SUPREME COURT OF THE AUSTRALIAN CAPITAL TERRITORY
Case Title: | Denham Constructions Project Company 810 Pty Ltd v Smithies & Anor; Denham Constructions Project Company 810 Pty Ltd v Risgalla & Anor |
Citation: | [2014] ACTSC 169 |
Hearing Date(s): | 1 July 2014 |
DecisionDate: | 11 July 2014 |
Before: | Mossop M |
Decision: | Applications dismissed. See [58] for further orders in relation to costs. |
Category: | Interlocutory application |
Catchwords: | BUILDING AND CONSTRUCTION – progress payments – filing arbitration certificate as judgment debt – security of costs – judicial review – whether proceedings should be stayed or dismissed for abuse of process or lack of utility |
Legislation Cited: | Building and Construction Industry (Security of Payment) Act2009 (ACT) ss 25-27, 38, 43 |
Cases Cited: | Birdon v Houben Marine (2011) 197 FCR 25 |
Texts Cited: | Spencer Bower and Handley, Res Judicata (LexisNexis Butterworths, 4th ed, 2009) |
Parties: | SC 217 of 2014: Denham Constructions Project Company 810 Pty Ltd (Plaintiff) Ted Smithies (First Defendant) Stowe Australia Pty Ltd (Second Defendant) SC 218 of 2014: Denham Constructions Project Company 810 Pty Ltd (Plaintiff) Rosemarie Risgalla (First Defendant) Stowe Australia Pty Ltd (Second Defendant) |
Representation: | Counsel: Mr M Condon SC & Mr G Blank (Plaintiff) Mr S Robertson (Second Defendant) |
| Solicitors: Crisp Legal (Plaintiff) Hicksons Lawyers (Second Defendant) | |
File Number(s): | SC 217 of 2014; SC 218 of 2014 |
Proceedings
There are two sets of proceedings currently on foot in which the plaintiff (Denham 810) seeks to quash decisions of an adjudicator under the Building and Construction Industry (Security of Payment) Act2009 (ACT) (SOP Act). Both adjudicators, the first defendants in each proceeding, have entered submitting appearances. The second defendant and beneficiary of the adjudicator’s decision in each of the proceedings (Stowe) seeks to have the proceedings either stayed or dismissed.
The adjudication certificate arising out of one of the adjudication decisions has been filed as a judgment of the Court under s 27 of the SOP Act. Section 27 provides:
27Filing of adjudication certificate as…
Keep reading for free
Create a free CaseChat account to read Denham Constructions Project Company 810 Pty Ltd v Smithies;... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2014] ACTSC 169
- Decision Date
CaseChat Overview and Summary
The primary legal issue before the court was whether the company's application for judicial review should be dismissed for being an abuse of process or lacking utility. The court considered the relevant principles of judicial review and whether the company had demonstrated a sufficient arguable case to support the granting of relief. The court also considered the appropriate remedy if the application was successful.
The court found that the company's application for judicial review was an abuse of process and lacked utility. The court found that the company had not demonstrated a sufficient arguable case to support the granting of relief. The court held that the company's application for judicial review was an abuse of process because it was an attempt to relitigate issues that had already been determined by the arbitral tribunal. The court held that the company's application for judicial review lacked utility because it was unlikely to achieve any useful purpose. The court dismissed the applications and ordered the company to pay the respondents' costs on an indemnity basis.
Orders
Orders of the court
Applications dismissed. See [58] for further orders in relation to costs.
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi