City of Mitcham v Hutchison 3G Australia Ltd

Link copied
Case Copied 69 min read

SUPREME COURT OF SOUTH AUSTRALIA

(Civil: Case Stated)

CITY OF MITCHAM v HUTCHISON 3G AUSTRALIA LTD & ORS

Judgment of The Full Court

(The Honourable Justice Perry, The Honourable Justice Bleby and The Honourable Justice Gray)

11 March 2005

ENVIRONMENT AND PLANNING - BUILDING CONTROL

On a special case stated, consideration by the Full Court of questions relating to the erection by a telecommunications carrier, Hutchison 3G Australia Pty Ltd ("Hutchison") of telecommunication facilities known as downlink sites within a local council area - the council issued enforcement notices pursuant to s 35 of the Development Act 1993, claiming that development approval under that Act was required - the facilities were erected upon stobie poles which were also utilised by ETSA, a supplier of electricity licensed under the Electricity Act 1996, as part of its distribution network - in several instances ETSA replaced existing stobie poles with larger poles in order to accommodate the extra load resulting from the installation of the telecommunication facilities - held (by a majority, Bleby J dissenting) that each of the relevant stobie poles was a 'tower' within the meaning of Schedule 3 of the Telecommunications Act 1997 (Cth); that they did not constitute low-impact facilities within the meaning of the Telecommunications (Low-Impact Facilities) Determination 1997; and that the erection of the stobie poles and the installation of the telecommunication facilities constituted development for which approval was required under the Development Act - case stated answered accordingly.

Development Act 1993 (SA) s 33, s 34, s 37 and s 49A; Development Regulations 1993 Schedule 14A; Telecommunications Act 1997 (Cth) Part 3, Div 3 and s 484; Commonwealth Constitution s 109; Judiciary Act 1903 (Cth) s 78B; Electricity Act 1996 (SA) s 4(1), Part 3, s 23(1); Electricity Transmission Code, 1 July 2003 Clause 12.1 and clause 13; Acts Interpretation Act 1901 (Cth) s 15AB, referred to.
Hurstville City Council v Hutchison 3G Australia Pty Ltd (2003) 127 LGERA 95; Telstra Corporation Ltd v City of Onkaparinga [2001] EDLR 263, 13 July 2001, considered.

CITY OF MITCHAM v HUTCHISON 3G AUSTRALIA LTD & ORS
[2005] SASC 78

Full Court:  Perry, Bleby and Gray JJ

  1. PERRY J. This is a special Case Stated, with the concurrence of the parties, for hearing and determination by the Full Court.[1]

    [1]   SCR r 72.01.

  2. The plaintiff, the City of Mitcham (“the Council”), is the relevant authority pursuant to s 34 of the Development Act 1993 (“the Development Act”) in respect of development undertaken within the area of the Council.

  3. The first defendant, Hutchison 3G Australia Pty Ltd (“Hutchison”) is a telecommunications carrier licensed pursuant to the provisions of Part 3, Division 3 of the Telecommunications Act1997 (Cth) (“the Telco Act”).

  4. The remaining defendants are a group of companies: CKI Utilities Development Ltd, HEI Utilities Development Ltd, CKI Utilities Holdings Ltd, HEI Utilities Holdings Ltd and CKI/HEI Utilities Distribution Ltd. Those companies together trade as ETSA Utilities. I will refer to them collectively as “ETSA”.

  5. In the proceedings,…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read City of Mitcham v Hutchison 3G Australia Ltd and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details

Case
[2005] SASC 78
Decision Date

CaseChat Overview and Summary

The case of City of Mitcham v Hutchison 3G Australia Ltd involved a dispute between the City of Mitcham and Hutchison 3G Australia Pty Ltd over the installation of telecommunications facilities by Hutchison within the council area. The council issued enforcement notices under the Development Act 1993, claiming that the installation of these facilities required development approval. Hutchison argued that the installations were low-impact facilities exempt from the need for such approval. The matter was brought before the Full Court of the Federal Court of Australia, which was tasked with answering several questions on special case stated by the Environment Resources and Development Court.

The central legal issues in the case revolved around the interpretation of the Telecommunications Act 1997 (Cth) and the Telecommunications (Low-Impact Facilities) Determination 1997. Specifically, the court needed to determine whether the telecommunication facilities erected by Hutchison on stobie poles were "towers" as defined in Schedule 3 of the Telecommunications Act, and whether they constituted "low-impact facilities" exempt from development approval under the Determination. If the facilities were not low-impact, the court had to decide whether their installation constituted development requiring approval under the Development Act 1993.

The court, by a majority, concluded that the stobie poles were indeed "towers" within the meaning of Schedule 3 of the Telecommunications Act and that the facilities did not qualify as low-impact facilities under the Determination. Therefore, the erection of these poles and the installation of the telecommunication facilities constituted development that required approval under the Development Act. Justice Bleby dissented from this majority decision, holding a different view on the interpretation of the relevant legislation.

Given the majority decision, the court answered the questions posed in the case accordingly. The matter of whether the City of Mitcham was entitled to a declaration regarding the need for development approval was left to the trial judge, as it depended on facts that might emerge during the trial. The final orders of the court would thus await the outcome of the trial proceedings.

Orders

Orders of the court

Background

Background to the litigation

While that procedure did not entirely eliminate the possibility of an element of instability developing with respect to the facts upon which the Case Stated was to be answered, the reasoning by which I have reached my conclusions does not turn in any respect upon facts other than those which appear in the Case Stated and which are, therefore, agreed facts.Factual Background The following account of the factual background is extracted from the Case Stated. During 2002 and early 2003, Hutchison established five downlink sites as part of its mobile telecommunications network, at five locations. For convenience, they may be described as the Colonel Light Gardens site, the Bellevue Heights site, the Torrens Park site, the Kingswood site and the Clarence Gardens site. All five sites are within the area of the Council, and are within residential areas within the meaning of the Telecommunications (Low-Impact Facilities) Determination 1997 (“the Determination”), to which I will in due course refer. Hutchison gave to the Council by letter, notice of its intention to establish each site. Each of the letters is in substantially the same terms, differing only as to the particulars of the address at which the facility is to be installed, and as to technical data relating to the proposed facility, including drawings annexed to each letter. In each letter, Hutchison state:“The proposed facility falls within the ambit of section 484 of the Telecommunications Act 1997 (Act), and is classified as a Low impact facility, as established by Schedule 3 of the Act and the Telecommunications (Low-Impact Facilities) Determination 1997. Hence no formal development approval is required from Council to install the proposed facility.” The Council did not accept the assertion that no formal development approval was required. In respect of each downlink site it issued enforcement notices pursuant to s 84 of the Development Act. In each instance the notices are in similar terms. The notices assert that Hutchison had undertaken development without approval, in breach of s 32 of the Development Act. The manner of the breach was particularised in the notices in the following terms:“You have undertaken development without the required Development Approval in that you have erected telecommunications facilities on a stobie pole on the above land which constitutes a load bearing structure and as such required development approval.” After receipt of the enforcement notices, Hutchison filed appeals in the Environment Resources and Development Court. Each notice of appeal asserted one ground only, namely:“The facility is a low-impact facility for the purposes of the Telecommunications Act 1997 (Cth) which does not require development approval under the Development Act.” Subsequently, the Council and Hutchison agreed that the appeals in the Environment Resources and Development Court be stayed pending the hearing and determination of the present proceedings. At the same time, the Council agreed with Hutchison to suspend the effect of the notices.

Evidence

Evidence before the court

Decision

Reasons for decision

PERRY J GRAY J
It follows that the points which Mr Whitington QC raises are better dealt with by the judge who has the carriage of the trial of the proceedings. I would therefore hold that the question whether the Council is entitled to a declaration is a matter for the trial judge to determine.Conclusion The facts contained in the Case Stated have been adequately summarised by Perry J. I will not repeat them. Nor will I set out again all the relevant legislation, although for the purpose of these reasons it will be necessary to repeat some parts of it. For the sake of convenience I will adopt the same abbreviations as Perry J has done. In order properly to understand the nature of the rights, duties and obligations of the several parties to this litigation in the circumstances which have happened, it is necessary first to understand the effect of the legislative provisions which govern their relationship and, against that background, to examine the nature and effect of the Facilities Access Agreement entered into between Hutchison and ETSA.Powers and immunities of carriers under the Telco Act Hutchison is a telecommunications carrier licensed pursuant to the provisions of Part 3, Division 3 of the Telco Act. Schedule 3 of the Telco Act describes various powers and immunities applicable to carriers. Schedule 3 is given effect by s 484 of the Telco Act. Under Schedule 3 a carrier is authorised to carry out the installation of a “facility”. By s 7 of the Telco Act “facility” is defined as meaning:“(a)Any part of the infrastructure of a telecommunications network; or(b)Any line, equipment, apparatus, tower, mast, antennae, tunnel, duct, hole, pit, pole or other structure or thing used, or for use, in or in connection with a telecommunications network.”It is not necessary for present purposes to venture into the statutory definitions of some of the terms used in that definition. So far as it is relevant, clause 6(1) of Schedule 3 provides:“(1)A carrier may, for purposes connected with the supply of a carriage service, carry out the installation of a facility if:(a) the carrier is authorised to do so by a facility installation permit; or(b) the facility is a low-impact facilty (as defined by subclause (3); …If a carrier installs a facility in South Australia under either of those conditions, the carrier is relieved from complying with the development approval requirements of the Development Act 1993 (SA). That relief is afforded by the combined operation of clause 37 of Schedule 3 and s 109 of the Constitution. For present purposes it is sufficient to note that the grant of a facility installation permit is governed by clauses 21 to 35 inclusive of Schedule 3 and requires consideration of an application and the granting of a permit by the Australian Communications Authority constituted under the Telco Act. The process bears some resemblance to a development approval process under State legislation. If the facility is a low-impact facility it does not require a permit and, as mentioned above, the installation is exempt from the operation of State laws such as the Development Act. In other words, for a low-impact facility, no statutory approval is required.

Ratio Decidendi

Legal principle established

Established by: PERRY J, GRAY J

Once a position is reached that none of the installations in question are low-impact facilities, State planning laws take effect, together with such exceptions, if any, as may be available under those laws.The Council’s entitlement to a Declaration The question is whether the Council is entitled to a declaration which gives expression to the answers to the questions posed in the Cast Stated, more particularly to the effect that the replacement of the stobie poles, with the exception of the pole at the Clarence Gardens site, together with the installation of the telecommunications facilities, constitutes development which requires approval pursuant to the Development Act. The making of a declaration involves the exercise of a discretion. At least one party, Hutchison, through Mr Whitington QC, put forward a strong plea that the discretion should be exercised against the making of a declaration in favour of the Council. The Council’s entitlement to a declaration may need to be considered in light of facts other than those set out in the Case Stated which may be the subject of further evidence to be called before the trial judge. It follows that the points which Mr Whitington QC raises are better dealt with by the judge who has the carriage of the trial of the proceedings. I would therefore hold that the question whether the Council is entitled to a declaration is a matter for the trial judge to determine.Conclusion The facts contained in the Case Stated have been adequately summarised by Perry J. I will not repeat them. Nor will I set out again all the relevant legislation, although for the purpose of these reasons it will be necessary to repeat some parts of it. For the sake of convenience I will adopt the same abbreviations as Perry J has done. In order properly to understand the nature of the rights, duties and obligations of the several parties to this litigation in the circumstances which have happened, it is necessary first to understand the effect of the legislative provisions which govern their relationship and, against that background, to examine the nature and effect of the Facilities Access Agreement entered into between Hutchison and ETSA.Powers and immunities of carriers under the Telco Act Hutchison is a telecommunications carrier licensed pursuant to the provisions of Part 3, Division 3 of the Telco Act. Schedule 3 of the Telco Act describes various powers and immunities applicable to carriers. Schedule 3 is given effect by s 484 of the Telco Act. Under Schedule 3 a carrier is authorised to carry out the installation of a “facility”. By s 7 of the Telco Act “facility” is defined as meaning:“(a)Any part of the infrastructure of a telecommunications network; or(b)Any line, equipment, apparatus, tower, mast, antennae, tunnel, duct, hole, pit, pole or other structure or thing used, or for use, in or in connection with a telecommunications network.”It is not necessary for present purposes to venture into the statutory definitions of some of the terms used in that definition.