Dickson Developments Precinct 1 Pty Ltd v Core Building Group Pty Ltd [2023] FCA 1473
File number(s): ACD 64 of 2023 Judgment of: JACKMAN J Date of judgment: 27 November 2023 Catchwords: ADMINISTRATIVE LAW – application for judicial review of adjudication determination in relation to construction contract – whether there was a reference date for the payment claim, being a jurisdictional criterion for the making of the determination – whether the adjudicator’s decision in relation to liquidated damages was so illogical or irrational as to constitute jurisdictional error – whether the determination was affected by jurisdictional error by reason of taking an irrelevant consideration into account, namely unsolicited submissions – whether there was jurisdictional error in the adjudicator’s decision to release retention monies – application dismissed
STATUTORY INTERPRETATION – construction of “properly made” in s 24(2)(e) of the Building and Construction Industry (Security of Payments) Act 2009 (ACT) (the Act) – construction of s 15(3)(b) of the Act – whether any distinction between the use of “is” in s 11 of the Act and “is to be” in cognate legislation
Legislation: Constitution ss 76, 77
Judiciary Act1903 (Cth) s 39B
Jurisdiction of Courts (Cross-Vesting) Act 1987 (Cth) s 9
Building and Construction Industry Security of Payment Act 1999 (NSW) ss 8, 9, 13, 22
Building and Construction Industry (Security of Payments) Act 2009 (ACT) ss 6, 10, 11, 15, 19, 20, 22, 23, 24, 29, 43
Jurisdiction of Courts (Cross-Vesting) Act 1993 (ACT) s 4
Supreme Court Act 1933 (ACT) ss 20, 34B
Cases cited: Ceerose Pty Ltd v A-Civil Aust Pty Ltd (No 2) [2023] NSWSC 345
Crosby v Kelly [2012] FCAFC 96; (2012) 203 FCR 451
Demex Pty Ltd v McNab Building Services Pty Ltd [2023] NSWCA 261
Downer Construction (Australia) Pty Ltd v Energy Australia [2007] NSWCA 49; (2007) 69 NSWLR 72
Iskra v MMIR Pty Limited [2019] NSWCA 126
John Holland Pty Ltd v Roads & Traffic Authority of New South Wales [2007] NSWCA 19
Northbuild Construction Pty Ltd v Central Interior Linings Pty Ltd [2011] QCA 22; [2012] 1 Qd R 525
Patterson Building Group Pty Ltd v Holroyd City Council [2013] NSWSC 1484
Probuild Constructions (Aust) Pty Ltd v Shade Systems Pty Ltd [2018] HCA 4; (2018) 264 CLR 1
Southern Han Breakfast Point Pty Ltd (in liq) v Lewence Construction Pty Ltd [2016] HCA 52; (2016) 260 CLR 340
Division: General Division Registry: Australian Capital Territory National Practice Area: Administrative and Constitutional Law and Human Rights Number of paragraphs: 57 Date of hearing: 20 November 2023 Counsel for the Applicant: Mr P Walker SC and Mr B Buckland Solicitor for the Applicant: HFW Australia Counsel for the First Respondent: Mr D L Cook SC and Mr D Weinberger Solicitor for the First Respondent: Crisp Law Counsel for the Second Respondent: The Second Respondent entered a submitting appearance ORDERS
ACD 64 of 2023 BETWEEN: DICKSON DEVELOPMENTS PRECINCT 1 PTY LTD
Applicant
AND: CORE…
Keep reading for free
Create a free CaseChat account to read Dickson Developments Precinct 1 Pty Ltd v Core Building Grou... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2023] FCA 1473
- Decision Date
CaseChat Overview and Summary
The court considered the jurisdictional nature of the adjudicator's role under the Act, particularly focusing on the distinction between the entitlement to a progress payment and the ascertainment of the exact amount of that payment. The court held that the ascertainment of the amount of a progress payment is not a precondition to the exercise of the adjudicator's jurisdiction. Furthermore, the court found that the application of s 15(3)(b) of the Act was a matter for the adjudicator to determine, not the court. The court also rejected the argument that the adjudicator's decision on liquidated damages was irrational or illogical, and it found no jurisdictional error in the adjudicator's consideration of unsolicited submissions or the release of retention monies.
The court concluded that the adjudicator's determination was within their jurisdiction and that the application for judicial review should be dismissed. The court ordered that the costs of the proceedings be paid by the applicant and that the money held by the court be released to the respondent, with the respondent being released from its undertaking not to enforce the determination.
The court's final orders were that the originating application be dismissed, the applicant pay the first respondent’s costs, and the money paid into court by the applicant be released to the respondent forthwith. Additionally, the respondent was released from its undertaking not to take steps to enforce the determination. These orders were made in accordance with Rule 39.32 of the Federal Court Rules 2011.
Orders
Orders of the court
1. The originating application be dismissed.
2. The applicant pay the first respondent’s costs of the proceedings.
3. In relation to the orders made on 3 November 2023:
(a) the amount of money held by the Court as a result of the applicant’s payment into Court pursuant to paragraph 1 of those orders be released to the first respondent forthwith; and
(b) the first respondent be released from its undertaking set out in paragraph 2 of those orders.
Note: Entry of orders is dealt with in Rule 39.32 of the Federal Court Rules 2011.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.