SUPREME COURT OF QUEENSLAND
File No S10993 of 2001
BETWEEN:
Cook’s Construction Pty Ltd
Applicant
AND:
Stork ICM Australia Pty Ltd
Respondent
MOYNIHAN J – REASONS FOR JUDGMENT
CITATION:
Cook’s Construction Pty Ltd v Stork ICM Australia Pty Ltd [2004] QSC 066
PARTIES:
Stork ICM Australia Pty Ltd
Applicant
v
Cook’s Construction Pty Ltd
Respondent
FILE NO/S:
SC 10993 of 2001
DIVISION:
Trial Division
PROCEEDING:
Application
ORIGINATING COURT:
Supreme Court of Queensland
DELIVERED ON:
16 March 2004
DELIVERED AT:
Brisbane
HEARING DATE:
18 November 2002
JUDGE:
Moynihan J
ORDER:
1. The Statement of Claim is struck out
CATCHWORDS:
Cases Cited
Adamson v Williams McMurdo P Thomas JA Mullins J (unreported) [2001] QCA 38 16/02/2001 (00/9510)
Commercial Bank of Australia Ltd v Amadio (1983) 151 CLR 447
Crawley v Roley; Tanner v Roley White J (unreported) [2000] QSC 139 16/05/2000 (99/8417, 99/8418)
Estate of Audrey Urbancic Muir J (unreported) [2000] QSC 170 09/06/2000(99/5996)
Goldtaper Pty Ltd v Berela Pty Ltd White J (unreported) [2000] QSC 187 003/02/2000
Hurley v McDonald’s Australia Ltd [1999] FCA 1728
Louth v Diprose (1992) 175 CLR 621
Multiplex Constructions Pty Ltd v Rapid Contracting Pty Ltd (In Liquidation) Shepherdson J (unreported) [1998] QCA 10856/98
Pavey & Mathews Pty Ltd v Paul (1986) 162 CLR 221
Robinson v Laws de Jersey CJ Williams JA Mackenzie J (unreported) [2001] QCA 122 06/04/01 (00/4177)
Smit v Chan Mackenzie J (unreported) [2001] QSC 70 16/03/2001 (95/1233)
Stork Wescon Australia Pty Ltd v Morton Engineering Company Pty Ltd [2000] 2 Qd R 148 at 152 [14]
Legislation Cited
Land Act 1994 (Qld)
Queensland Building Services Authority Act 1991 (Qld)
Trade Practices Act 1974 (Cth)
Uniform Civil Procedure Rules 1999 (Qld)
COUNSEL:
K Downes for the applicant
J Digby QC with McGowan for the respondent
SOLICITORS:
Clarke & Kann for the applicant
McCullough Robertson for the respondent
Introduction
This is an application in an action arising out of the defendant having contracted to construct a plant to produce ammonium nitrate for Queensland Nitrates Pty Ltd at Moura in Queensland (the project). The defendant subcontracted aspects of the work to the plaintiff which now sues it for $1,654,510 for work allegedly done under the subcontract.
The defendant brings this application for:-
(a) summary judgment on a number of claims;
(b) summary judgment or alternatively striking out of additional claims;
(c) striking out of more claims;
(d) striking out or alternatively for particulars in respect of claims.
The plaintiff’s claim is evolving. The proceedings were instituted in the Supreme Court of Victoria on 5 March 2001. There was a response to the defendant’s request for further and better particulars of the original statement of claim on 5 July 2001. An amended statement of claim was delivered on 24 July 2001 and on 27 July the matter was remitted to this Court. A defence and counter-claim was filed on 17 August 2001 and a reply on 4 September 2001.
Further editions of the statement of claim were filed on 21 February and 26…
Keep reading for free
Create a free CaseChat account to read Cook's Construction Pty Ltd v Stork ICM Australia Pty Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2004] QSC 66
- Decision Date
CaseChat Overview and Summary
The court examined whether a collateral contract existed, and if so, whether it was binding. The analysis involved determining whether there was a clear and unequivocal promise made by Stork ICM Australia Pty Ltd, and if Cook's Construction Pty Ltd had relied on that promise to their detriment. The court also considered the terms of the primary contract and whether any collateral promises were intended to be part of that agreement. The reasoning provided by the court indicated that the plaintiff failed to establish the existence of a collateral contract as a matter of law. The court found that there was no clear and unequivocal promise that could be relied upon by the plaintiff. Additionally, the court held that the terms of the primary contract did not support the inference that any additional obligations were intended to be part of the agreement.
As a result, the court determined that the plaintiff's claim was not substantiated and accordingly struck out the Statement of Claim in its entirety. This decision highlights the importance of clear and unambiguous communication in the formation of contracts and the stringent requirements for establishing the existence of a collateral contract.
Orders
Orders of the court
1. The Statement of Claim is struck out
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.