[2014] FWC 1720 |
FAIR WORK COMMISSION |
DECISION |
Fair Work Act 2009
s.739 - Application to deal with a dispute
Construction, Forestry, Mining and Energy Union
v
Form 700 Pty Ltd
(C2014/2669)
AndHansen Yuncken Pty Ltd
v
Construction, Forestry, Mining and Energy Union
(C2014/2907)
AndLeighton Contractors Pty Ltd
v
Construction, Forestry, Mining and Energy Union
(C2014/2908)
Building, metal and civil construction industries
DEPUTY PRESIDENT BARTEL | ADELAIDE, 12 MARCH 2014 |
S.739 Dispute - Interpretation of Inclement Weather Provisions
[1] Hansen Yuncken Pty Ltd (HY) and Leighton Contractors Pty Ltd (LC) are in a joint venture to design and construct the new Royal Adelaide Hospital (NRAH) under contract with the South Australian Government. Both HY and LC employ workers in their own right at the NRAH site. A number of contractors are engaged by the joint venture to undertake work at the site, including Form 700 Pty Ltd (Form 700).
[2] On 15 January 2014, the Construction, Forestry, Mining and Energy Union (CFMEU) filed an application pursuant to s.739 of the Fair Work Act 2009 (the Act). A dispute had arisen with Form 700 concerning the interpretation of the inclement weather provisions of the Form 700 Pty Ltd/CFMEU Enterprise Agreement 2011. On 22 January 2014 this agreement was replaced with the Form 700/CFMEU Enterprise Agreement 2013 (the Form 700 Agreement). The inclement weather clauses are the same in both instruments.
[3] On 4 February 2014, HY and LC each filed applications pursuant to s.739 of the Act in relation to a dispute with the CFMEU over the interpretation of the inclement weather provisions of the Hansen Yuncken Pty Ltd Enterprise Agreement 2012 (the HY Agreement) and the Leighton Contractors Pty Limited and CFMEU South Australia Enterprise Agreement 2011-2015 (the LC Agreement), respectively. These two applications will be referred to collectively as “the employer applications”.
[4] The Form 700 Agreement, the HY Agreement and the LC Agreement will be referred to collectively in this decision as “the Agreements”.
[5] The case proceeded to a hearing on 17 February 2014 on the basis that the Fair Work Commission (the Commission) would interpret the respective inclement weather provisions of the Agreements. The applications were heard concurrently because of the similarity in the dispute applications and the relevant clauses in the respective enterprise agreements and because all relate to afternoon shift workers engaged at the NRAH project site. Mr David Putland, of the Master Builders Association of South Australia Inc (the MBA), represented the three employers and Mr Stuart Maxwell appeared for the CFMEU with Ms Liz Dooley, also of the CFMEU.
[6] The issue that divides the parties in each of the applications before the Commission is, in short, under what circumstances the afternoon shift workers can leave the NRAH site when the temperature reaches 37 degrees.
The circumstances giving rise to the disputes/the relief sought
[7] The CFMEU dispute application concerns a situation that arose on 13 and 14 January 2014. At the commencement of shift at 4.00pm the outside temperature was…
Keep reading for free
Create a free CaseChat account to read Construction, Forestry, Mining and Energy Union v Form 700 P... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2014] FWC 1720
- Decision Date
CaseChat Overview and Summary
The legal issues at hand primarily revolved around the interpretation of specific clauses within the enterprise agreement concerning inclement weather. The key issue was whether these clauses implied a right to compensation or time off when weather conditions made it unsafe or impracticable to work. The Commission had to determine whether the language used in the agreement was sufficiently clear to impose such obligations on the employer or if it merely provided a guideline without any mandatory effect.
In its decision, the Commission closely examined the wording of the relevant clauses and considered the broader context of the enterprise agreement. It concluded that the language used did not unequivocally mandate compensation or time off for employees in cases of inclement weather. Instead, the provisions were seen as indicating a guideline for the employer to follow in determining appropriate action in such situations, rather than imposing a strict obligation. The Commission held that the agreement did not clearly and unambiguously require the employer to provide compensation or time off when work was disrupted by weather conditions. This interpretation was based on the absence of explicit language that would impose such a duty.
Orders
Orders of the court
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi