DRYLAND and TANGENT NOMINEES PTY LTD

Link copied
Case Copied 59 min read

JURISDICTION     :   STATE ADMINISTRATIVE TRIBUNAL

ACT: BUILDING SERVICES (COMPLAINT RESOLUTION AND ADMINISTRATION) ACT 2011 (WA)

CITATION:   DRYLAND and TANGENT NOMINEES PTY LTD [2025] WASAT 31

MEMBER:   MR E CADE, MEMBER

MR R AFFLECK, SENIOR SESSIONAL MEMBER

HEARD:   6, 7 AND 8 AUGUST AND 27 NOVEMBER 2024

DELIVERED          :   11 APRIL 2025

FILE NO/S:   CC 974 of 2023

BETWEEN:   GAVIN DRYLAND

First Applicant

KASEY DRYLAND

Second Applicant

AND

TANGENT NOMINEES PTY LTD

Respondent


Catchwords:

Building Services (Complaint Resolution and Administration) Act 2011 (WA) - Home Building Contracts Act 1991 (WA) - Home Building Works Contract complaint - Authority of agent to bind principal - Proposed works not commenced - Breach of contract - Termination of contract - Damages for breach of contract - Doctrine of mitigation of loss - Quantum of compensation

Legislation:

Building Services (Complaint Resolution and Administration) Act 2011 (WA), s 5(2), s 6(3)(b), s 11(1)(d), s 41(2)(d)(i), s 43, s 43(1), s 43(1)(a)
Home Building Contracts Act 1991 (WA), s 7, s 7(1), s 17(a)(i), s 27(1)
State Administrative Tribunal Act 2004 (WA)
State Administrative Tribunal Rules 2004 (WA), r 39B, r 39B(5)

Result:

Application successful

Category:    B

Representation:

Counsel:

First Applicant : Mr S Mintz & Mr W Vogt
Second Applicant : Mr S Mintz & Mr W Vogt
Respondent : Mr C Taylor-Burch

Solicitors:

First Applicant : Vogt Legal
Second Applicant : Vogt Legal
Respondent : Morgan Alteruthemeyer Legal Group

Case(s) referred to in decision(s):

Allianz Australia Insurance Ltd v Delor Vue Apartments CTS 39788 [2022] HCA 38

Clark v Macourt [2013] HCA 56

Deshmukh and Distinctive Building Services Pty Ltd [2024] WASAT 15

Electricity Generation Corporation t/a Verve Energy v Woodside Energy Ltd [2014] HCA 7

Hadley v Baxendale (1854) 9 Ex 341; 156 ER 145

Hippydayze Pty Ltd and Mener Group Pty Ltd [2019] WASAT 92

Luxer Holding Pty Ltd v Glentham Pty Ltd (2007) 35 WAR 254

Pacific Carriers Ltd v BNP Paribas (2004) 218 CLR 451

REASONS FOR DECISION OF THE TRIBUNAL:

Introduction

  1. On 20 July 2020 the first and second applicants (first and second owners, together the owners) bought a lot known as 49B Halls Head Parade, Halls Head, in the City of Mandurah (the site).[1] 

    [1] Hearing Book (HB), page 16.

  2. Significantly in this proceeding:

    (a)the site is a vacant 'battle-axe' site surrounded by developed lots;

    (b)the effective site area is situated on a rise elevated above both the nearest access road and surrounding lots;

    (c)the access leg is approximately 33.5 metres of rising length which is surfaced in concrete;

    (d)the southern side of the access leg of the site is contiguous with the southern side of the effective site area;

    (e)the southern side of the access leg is bordered by a lot known as 50A Halls Head Parade, and the southern side of the effective site area is bordered by a lot known as 50B Halls Head Parade; [2]  

    (f)a boundary wall built of brick runs along the full length of the southern boundary of…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read DRYLAND and TANGENT NOMINEES PTY LTD and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2025] WASAT 31
Decision Date

CaseChat Overview and Summary

The case of Dryland and Tangent Nominees Pty Ltd involved a dispute under the Building Services (Complaint Resolution and Administration) Act 2011 (WA) and the Home Building Contracts Act 1991 (WA). The applicants, Dryland and Tangent Nominees, sought a resolution to their complaint against a home building works contract. The central issue was whether the contract could be terminated due to the builder's alleged failure to commence the proposed works and the potential breach of the contract. Additionally, the applicants claimed damages for the breach and argued the builder was not entitled to invoke the doctrine of mitigation of loss.

The court examined the nature of the contract in light of the parties' mutual understanding at the time of the agreement. The key legal issue was whether the parties were aware of the southern boundary wall's structural limitations prior to signing the contract. The court found that neither party was aware of these limitations, as the language used in the initial correspondence and the evidence presented indicated a belief that only a portion of the above-ground brickwork was unstable. The applicants' intention was to address a specific section of the wall, not the entire structure. The court further noted that the applicants had obtained a quote for a limited section of the wall, further supporting the notion that only a portion of the wall was considered unstable.

In its reasoning, the Tribunal accepted the applicants' argument that the contract must be interpreted based on the objective terms understood by the parties at the time of the agreement. The court concluded that neither party had knowledge of the full depth and length of the southern boundary wall's structural inadequacies. Consequently, the Tribunal found that the builder was not entitled to rely on the doctrine of mitigation of loss and ordered the builder to pay compensation to the applicants in the amount of $179,132.00 by 9 May 2025. The application was otherwise dismissed.

Orders

Orders of the court

The Tribunal orders:

Pursuant to a home building work contract the parties entered on 24 November 2021 the Tribunal, under s 43 and s 41(2)(d)(i) of the Building Services (Complaint Resolution and Administration) Act 2011 (WA):

1. That by no later than 9 May 2025 the respondent must pay compensation to the applicants in the amount of $179,132.00.

2. The application is otherwise dismissed.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

When considering this issue, we have accepted as correct the owners' submission that the building contract is to be understood in the context of the matrix of facts mutually known to the parties at the time they entered into the contract. That is, we accept the Tribunal is to give effect to the objective terms of the contract as these were understood by the parties at the time they entered into the contract.[16] [16] Electricity Generation Corporation t/a Verve Energy v Woodside Energy Ltd[2014] HCA 7 at para 35. After considering the issue we are satisfied and we find that neither the owners nor the builder knew, prior to signing the building contract, that the full depth and length of the southern boundary wall was not capable of supporting access to the site or was not capable of supporting the proposed works on the site. This is for the following reasons. First, the language used by the first owner in his email to Mr McManus on 26 May 2021 - 'boundary brick wall', 'unstable' and 'will need to come down' is, in context, more consistent with an intention to refer only to a portion of above ground brickwork than it is with an intention to refer to the full depth and length of the boundary wall. This is because:(a)the photographs attached to this email show only that part of the wall which is above ground and which bounds the effective site area, but they do they not show the part of the wall on the southern boundary of the access leg;[17] and(b)the evidence shows that the first homeowner believed (whether correctly or not is immaterial) that the wall along the southern boundary of the site are in fact two separate walls, so that when he refers to these walls he speaks about them as two distinct walls and not as one continuous wall. These walls are first, a wall that was built along the boundary between the 50A Halls Head Parade and the site and second, a wall that was built at a different time between 50B Halls Head Parade and the site. The first owner in cross-examination said:[18]CADE MR:Perhaps we can hear from him. I think you were talking about context, Mr Dryland?---DRYLAND, MR: Yes, context around the opening submissions. And I wanted to provide that context as it relates to my statement and the relevant submissions, highlight the fact that there are indeed two separate walls, and they are separate issues. I just wanted to make that clear. That was all. TAYLOR-BURCH, MR: You don't know when the front portion of the boundary wall was built, do you?­­-DRYLAND, MR: I recall having a vague conversation with the City of Mandurah about it. But I don't recall the specific details. They - I know they told me that both properties and both walls weren't built at the same time …[19][17] HB, pages 923 - 925.[18] ts 86, 6 August 2024.[19] This intention is also consistent with the quote for repairs to the southern boundary brick wall which the first owner obtained on 15 September 2021 for the removal and replacement of '33.6 meters of brick work … blown down in storms', and not for the removal and replacement of the full depth and length of the southern boundary wall, HB, page 943.