CORRADINI & ANOR v O’BRIEN LOVRINOV CRAFTER PTY LTD
[2000] SASC 224
Full Court: Doyle CJ, Debelle and Nyland JJ
DOYLE CJ. This appeal arises from a dispute of a not uncommon kind. A firm agreed to design and supervise extensive renovations to an existing house, the client being the owner of the house. At an early stage the cost of the work was estimated at about $200,000. The work finished up costing about $375,000. The total cost is unclear, because the parties are at issue as to amounts paid, including amounts paid by the defendants directly to some suppliers. Be that as it may, the cost of the work has substantially exceeded the original estimate. When the firm sued for the balance that it claimed was owing, the owners defended and counterclaimed mainly on the basis that, part way through the work, there was an agreement that the work would be completed at a cost not exceeding a stated sum, that that sum had been paid, and that no further amount was payable by the owners. The owners also claimed that the contract was unenforceable by the firm for failure to comply with certain statutory requirements applicable to the contract.
It is now necessary to turn to the matter in greater detail.
Background
The plaintiff is a company carrying on business as builder and architect. I will refer to it as “the firm”. Most of the relevant dealings on behalf of the plaintiff were conducted by Mr Lovrinov, a qualified architect.
The firm issued proceedings in the District Court against Mr and Mrs Corradini (“the Corradinis”). The claim was for payment for work done by the firm in connection with alterations and additions (“the renovations”) carried out on the Corradinis’ house. The work was carried out between about March 1994 and early 1995.
The claim was for a balance alleged to be owing to the firm. The balance allowed for payments already made by the Corradinis to the firm. The claim was for the balance of an amount with three components. First, a fixed fee for preparing working drawings of the work, needed to obtain Council approval and, presumably, for the purposes of the renovations themselves. Secondly, a fee for supervising the work, which I gather comprised obtaining quotations, advising on them, advising the Corradinis generally on the work, and supervising the work. It is convenient to refer to this aspect of the work as “project management”. I do so simply for convenience, and not using that expression in any technical sense. This fee was calculated at 10 per cent of the value of the work, although that statement requires some modification as will appear later. The third component of the balance was the amount of payments made by the firm to subcontractors and suppliers who worked on the renovations and supplied materials for the renovations.
The amount claimed was $102,993. I ignore questions of interest.
The firm sued on a contract of engagement contained in a letter of…
Continue reading Corradini v O'Brien Lovrinov Crafter P/L No. Scgrg-99-1662
Sign in free to access the full text
- AGLC
- Corradini v O'Brien Lovrinov Crafter P/L No. Scgrg-99-1662 [2000] SASC 224
- Case
- [2000] SASC 224
- Decision Date
CaseChat Overview and Summary
The Court found that a contract was indeed entered into on 16 March 1994, which included terms for the preparation of working drawings and a fee for project management based on a percentage of the value of the project. The Court rejected the Corradinis' argument that the contract was limited to architectural services and that a subsequent agreement for a fixed-price contract had been reached. The Court held that the contract was varied to include the firm making payments to contractors and suppliers, but there was no evidence to support the Corradinis' claim of a fixed-price agreement for the completion of the renovations.
Regarding the statutory requirements under the Builders Licensing Act 1986 (SA), the Court concluded that the failure to comply with these requirements did not render the contract unenforceable. The Court found that the Act provided detailed penalties and remedies for breaches, and that treating the contract as unenforceable would not advance the legislative purpose. The Court further held that considerations of public policy did not necessitate the contract's unenforceability. The Court allowed the appeal only to vary the answer to the second question, clarifying the terms of the contract and the circumstances under which the fee and reimbursement were payable.
The Court dismissed the appeal and directed that the issues of the amount payable to the firm and the counterclaim for defective work be referred to arbitration. The Court emphasised that the firm's claim for reimbursement depended on proving that the Corradinis had authorised each payment, and that the contract did not entitle the firm to recover whatever it had expended on the renovations. The Court's decision highlighted the importance of clear contractual agreements and the potential consequences of proceeding with work without such agreements in place.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Established by: DOYLE CJ,
Full text does not contain this section.