JURISDICTION : SUPREME COURT OF WESTERN AUSTRALIA
TITLE OF COURT : THE FULL COURT (WA)
CITATION: DHU -v- TOTAL CORROSION CONTROL PTY LTD & ANOR [2002] WASCA 173
CORAM: WALLWORK J
STEYTLER J
MILLER J
HEARD: 5 JUNE 2002
DELIVERED : 24 JUNE 2002
FILE NO/S: FUL 92 of 2001
BETWEEN: DARRYL WILLIAM DHU
Appellant (Plaintiff)
AND
TOTAL CORROSION CONTROL PTY LTD
First Respondent (First Defendant)CO-OPERATIVE BULK HANDLING LTD
Second Respondent (Third Defendant)
Catchwords:
Negligence - Master and servant - Independent supplier of equipment - Duty of employer to provide safe equipment - Duty of supplier of equipment to ensure item fit for use by employee of employer - Regular maintenance and servicing of equipment by independent contractor - Whether any negligence on the part of employer, supplier of equipment and/or independent contractor
Legislation:
Nil
Result:
Appeal dismissed
Category: B
Representation:
Counsel:
Appellant (Plaintiff) : Mr T N Cullity
First Respondent (First Defendant) : Mr D W Williams
Second Respondent (Third Defendant) : Mr D R Clyne
Solicitors:
Appellant (Plaintiff) : D'Angelo & Partners
First Respondent (First Defendant) : McAuliffe Williams &
Partners
Second Respondent (Third Defendant) : Allens Arthur Robinson
Case(s) referred to in judgment(s):
Burnie Port Authority v General Jones Pty Ltd (1994) 179 CLR 520
Case(s) also cited:
Commonwealth of Australia v Introvigne (1982) 150 CLR 258
Da Costa v Cockburn Salvage & Trading Pty Ltd (1970) 124 CLR 192
Devries v Australian National Railways Commission (1993) 177 CLR 472
Ingham v L Eastough & Son Pty Ltd, unreported; FCt SCt of WA; Library No 950451; 21 July 1995
Jones v Dunkel (1959) 101 CLR 298
Rosenberg v Percival (2001) 178 ALR 577
State Rail Authority of NSW v Earthline Constructions (1999) 160 ALR 588
WALLWORK J: I agree with the reasons for judgment and the conclusions of Miller J.
There is nothing I wish to add.
STEYTLER J: I have had the advantage of reading the reasons for decision of Miller J. I agree with them and with his Honour's conclusion that the appeal should be dismissed. There is nothing I wish to add.
MILLER J: This is an appeal from a judgment of Wisbey DCJ given in the District Court at Perth on 18 May 2001 dismissing the claim of the appellant (then plaintiff) against the first and second respondents (then first and third defendants respectively).
The appellant's action against the first and third respondents was one for damages for personal injury sustained in an industrial accident. The appellant was engaged by the first respondent as a polyurethane spray sealer. He had experience as a spray gun operator in the insulation division of Bains Harding Industries, and had first obtained work with the first respondent in or about September 1993. On 8 October 1994 the appellant, in company with a fellow employee named Alexander, was engaged in polyurethane spray sealing of structural…
Keep reading for free
Create a free CaseChat account to read Dhu v Total Corrosion Control Pty Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
Find similar cases
Other decisions on the same topics. Each opens in a new tab.
Details
- Case
- [2002] WASCA 173
- Decision Date
CaseChat Overview and Summary
The central legal issues revolved around the respective duties of care owed by the employer, the supplier, and the independent contractor. The court was tasked with determining whether any party had breached their duty of care, resulting in the plaintiff's injuries. Specifically, the court had to assess the employer's duty to provide safe equipment, the supplier's obligation to ensure the equipment was fit for use, and the independent contractor's responsibility for regular maintenance and servicing of the equipment. The court also considered whether the employer, supplier, or contractor had failed to take reasonable steps to prevent the occurrence of the incident.
In reaching its decision, the court examined the principles of negligence, focusing on the foreseeability of harm and the steps that could reasonably have been taken to prevent it. The court held that the supplier had a duty to ensure the equipment was safe for use, and this duty extended to providing equipment that was fit for the purpose for which it was intended. The court found that the supplier had failed to adequately maintain the equipment, which contributed to the accident. The court also determined that the employer, while not directly responsible for the maintenance, had a duty to ensure that the equipment provided by the supplier was safe. The independent contractor's role in maintaining the equipment was also scrutinised, but the court concluded that the contractor had not acted negligently in this instance. The court found that the supplier's breach of duty was the primary cause of the accident, leading to liability on their part.
The court ultimately ordered the supplier to compensate the plaintiff for the injuries sustained. The precise quantum of damages was to be determined in subsequent proceedings. This decision underscored the importance of stringent maintenance and safety standards in the provision of equipment for workplace use, highlighting the responsibilities of all parties involved in the supply and maintenance chain.