LTD
ApplicantAND:
STATE OF NEW SOUTH WALES
Respondent
JUDGE:
LINDGREN J
DATE:
20 MARCH 2008
PLACE:
SYDNEY
REASONS FOR JUDGMENT
INTRODUCTION
The applicant (Eden) applies for an extension of time in which to file and serve notice of an appeal from the judgment of a Judge of the Court given on 9 May 2007: see Eden Construction Pty Ltd v State of New South Wales (No 2) (2007) ATPR 42. On that date, the primary Judge, Graham J, answered a number of questions separately and before any other questions in the proceeding. According to the application, the extension of time is required because the notice of appeal was not filed and served within the time limited by O 52 r 15 of the Federal Court Rules. Order 52 r 15 provides, relevantly, that a notice of appeal must be filed and served within 21 days after the date when the judgment appealed from was pronounced. In its written submissions, Eden states that its application is for “leave to appeal out of time”. There is no right of appeal from an interlocutory judgment unless the Court or a Judge gives leave to appeal: see s 24(1)A of the Federal Court of Australia Act 1976 (Cth).
On 8…
Keep reading for free
Create a free CaseChat account to read Eden Construction Pty Ltd v State of New South Wales and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2008] FCA 376
- Decision Date
CaseChat Overview and Summary
The court was tasked with deciding whether the DPWS's actions constituted a breach of an implied contract, referred to as a 'process contract,' between Eden and Allied, and if the State's actions constituted the tort of interference with contractual relations. The court examined whether such a process contract existed and whether the DPWS breached it by influencing Allied's decision. Additionally, the court considered the adequacy of the reasons given by the primary judge for dismissing the interference claim.
The court held that Eden's claims were not properly before it as they were not raised at trial. The court emphasised that the claim of an implied process contract was new and could not be introduced at the appellate stage. Furthermore, Eden failed to specify the nature of the implied contractual obligation that the DPWS allegedly induced Allied to breach. The court also found that the primary judge's reasons for dismissing the interference claim were adequate, and there was no basis for the appeal. Consequently, the application was dismissed with Eden ordered to pay the respondent's costs.
Orders
Orders of the court
1. The application be dismissed.
2. The applicant pay the respondent’s costs of the proceeding.
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi
Legal Principle Established
Established by: LINDGREN J
The three grounds of appeal now pressed are as follows:1.Graham J erred in failing to hold on the facts before him that a contract in the nature of a ‘process contract’ existed between the Appellant and Allied Constructions Pty Ltd.2.Graham J erred in failing to hold on the facts as found by him that the elements of the tort of interference with contractual relations was made out in relation to the process contract between the Appellant and Allied Constructions.3.The reasons for decision delivered by Graham J in relation to the issue of the tort of interference with contractual relations were inadequate and failed to disclose any reasoning process sufficient to justify his decision.CONSIDERATION The obvious must be emphasised: Allied did not accept Eden’s tender, and Eden has not sued Allied for breach of any kind of contract. Eden contends that there was a “process contract” between Eden and Allied, and that the State unlawfully interfered with that contract. Eden refers to Hughes Aircraft Systems International v Airservices Australia (1997) 76 FCR 151 (Hughes) and Cubic Transportation Systems Inc v State of New South Wales [2002] NSWSC 656 (Cubic Transportation). The facts of Hughes were vastly different from those of the present case. In Hughes, there were two competing tenderers, the applicant in the proceeding being the unsuccessful one. Finn J held that in the circumstances of the case, there was an implied contract that might be called a “process contract”, according to which Airservices Australia incurred implied contractual obligations in favour of the tenderers, including an implied obligation to conduct its evaluation fairly and in a manner that would ensure equal opportunity as between them. Cubic Transportation also concerned competing tenderers. Eden’s case as now presented is that there was a process contract between Allied and Eden, and that the DPWS induced Allied to breach that contract by not accepting Eden’s tender. Eden has not referred to evidence of any competing tenderer on the scene. Indeed, Eden has not referred to any evidence of the terms on which it tendered to Allied. So far as I know, the circumstances were simply that Eden tendered; Allied was disposed but not bound to accept Eden’s tender; and Allied decided not to do so for the reasons mentioned. The first reason why Eden’s present application fails is that Eden did not make the present claim at trial. Notwithstanding the attempt by Senior Counsel for Eden to suggest otherwise, the fact is that the relevant parts of Eden’s amended points of claim alleged only that DPWS made representations to Allied and that as a result Allied did not engage Eden as its subcontractor on the Moruya Heads Project. Eden did not make submissions to his Honour in support of the existence of a tender process contract. A Full Court would not permit Eden to raise an entirely new case for the first time at the appellate level. Secondly, Eden has not pointed to any circumstances giving rise to the supposed implied tender process contract or suggested what the content of the implied contract would be. These two matters are closely interrelated. On the hearing, I raised the following question: what was the implied contractual obligation that DPWS is said to have induced Allied to breach? However, in its post-hearing written submissions, Eden has not attempted to identify that obligation.