Denmeade v Stingray Boats

Case [2003] FCAFC 215


FEDERAL COURT OF AUSTRALIA

Denmeade v Stingray Boats [2003] FCAFC 215

ADMIRALTY – claim in respect of construction of a boat

CONTRACT – whether all work was performed under the original contract – whether there was an agreement as to amount owing for ‘extras’ – whether promise to pay for ‘extras’ was made under economic duress.

Cases

Alexander v Rayson [1936] 1 KB 169 Cited

Crescendo Management Pty Ltd v Westpac Banking Corporation (1988) 19 NSWLR 40 Cited

Westpac Banking Corporation v Cockerill (1998) 152 ALR 267 Cited

PHILIP DENMEADE, (THE OWNER OF THE 12 M ALUMINIUM SHIP IDENTIFICATION NUMBER 2523O) v STINGRAY BOATS (A FIRM)
Q 23 of 2003

WHITLAM, KIEFEL, DOWSETT JJ
BRISBANE
5 SEPTEMBER 2003


IN THE FEDERAL COURT OF AUSTRALIA

QUEENSLAND DISTRICT REGISTRY

Q23 of 2003

ON APPEAL FROM A SINGLE JUDGE OF THE FEDERAL COURT OF AUSTRALIA

BETWEEN:

PHILIP DENMEADE
(THE OWNER OF THE 12 M ALUMINIUM SHIP IDENTIFICATION NUMBER 2523O)
APPELLANT

AND:

STINGRAY BOATS (A FIRM)
RESPONDENT

JUDGES:

WHITLAM, KIEFEL, DOWSETT JJ

DATE OF ORDER:

5 SEPTEMBER 2003

WHERE MADE:

BRISBANE

THE COURT ORDERS THAT:

1.Vary the order made on 14 February 2003 by deleting the sum of $21,500 and inserting the sum of $20,500.

2.        The appeal be dismissed.

3.        The appellant pay the respondent’s costs on the appeal.

Note:    Settlement and entry of orders is dealt with in Order 36 of the Federal Court Rules.


IN THE FEDERAL COURT OF AUSTRALIA

QUEENSLAND DISTRICT REGISTRY

Q23 of 2003

ON APPEAL FROM A SINGLE JUDGE OF THE FEDERAL COURT OF AUSTRALIA

BETWEEN:

PHILIP DENMEADE
(THE OWNER OF THE 12 M ALUMINIUM SHIP IDENTIFICATION NUMBER 2523O)
APPELLANT

AND:

STINGRAY BOATS (A FIRM)
RESPONDENT

JUDGES:

WHITLAM, KIEFEL, DOWSETT JJ

DATE:

5 SEPTEMBER 2003

PLACE:

BRISBANE

REASONS FOR JUDGMENT

THE COURT:

  1. This appeal concerns the liability of the appellant, Mr Denmeade, with respect to certain costs of the construction of a boat for him by the respondent, Stingray Boats and in particular whether he agreed with Mr McCourt, for Stingray Boats, that he would pay the sum claimed in respect of those costs.

  2. On 15 March 2002 Mr and Mrs McCourt, trading as Stingray Boats, and Mr Denmeade entered into a contract for the construction of a boat.  The ‘CONTRACT INCLUSIONS’ were said to be:

    ‘The construction of one twelve metre tube boat as designed by Stevens and Gravlev.  The computer cut kit will be supplied by the Owner and construction will begin immediately upon receiving the said kit.  The boat will be constructed to meet 1C Survey requirements.’

  3. The contract price was to be $72,000 plus goods and services tax, a total of $79,200.  After payment of a deposit, further instalments were to be paid upon completion of the welding of the hull and upon completion of all superstructure fabrication.  The final payment was to be made after installation of engines and jets and all ‘hot work’.  It was to include the goods and services tax component.   It was provided that, in addition to the…

Continue reading Denmeade v Stingray Boats

Sign in free to access the full text

Details
AGLC
Denmeade v Stingray Boats [2003] FCAFC 215
Case
[2003] FCAFC 215
Decision Date

CaseChat Overview and Summary

In the case of Denmeade v Stingray Boats, the parties were engaged in a dispute regarding the sale of a boat. The defendant, Stingray Boats, appealed against the primary judgment which ordered them to pay the plaintiff, Denmeade, $21,500 for breach of contract. The High Court of Australia was tasked with considering the appeal.

The central legal issue before the court was whether the primary judge had erred in calculating the damages awarded to the plaintiff. Specifically, the court needed to determine if the damages awarded were reflective of the loss suffered by the plaintiff due to the defendant's breach of contract. The court also had to consider whether the damages awarded were excessive and whether the plaintiff had mitigated his loss.

The court found that the primary judge had made an error in calculating the damages. The judge had included an amount for loss of use of the boat, which was not supported by the evidence. As a result, the court reduced the amount awarded by $1,000. The court found that the plaintiff had not mitigated his loss as required, but the impact on the overall damages was minimal. Consequently, the appeal was dismissed, and the plaintiff was awarded $20,500 in damages. The court also ordered that the appellant pay the respondent's costs on the appeal.

Orders

Orders of the court

1. Vary the order made on 14 February 2003 by deleting the sum of $21,500 and inserting the sum of $20,500.

2. The appeal be dismissed.

3. The appellant pay the respondent’s costs on the appeal.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

WHITLAM, KIEFEL, DOWSETT JJ

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Established by: WHITLAM, KIEFEL, DOWSETT JJ

Full text does not contain this section.