Civil and Administrative Tribunal
New South Wales
Medium Neutral Citation: Ding v Sanli Design & Construction Pty Ltd [2021] NSWCATCD 116 Hearing dates: 1, 2, 8 December 2021 Date of orders: 20 December 2021 Decision date: 20 December 2021 Jurisdiction: Consumer and Commercial Division Before: Graham Ellis SC, Senior Member Decision: 1. The applicants are to pay the respondent $7,000 immediately.
2. On or before 31 December 2021 the respondent is to provide the applicants with certificates in relation to the electrical work and plumbing work the subject of the contract dated 08 December 2018.
3. No order as to costs by reason of the order for costs made in the related proceedings.
Catchwords: BUILDING AND CONSTRUCTION – Renewal proceedings - Compliance with orders - Whether to make money order - Reasonable cost of rectification
Legislation Cited: Civil and Administrative Tribunal Act 2013 (NSW)
Civil and Administrative Tribunal Rules 2014 (NSW)
Home Building Act 1989 (NSW)
Cases Cited: 3D Design & Build Pty Ltd v Lynch [2016] NSWCATAP 229
Bellgrove v Eldridge [1954] HCA 36
Blessed Sydney Constructions Pty Ltd v Vasudevan [2018] NSWCATAP 98
Bondarek v NSW Land and Housing Corporation [2018] NSWCATAP 299
Bonita v Shen [2016] NSWCATAP 159
Cretazzo v Lombardi (975) 13 SASR 4
Cripps v G & M Mawson [2006] NSWCA 84
Haines v Bendall [1991] HCA 15
Hamod v State of New South Wales and Anor [2011] NSWCA 375
Latoudis v Casey [1990] HCA 59
Maiolo v Chiarelli [2016] NSWCATAP 81
Makita (Australia) Pty Ltd v Sprowles [2001] NSWCA 305
Megerditchian v Kumond Homes Pty Ltd [2014] NSWCATAP 120
Minifie v Maxwell [2020] NSWCATAP 30
Mitchell v Cullingral Pty Ltd [2012] NSWCA 389
News v Cotes [2019] NSWCATAP 186
Oshlak v Richmond River Council [1998] HCA 11
Pacorp Holdings Pty Ltd v Waller [2017] NSWCATAP 167
The Owners Corporation Strata Plan No. 63341 v Malachite Holdings Pty Ltd [2018] NSWCATAP 256
The Owners Strata Plan No 79642 v Five D Pty Ltd [2020] NSWCATAP 110
Texts Cited: Nil
Category: Principal judgment Parties: De Long Ding and Kun Ding (Applicants)
Sanli Design & Construction Pty Ltd (Respondent)Representation: Solicitor:
Birch Partners (Applicants)
C Wei (Respondent)
File Number(s): HB 21/16050 (related proceedings HB 21/16006) Publication restriction: Nil
REASONS FOR DECISION
Outline
-
These proceedings, commenced on 12 April 2021, involve a renewal application by owners against a builder. It is convenient to here note that there is a related application (HB 21/16006) that was heard at the same time as these proceedings and is the subject of separate orders and reasons.
-
The issues raised by the renewal application may be summarised as whether there has been compliance with orders made by the Tribunal on 22 September 2020 and, if not, what orders should now be made.
-
Having considered the evidence and submissions, the Tribunal determined that both parties had failed to comply with those orders and that (1) the owners should be required to comply with order 8 which, as the…
Keep reading for free
Create a free CaseChat account to read Ding v Sanli Design and Construction Pty Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2021] NSWCATCD 116
- Decision Date
CaseChat Overview and Summary
The tribunal considered the evidence presented by both parties and the relevant statutory framework governing building and construction contracts. It found that the applicants had not fully complied with the orders and that there was a reasonable basis for the tribunal to order the applicants to pay the respondent $7,000. The tribunal also determined that the respondent should provide the applicants with the relevant certificates within the specified timeframe. The tribunal declined to make any order as to costs, citing the costs order made in the related proceedings.
In summary, the tribunal ordered the applicants to pay the respondent $7,000 and mandated that the respondent provide the applicants with certificates concerning the electrical and plumbing work. The tribunal refrained from making any further order regarding costs.
Orders
Orders of the court
1. The applicants are to pay the respondent $7,000 immediately.
2. On or before 31 December 2021 the respondent is to provide the applicants with certificates in relation to the electrical work and plumbing work the subject of the contract dated 08 December 2018.
3. No order as to costs by reason of the order for costs made in the related proceedings.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.