Court of Appeal
Supreme Court
New South Wales
Medium Neutral Citation: DCT Projects Pty Limited v Champion Homes Sales Pty Limited [2016] NSWCA 117 Hearing dates: 17 March 2016 Decision date: 20 May 2016 Before: Macfarlan JA at [1]
Gleeson JA at [2]
Sackville AJA at [193]Decision: (1) Appeal allowed in part;
(2) set aside Orders 1 and 2 made by the primary judge on 26 May 2015;
(3) in lieu thereof, order:
(a) judgment in favour of the plaintiff against the first defendant in the sum of $61,593.23;
(b) judgment in favour of the plaintiff against each of the second to ninth defendants in the sum of $6,843.69;
(c) in each case, the judgment is to take effect on 26 May 2015;(4) the parties are to agree on the calculation of interest on the above judgments at the rates prescribed by Practice Note SC Gen 16 from 2 July 2008 to 26 May 2015, and submit a draft consent order within 14 days of the date of this judgment. In the absence of agreement between the parties, the parties are to file and serve their respective calculations of interest on the judgments and short written submissions in support, not exceeding 2 pages, within 21 days of the date of this judgment. The Court will determine the amount of interest on the papers;
(5) appellants to pay 90% of the respondent’s costs of the appeal.Catchwords: CONTRACTS - building, engineering and related contracts - the contract – discharge, breach and defences to action for breach – where delay by the builder – whether repudiatory conduct– where purported termination by principal followed by purported termination by builder– onus on principal to prove work that could have been done – threats to suspend work made by builder in context of non-payment by principal – where builder suspended works for alleged breach by the principal – where principal did not serve a notice requiring the builder to remedy alleged breaches of contract – whether builder’s conduct evinced intention to no longer be bound or to fulfil contact in manner substantially inconsistent with its obligations
CONTRACTS - building, engineering and related contracts – claims for extensions of time – where no objection by principal when claims for extensions of time first made in closing submissions at trial – validity of claimed extensions by the builder and any notice of dispute by the principal under contractual regime for giving notice of claims– calculation of extensions by calendar or working days
CONTRACTS - building, engineering and related contracts – determination of contract sum/price – nature of deposit – whether fee for advice or part of contract sum – terms of contract
TRADE AND COMMERCE - Trade Practices Act 1974 (Cth) and related legislation – misleading and deceptive conduct – contract expressly excluded retaining walls and gave provisional sums for certain items including rock excavation – where builder aware of need for large retaining walls and did not inform principal prior to entry into contract…
Keep reading for free
Create a free CaseChat account to read DCT Projects Pty Ltd v Champion Homes Sales Pty Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2016] NSWCA 117
- Decision Date
CaseChat Overview and Summary
The Court of Appeal was required to determine whether the builder's suspension of works constituted repudiatory conduct, particularly in light of the principal's alleged non-payment and failure to serve a notice to remedy breaches. It also had to consider the validity of the builder's claims for extensions of time and the principal's objections thereto, as well as the nature of a deposit paid under the contract. Furthermore, the court needed to assess whether the builder engaged in misleading or deceptive conduct by failing to disclose its awareness of the need for significant retaining walls prior to the contract's formation, and whether the principal, represented by its own project manager, could recover damages on a "no contract" basis for this alleged conduct.
The court found that the builder's threats to suspend work were made in the context of non-payment by the principal, and that the builder's subsequent suspension of works was justified as a response to the principal's breaches. The court held that the onus was on the principal to prove the work that could have been done, and that the principal had not served a notice requiring the builder to remedy alleged breaches. Regarding extensions of time, the court noted that the principal had not objected when these claims were first made in closing submissions at trial, and it considered the contractual regime for claims and notices. The court also addressed the nature of the deposit, determining it was part of the contract sum. On the misleading and deceptive conduct claim, the court found that while the builder was aware of the need for retaining walls, the principal was represented by its own project manager, and no complaint was made contemporaneously with the need becoming apparent, thus limiting recovery.
The appeal was allowed in part, and the orders of the primary judge were set aside. The Court of Appeal entered judgment in favour of the plaintiff (DCT Projects Pty Ltd) against the first defendant (Champion Homes Sales Pty Ltd) for $61,593.23 and against the second to ninth defendants for $6,843.69 each, with these judgments taking effect on 26 May 2015. The parties were ordered to agree on the calculation of interest on these judgments, or otherwise submit their calculations and submissions for the court to determine. The appellants were ordered to pay 90% of the respondent's costs of the appeal.
Orders
Orders of the court
(1) Appeal allowed in part;
(2) set aside Orders 1 and 2 made by the primary judge on 26 May 2015;
(3) in lieu thereof, order:
(a) judgment in favour of the plaintiff against the first defendant in the sum of $61,593.23;
(b) judgment in favour of the plaintiff against each of the second to ninth defendants in the sum of $6,843.69;
(c) in each case, the judgment is to take effect on 26 May 2015;
(4) the parties are to agree on the calculation of interest on the above judgments at the rates prescribed by Practice Note SC Gen 16 from 2 July 2008 to 26 May 2015, and submit a draft consent order within 14 days of the date of this judgment. In the absence of agreement between the parties, the parties are to file and serve their respective calculations of interest on the judgments and short written submissions in support, not exceeding 2 pages, within 21 days of the date of this judgment. The Court will determine the amount of interest on the papers;
(5) appellants to pay 90% of the respondent’s costs of the appeal.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.