CS Energy Limited v GPS Power Pty Limited

Link copied
Case Copied 53 min read

SUPREME COURT OF QUEENSLAND

CITATION:

CS Energy Limited v GPS Power Pty Limited & Ors [2021] QCA 194

PARTIES:

CS ENERGY LIMITED
ACN 078 848 745
(appellant)
v
GPS POWER PTY LIMITED
ACN 009 103 422
(first respondent)
GPS ENERGY PTY LIMITED
ACN 063 207 456
(second respondent)
SUNSHINE STATE POWER B.V.
ARBN 062 295 425
(third respondent)
SUNSHINE STATE POWER (NO. 2) B.V.
ARBN 063 382 829
(fourth respondent)
SOUTHERN CROSS GPS PTY LTD
ACN 063 779 028
(fifth respondent)
RYOWA II GPS PTY LIMITED
ACN 063 780 058
(sixth respondent)
YKK GPS (QUEENSLAND) PTY LIMITED
ACN 062 905 275
(seventh respondent)

FILE NO/S:

Appeal No 5746 of 2020
Appeal No 5749 of 2020
SC No 761 of 2018
SC No 13392 of 2017

DIVISION:

Court of Appeal

PROCEEDING:

General Civil Appeal

ORIGINATING COURT:

Supreme Court at Brisbane – [2018] QSC 294 (Jackson J); [2020] QSC 93 (Jackson J)

DELIVERED ON:

7 September 2021

DELIVERED AT:

Brisbane

HEARING DATE:

11 September 2020

JUDGES:

Fraser, McMurdo and Mullins JJA

ORDER:

Appeals dismissed with costs.

CATCHWORDS:

CONTRACTS – GENERAL CONTRACTUAL PRINCIPLES – CONSTRUCTION AND INTERPRETATION OF CONTRACTS – INTERPRETATION OF MISCELLANEOUS CONTRACTS AND OTHER MATTERS – where the appellant and the respondents are parties to a long term contract concerning the supply and sale of electricity from a power station – where operative provisions of the contract contain a defined term “Station Annual Forecast” – where the contract permits a defined term to bear a meaning other than its defined meaning, if the context otherwise requires – where the defined meaning relies on another clause of the contract which prescribes a list of information to be included in the Station Annual Forecast – whether the use of the defined term incorporates only that part of the list information which is necessary for the purpose of the particular clause – where the primary judge approached the construction of the defined term in the operative provisions by considering the context and purpose of each provision and concluded that the reference to the Station Annual Forecast did not extend to part of the information included in the defined term – whether the primary judge erred in failing to apply the orthodox approach of inserting the full meaning given to the defined term into the operative clause of the contract

CONTRACTS – GENERAL CONTRACTUAL PRINCIPLES – CONSTRUCTION AND INTERPRETATION OF CONTRACTS – INTERPRETATION OF MISCELLANEOUS CONTRACTS AND OTHER MATTERS – where the appellant and the respondents are parties to a long term contract concerning the supply and sale of electricity from a power station – where the appellant sought a declaration that Station Annual Forecast for the purpose of the relevant clause includes the upper and lower estimates – where the respondents conceded before the primary judge that the reference to Station Annual Forecast in a related clause includes the upper and lower estimates – where the primary judge did not refer to the concession in the part of the reasons that dealt with the…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read CS Energy Limited v GPS Power Pty Limited and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2021] QCA 194
Decision Date

CaseChat Overview and Summary

In the case of CS Energy Limited v GPS Power Pty Limited, the appellant, CS Energy Limited, appealed against certain orders made by the primary judge in relation to two proceedings. The primary dispute involved the interpretation of several terms within a long-term contract concerning the supply and sale of electricity from the Gladstone Power Station, owned by the respondents, GPS Power Pty Limited. The main issues before the court were whether the primary judge had correctly interpreted the defined term “Station Annual Forecast” and whether the primary judge erred in not considering a concession made by the respondents regarding the meaning of this term in a specific clause.

The court was required to determine whether the primary judge correctly interpreted the contract by applying the orthodox approach of inserting the full meaning of the defined term into the operative clause. Additionally, the court needed to assess whether the primary judge erred by not referring to a concession made by the respondents, which would only be relevant if it made a difference to the construction of the clause. The court also needed to decide whether the primary judge was correct in not making certain declarations sought by the appellant regarding the meaning of terms such as “coal stockpile forecast” and “stockpile level forecast”.

The court held that the primary judge did not err in his interpretation of the contract. The primary judge had appropriately considered the context and purpose of each provision and concluded that the reference to the Station Annual Forecast did not extend to part of the information included in the defined term. The court found that the failure of the primary judge to refer to the respondents’ concession did not make a difference to the construction of the relevant clause. Consequently, the primary judge's decision not to make the declarations sought by the appellant was upheld due to the lack of evidence on relevant matters which may affect the utility of such declarations.

The appeals were dismissed with costs.

Orders

Orders of the court

Appeals dismissed with costs.

Background

Background to the litigation

The appellant appeals against only some of the orders made in both proceedings. Grounds 1 to 3 are identical in both appeals. The notice of appeal in relation to the 2018 reasons also includes grounds 4 to 6. The respondents have filed a notice of contention in the appeal in respect of the decision to dismiss paragraph 5A of the amended originating application in proceeding 761 of 2018 and contend that the dismissal should be affirmed on a ground other than a ground relied on by the primary judge.Background The respondents are the owners of the Gladstone Power Station which is referred to in the IPPA as “GPS”. GPS is Queensland’s largest power station. In 1982, it became the source of electricity for the Boyne Aluminium Smelter (which is referred to in the IPPA as the “Smelter”). The Smelter is Queensland’s largest individual user of electricity. The Smelter is owned by “BSL” which means Boyne Smelters Limited. Since the end of 1998, electricity for the Smelter has been obtained from the National Electricity Market (NEM). The appellant is a Queensland Government owned electricity provider and the “Nominated Generator” for GPS under the “Rules” governing the NEM. Rules is defined in the annex to mean the National Electricity Rules under part 7 of the “National Electricity Law”, as amended from time to time in accordance with that part. National Electricity Law is also defined in the annex and means the National Electricity (Queensland) Law as defined in the Electricity – National Scheme (Queensland) Act 1997 (Qld). The history and the manner of operation of GPS are described in general terms at [3]-[16] of the 2018 reasons. The operational limits of, and constraints on, the capacity of GPS are described in general terms at [17]-[19] of the 2018 reasons. They include the specification and configuration of the six “Units” of GPS, the constraints of the coal handling and storage facilities, the availability, suitability and reliability of supplies of coal and the scheduling of trains on the rail network. A Unit is defined in the annex to mean “any one of the six steam boiler/turbine/alternator units comprised within GPS”. The acquisition of GPS by the Participants in March 1994, the entry by Queensland Electricity Commission (QEC) and the Participants into the original IPPA (which the primary judge sometimes referred to as the 1994 IPPA) and other contracts and the importance of the uninterrupted supply of electricity to the operation of the Smelter are referred to at [21]-[28] of the 2018 reasons. The primary judge summarised the operation of the NEM and the resulting amendments to produce the 2009 IPPA: see [47]-[57] of the 2018 reasons. The making of significant amendments to the IPPA in 2009 and further amendments in 2011 are outlined in [30]-[32] of the 2018 reasons. The primary judge noted (at [59] of the 2018 reasons) that the changes made in the 2009 IPPA included new clauses 5A, 6.3, 23.4A, 23.4B and 23.4C.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.