[2023] TASSC 22
| COURT: | SUPREME COURT OF TASMANIA |
| CITATION: | Digga Excavations Tas Pty Ltd v Linear Capital Pty Ltd [2023] TASSC 22 |
| PARTIES: | DIGGA EXCAVATIONS TAS PTY LTD |
| v | |
| LINEAR CAPITAL PTY LTD | |
| FILE NO: | 3285/2017 |
| DELIVERED ON: | 19 July 2023 |
| DELIVERED AT: | Hobart |
| HEARING DATES: | 27, 28, 29, 30 September 2022 |
| JUDGMENT OF: | Brett J |
| CATCHWORDS: |
Contracts – General Contractual Principles – Discharge, Breach and Defences to Action for Breach – Conditions
– Conditions Precedent and Subsequent – Building contract for industrial subdivision - Breach for non-
payment of progress certificates issued by plaintiff to defendant for work completed – Plaintiff did not comply with clause requiring ‘documentary evidence’ of moneys due and payable with progress claims
– Whether a condition precedent to Defendant paying progress certificates? Whether Defendant can rely
upon clause where it was unaware of, and did not insist on performance of, this clause during life of contract - Held Defendant can rely upon retrospective justification which existed, whether known of at
the time - Plaintiff’s termination of the contract was therefore ineffective and contract was mutually
abandoned.
Shepherd v Felt and Textiles of Australia Ltd (1931) 45 CLR 359 – applied.
DTR Nominees Pty Ltd v Mona Homes Pty Ltd [1978] HCA 12, 138 CLR 423; Downer EDI Limited v Gillies
[2012] NSWCA 333 – considered.
Sopov v Kane Constructions Pty Ltd [2007] VSCA 257, 20 VR 127; Queensland University of Technology v Project Constructions (Aust) Pty Ltd (in liq) [2002] QCA 224, 1 Qd R 259; Re Concrete Constructions Group Pty Ltd [1996] QCA 086; [1997] 1 Qd R 6; Algons Engineering Pty Limited v Abigroup Contractors Pty Ltd (1997) 14 BCL 215; McDonald v Dennys Lascelles Ltd [1933] 48 CLR 457 - referred to.
CKP Constructions Pty Ltd v Gabba Holdings Pty Ltd [2016] QDC 356 – not followed.
Aust Dig Contracts [142]
Contracts – Building, Engineering and Related Contracts – Remuneration – Recovery on Quantum Meruit – In General – Defendant’s counterclaim for defective works by plaintiff – Found that plaintiff did fail to perform work to required standard –- Held that termination by mutual abandonment removes a right by the Plaintiff to use or set-off against the counterclaim for damages for breach – Defendant’s counter-
claim allowed.
McDonald v Dennys Lascelles Ltd [1933] 48 CLR 457 – applied.
Cedar Meats (Aust) Pty Ltd v Five Star Lamb Pty Ltd [2014] VSCA 32 – distinguished.
Aquatec-Maxcon Pty Ltd v Minson Nacap Pty Ltd (2004) 8 VR 16 – considered.
Queensland University of Technology v Project Constructions (Aust) Pty Ltd (in liq) – considered.
Mann v Paterson Constructions Pty Ltd [2019] HCA 32, 267 CLR 560 – applied.
Aust Dig Contracts [271]
REPRESENTATION:
Counsel:
Plaintiff: M O'Farrell SC, E Stewart Defendant: B McTaggart SC
Solicitors:
Plaintiff: Butler McIntyre & Butler Defendant: Abetz Curtis Lawyers
| Judgment Number: | [2023] TASSC 22 |
| Number of paragraphs: | 131 |
Serial No 22/2023 File No…
Keep reading for free
Create a free CaseChat account to read Digga Excavations Tas Pty Ltd v Linear Capital Pty Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2023] TASSC 22
- Decision Date
CaseChat Overview and Summary
The primary legal issues before the court were whether the requirement for documentary evidence of moneys due and payable was a condition precedent to the defendant's obligation to pay progress certificates. Furthermore, the court had to decide if the defendant could rely on the plaintiff's failure to provide such evidence as a defence to the plaintiff's claim for payment. The court examined the contractual terms, the nature of the condition, and the consequences of its non-fulfilment in the context of the overall agreement.
The court held that the requirement for documentary evidence was indeed a condition precedent to the defendant's payment obligation. This condition was necessary for the defendant to ascertain the accuracy and validity of the amounts claimed by the plaintiff. Since the plaintiff did not provide the required documentary evidence, the defendant was not obligated to pay the certified amounts. The court found that the defendant could rely on this failure as a valid defence to the plaintiff's claim for payment. Consequently, the plaintiff's claim for the outstanding amounts was dismissed.
No further orders were made by the court as the primary issue of non-payment due to the condition precedent was upheld. The court's decision emphasised the importance of strict compliance with contractual conditions, particularly where such conditions are necessary for the performance of obligations under the contract. The outcome underscored that failure to meet a condition precedent can absolve the party obligated from their contractual duties.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.