Dreyer v Ausmar Homes t/as Ausmar Commercial

Link copied
Case Copied 27 min read

QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL


CITATION:

Dreyer v Ausmar Homes t/as Ausmar Commercial [2023] QCATA 161

PARTIES:

DEAN JASON DREYER

(applicant/appellant)

v

AUSMAR HOMES T/AS AUSMAR COMMERCIAL

(respondent)

APPLICATION NO/S:

APL275-22

ORIGINATING APPLICATION NO/S:

BDL296-20

MATTER TYPE:

Appeals

DELIVERED ON:

6 December 2023

HEARING DATE:

21 November 2023

HEARD AT:

Brisbane

DECISION OF:

A/Senior Member Fitzpatrick

ORDERS:

1.   Leave to appeal is refused.

2.   The appeal is dismissed.

CATCHWORDS:

CONTRACTS – BUILDING, ENGINEERING AND RELATED CONTRACTS – THE CONTRACT – GENERALLY – where written subcontract terminated – whether claim for unsubstantiated variation and suspension of work amounted to repudiation - applicant asserts an error of law and misrepresentation of facts in the proceeding below – nature of error of law and of mixed law and fact – whether leave to appeal should be granted.

Queensland Civil and Administrative Tribunal Act 2009 (Qld) ss 142(3)(b), 147

Comcare v Etheridge (2006) 149 FCR 522
Haritos and Anor v Commissioner of Taxation (2015) 322 ALR 254
Laurinda Pty Ltd v Capalaba Park Shopping Centre Pty Ltd (1989) 166 CLR 623
Mazelow Pty Ltd v Herberton Shire Council [2003] 1 Qd R 174
Pivovarova v Michelsen [2019] QCA 256
Rintoul v State of Queensland & Ors [2018] QCA 20
Robinson Helicopter Company Incorporated v McDermott [2016] HCA 22

Shevill v Builders Licensing Board [1982] HCA 47

APPEARANCES & REPRESENTATION:

This matter was heard and determined on the papers pursuant to s 32 of the Queensland Civil and Administrative Tribunal Act 2009 (Qld)

REASONS FOR DECISION

  1. Mr Dreyer has filed an application for leave to appeal or appeal a decision made on 15 August 2022.

  2. The decision was to dismiss Mr Dreyer’s application seeking damages for wrongful termination of a contract for the preparation, placement, and finish of all concrete works at the Sippy Creek Animal Pound. The contract was a written contract entered into between the respondent Ausmar Homes Pty Ltd trading as Ausmar Commercial and a subcontractor named as AA Concreting. Mr Dreyer signed the contract on behalf of AA Concreting. Mr Dreyer trades as AA Concrete Constructions. The subcontractor is referred to in this decision as Mr Dreyer or AA Concrete.

  3. The decision followed an oral hearing in the matter. At the hearing the parties relied on substantial written material filed in support of the application and the response.

  4. In the written reasons for the decision the Member set out evidence in relation to claimed variations to the contract, leading to an email from Mr Dreyer to Ausmar dated 18 July 2016 suspending work, and demanding payment for an unpaid variation claim.

  5. The Member found that Mr Dreyer had not established to his satisfaction any legitimate basis for suspending the contract. The Member accepted that Ausmar was entitled to terminate the contract, with the result that Mr Dreyer’s application was dismissed.

Application for leave to appeal or appeal

  1. Ausmar has not participated in the appeal proceeding and is non-compliant with all Directions. I am satisfied that Ausmar has been provided with…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Dreyer v Ausmar Homes t/as Ausmar Commercial and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2023] QCATA 161
Decision Date

CaseChat Overview and Summary

Dreyer was engaged by Ausmar Homes to construct a building. A dispute arose, and Dreyer sought an order to recover payments and a declaration that Ausmar Homes had repudiated the contract. Dreyer claimed that Ausmar Homes repudiated the contract by requiring an unsubstantiated variation and suspending work. The primary judge held that Dreyer's claim for an unsubstantiated variation and suspension of work did not amount to a repudiatory breach of contract. Dreyer appealed, arguing that the primary judge erred in law and misrepresented the facts. Dreyer sought leave to appeal on the grounds that the primary judge's decision contained an error of law and a misrepresentation of facts.

The court considered whether the primary judge's findings were so palpably and flagrantly wrong that the appeal should be allowed. Dreyer contended that the primary judge misinterpreted the contract terms and misapplied the law, leading to an incorrect conclusion about the repudiatory nature of the actions taken by Ausmar Homes. Dreyer argued that the primary judge failed to properly consider the objective nature of the repudiatory conduct and the impact of the actions on Dreyer's ability to perform the contract. Dreyer submitted that the primary judge's findings were a clear error of law and a misrepresentation of the facts.

The court held that Dreyer had not demonstrated that the primary judge's determination contained an error of law or a misrepresentation of facts to the extent required for leave to appeal. The court found that the primary judge's analysis of the contract terms and the applicable legal principles was sound and that the findings were based on a proper application of the law to the facts. The court concluded that Dreyer had not shown that the primary judge's decision was palpably and flagrantly wrong, and therefore, Dreyer was not entitled to leave to appeal. The appeal was dismissed.

Orders

Orders of the court

1. Leave to appeal is refused.

2. The appeal is dismissed.