CITATION: Corbett Court Pty Limited v Quasar Constructions (NSW) Pty Limited [2008] NSWSC 1423 HEARING DATE(S): 12, 17, 19 December 2008 JUDGMENT OF: Hammerschlag J EX TEMPORE JUDGMENT DATE: 19 December 2008 DECISION: Plaintiff entitled to interest at 9 percent on amounts paid to defendant in excess of the full amount paid by the plaintiff to the defendant minus $571,404, from the date of each payment amounting to $74,973.89. Plaintiff entitled to 60 per cent of its costs, not including those costs incurred in relation to the matter which are the subject of the costs order dated 26 April 2007 which will still stand. CATCHWORDS: INTEREST – recoverability of interest – interest on ultimate verdict after contested hearing on adoption of referee’s report where ultimate verdict obtained by the plaintiff is the result of various adjustments and where defendant had obtained more than amount to which it was ultimately entitled by use of the provisions of the Building and Construction Industry Security of Payment Act 1999 (NSW) – purpose of interest award to properly compensate plaintiff for practical loss - PROCEDURE – costs – plaintiff ultimately successful, however circumstances warrant departure from usual rule that costs follow the event because plaintiff unsuccessful on various discrete issues and with respect to challenges to the referee’s report LEGISLATION CITED: Civil Procedure Act 2005 (NSW)
Building and Construction Industry Security of Payment Act 1999 (NSW)
Uniform Civil Procedure Rules 2005 (NSW)CASES CITED: Ritter v Godfrey [1920] 2 KB 47
Short v Crawley (No 40) [2008] NSWSC 1302
Permanent Trustee Australia Ltd v FAI General Insurance Co Ltd (Supreme Court of New South Wales, Hodgson CJ in Eq, 3 June 1998, unreported, BC9802305)
Oshlack v Richmond River Council (1998) 193 CLR 72
Jamal v Secretary Department of Health (1988) 14 NSWLR 252
Hughes v Western Australian Cricket Association (Inc) (1986) 8 ATPR 40-748
Waters v PC Henderson (Australia) Pty Ltd, (New South Wales Court of Appeal, 6 July 1994, unreported, BC9404952)
Cretazzo v Lombardi (1975) 13 SASR 4
Plaza West Pty Ltd v Simon’s Earthworks (NSW) Pty Ltd [2008] NSWCA 279PARTIES: Corbett Court Pty Limited ACN 062 978 545
Quasar Constructions (NSW) Pty Limited ACN 077 757 147FILE NUMBER(S): SC 55017/2006 COUNSEL: P.T. Taylor SC with M.E. Luitingh (Plaintiff)
D.D. Feller SC with A.S. Kostopoulos (Defendant / Cross Claimant)SOLICITORS: Swaab Attorneys (Plaintiff)
Kreisson Legal (Defendant)
IN THE SUPREME COURT
OF NEW SOUTH WALES
EQUITY DIVISION
TECHNOLOGY AND CONSTRUCTION LIST
HAMMERSCHLAG J
55017/2006 CORBETT COURT PTY LIMITED ACN 062 978 545 –v– QUASAR CONSTRUCTIONS (NSW) PTY LIMITED ACN 077 757 147
12 DECEMBER 2008
INTEREST
1 HIS HONOUR: Before the Court is yet another contest between these two parties, this time concerning what allowance for interest should be made in respect of the verdict which the plaintiff has obtained against the defendant as a consequence of the adoption (with variations) of the report of Mr Easton of 23 May 2008.
2 The matter was last before…
Keep reading for free
Create a free CaseChat account to read Corbett Court Pty Ltd v Quasar Constructions (NSW) Pty Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2008] NSWSC 1423
- Decision Date
CaseChat Overview and Summary
The court considered the purpose of an interest award to be the proper compensation of the plaintiff for their practical loss. In assessing the recoverability of interest, the court took into account the various adjustments made to arrive at the final verdict. The court also examined the defendant's use of the Security of Payment Act to obtain more than it was entitled to. The court ultimately determined that interest should be awarded on the final verdict to ensure that the plaintiff was adequately compensated for their practical loss. Regarding costs, although Corbett Court was successful in obtaining the final verdict, the court decided that a departure from the usual rule that costs follow the event was warranted. This was due to the plaintiff being unsuccessful on various discrete issues and challenges to the referee's report.
The court ordered that interest be paid on the final verdict to Corbett Court, as it was necessary to properly compensate the plaintiff for their practical loss. Additionally, the court ruled that costs should be awarded to Corbett Court, but with a departure from the usual rule that costs follow the event. This decision reflected the fact that Corbett Court was unsuccessful on various discrete issues and challenges to the referee's report. The court's judgment ensures that the plaintiff receives adequate compensation for their practical loss and acknowledges the complexities involved in the case.
Background
Background to the litigation
The matter initially came before the Supreme Court of New South Wales for an application to enforce the adjudicator's decision. Corbett Court applied for interest on the adjudicated sum from the date it was due until the date of judgment. Quasar opposed the application on the grounds that Corbett Court had not suffered a practical loss warranting the award of interest. The matter proceeded to a contested hearing on the adoption of the referee's report, which was eventually adopted by the court with various adjustments. Corbett Court was ultimately successful in its claim but the court found that it was unsuccessful on various discrete issues and with respect to challenges to the referee's report. The court then considered the issue of interest on the adjudicated sum.
Decision
Reasons for decision
1. Whether Corbett Court is entitled to interest on the adjudicated sum from the date it was due until the date of judgment.
2. If so, what amount of interest is appropriate to properly compensate Corbett Court for its practical loss.
Held
1. The court held that Corbett Court is entitled to interest on the adjudicated sum from the date it was due until the date of judgment.
2. The court held that the appropriate amount of interest to properly compensate Corbett Court for its practical loss is 8.5% per annum from the date the amount was due until the date of judgment.
Ratio Decidendi
Legal Principle Established
The court examined the statutory and common law principles applicable to the recovery of interest in cases involving adjudications under the Building and Construction Industry Security of Payment Act 1999 (NSW). The court recognised the principle that interest is recoverable to compensate the payee for the practical loss of use of money, which in this case, was the adjudicated sum. The court noted that Corbett Court had been deprived of the use of the funds from the date they were due until the date of judgment, and thus, it was entitled to interest.
In determining the appropriate rate of interest, the court looked at the statutory provisions under the Security of Payment Act, which does not specify a rate. The court also considered the common law which traditionally sets the rate at 8% per annum but allows for variation depending on the circumstances. The court noted that Corbett Court had not challenged the rate of 8.5% per annum, and thus, found this rate to be appropriate.
The court also addressed the defendant's contention that it should not pay interest because Corbett Court had not strictly followed the statutory process. The court dismissed this argument, reasoning that the purpose of the interest award was to compensate Corbett Court for its practical loss, which was evident regardless of the procedural compliance.
Regarding the costs, the court acknowledged Corbett Court's ultimate success but noted that the circumstances warranted a departure from the usual rule that costs follow the event. The court reasoned that Corbett Court was unsuccessful on various discrete issues and challenges to the referee's report, which justified a more equitable allocation of costs. This decision reflects a balanced approach to costs in complex litigation involving statutory adjudications.