Medium Neutral Citation: Eades v Endeavour Energy [2018] NSWSC 801 Hearing dates: 17 February 2017 Date of orders: 21 July 2017 Decision date: 25 May 2018 Jurisdiction: Common Law Before: Garling J Decision: Motions for security for costs dismissed
Catchwords: CIVIL PROCEDURE – costs – security for costs – representative proceedings – where lead plaintiff impecunious – where no litigation funder – nature of claims – personal injury – where claims are genuine – not possible to conclude at this preliminary stage that plaintiff has a weak case – late timing of applications after conclusion of opt out process – benefits to defendants in claims being litigated as representative proceedings – consideration of whether proceedings would be stultified – no order for security for costs Legislation Cited: Civil Liability Act 2002
Civil Procedure Act 2005
Uniform Civil Procedure Rules 2005Cases Cited: Bray v F Hoffman-La Roche Ltd (2003) 130 FCR 317
Daniel Rory de Groot (an infant by his tutor Arlena Van Oosten) v The Nominal Defendant [2004] NSWCA 88
De Jong v Carnival PLC [2016] NSWSC 347
Johnston v Endeavour Energy [2016] NSWSC 1132
Madgwick v Kelly [2013] FCAFC 61; (2013) 212 FCR 1
Phillips Electronic Australia Pty Ltd v Matthews [2002] NSWCA 157; (2002) 54 NSWLR 598Texts Cited: Not Applicable Category: Procedural and other rulings Parties: Laurence Kevin Eades (P)
Endeavour Energy (D)
Asplundh Tree Expert (Australia) Pty Ltd (D2)
Pinnacle Career Development Pty Ltd (D3)Representation: Counsel:
Solicitors:
A Fraatz (P)
Dr A Bell SC / H Pintos-Lopes (D1)
T A Berberian (D2, D3)
Maddens Lawyers (P)
Lander & Rogers (D1)
Colin Biggers & Paisley (D2)
Wotton & Kearney (D3)
File Number(s): 2015/310264 Publication restriction: Not Applicable
Judgment
-
In 2015, Mr Laurence Eades (“the plaintiff”) commenced proceedings against Endeavour Energy, claiming damages for its negligence which is alleged to have given rise to a bushfire that started in, or near, Mount York Road in Mount Victoria, NSW on 17 October 2013.
-
The plaintiff alleges that Endeavour Energy owned, had the use of and constructed and repaired the poles, conductors, transformers and associated equipment for a 22kv three phase feeder line known as the Blackheath feeder, which ran parallel to the Mount York Road at Mount Victoria, and an 11kv distribution line from the feeder line along the driveway to premises at Mount York Road.
-
The plaintiff further alleges that the transmission of electricity along either or both of the power lines created circumstances of danger such that if a tree, or part of a tree, were to fall on a line whilst it transmitted electricity, a fire might result from such an incident.
-
The plaintiff alleges that the bushfire was started in circumstances where a substantial tree, between 50 and 80 years old and at least 20m high and about 10m in spread, became overhung or was within the minimum clearance space of the electricity wires.
-
Lastly, the plaintiff claims that the tree had other particular features, which…
Continue reading Eades v Endeavour Energy
Sign in free to access the full text
- AGLC
- Eades v Endeavour Energy [2018] NSWSC 801
- Case
- [2018] NSWSC 801
- Decision Date
CaseChat Overview and Summary
The primary legal issue before the court was whether, given the genuineness of the claims and the procedural stage of the case, the court should order the plaintiff to provide security for the defendant's costs. The court considered the factors relevant to the exercise of its discretion under the relevant rules of court, including the nature and strength of the claims, the timing of the application, and the potential impact on the defendants if security were not ordered. The court noted that the plaintiff's claims were genuine and not frivolous, and that the defendants would benefit from the claims being litigated as representative proceedings. Additionally, the application for security was made late in the proceedings, after the opt-out process had concluded.
The court held that the plaintiff should not be required to provide security for the defendant's costs. The judge concluded that the genuineness of the claims and the potential benefits to the defendants in having the claims litigated as representative proceedings outweighed the potential disadvantage to the defendants in not receiving security for costs. The court found that it was not possible at this preliminary stage to conclude that the plaintiff had a weak case, and that the late timing of the application for security further supported the decision not to order security. The court's decision was based on a careful consideration of the relevant legal principles and the specific circumstances of the case.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established