SUPREME COURT OF SOUTH AUSTRALIA
(Civil: Case Stated)
CITY OF MITCHAM v HUTCHISON 3G AUSTRALIA LTD & ORS
Judgment of The Full Court
(The Honourable Justice Perry, The Honourable Justice Bleby and The Honourable Justice Gray)
11 March 2005
ENVIRONMENT AND PLANNING - BUILDING CONTROL
On a special case stated, consideration by the Full Court of questions relating to the erection by a telecommunications carrier, Hutchison 3G Australia Pty Ltd ("Hutchison") of telecommunication facilities known as downlink sites within a local council area - the council issued enforcement notices pursuant to s 35 of the Development Act 1993, claiming that development approval under that Act was required - the facilities were erected upon stobie poles which were also utilised by ETSA, a supplier of electricity licensed under the Electricity Act 1996, as part of its distribution network - in several instances ETSA replaced existing stobie poles with larger poles in order to accommodate the extra load resulting from the installation of the telecommunication facilities - held (by a majority, Bleby J dissenting) that each of the relevant stobie poles was a 'tower' within the meaning of Schedule 3 of the Telecommunications Act 1997 (Cth); that they did not constitute low-impact facilities within the meaning of the Telecommunications (Low-Impact Facilities) Determination 1997; and that the erection of the stobie poles and the installation of the telecommunication facilities constituted development for which approval was required under the Development Act - case stated answered accordingly.
Development Act 1993 (SA) s 33, s 34, s 37 and s 49A; Development Regulations 1993 Schedule 14A; Telecommunications Act 1997 (Cth) Part 3, Div 3 and s 484; Commonwealth Constitution s 109; Judiciary Act 1903 (Cth) s 78B; Electricity Act 1996 (SA) s 4(1), Part 3, s 23(1); Electricity Transmission Code, 1 July 2003 Clause 12.1 and clause 13; Acts Interpretation Act 1901 (Cth) s 15AB, referred to.
Hurstville City Council v Hutchison 3G Australia Pty Ltd (2003) 127 LGERA 95; Telstra Corporation Ltd v City of Onkaparinga [2001] EDLR 263, 13 July 2001, considered.
CITY OF MITCHAM v HUTCHISON 3G AUSTRALIA LTD & ORS
[2005] SASC 78Full Court: Perry, Bleby and Gray JJ
PERRY J. This is a special Case Stated, with the concurrence of the parties, for hearing and determination by the Full Court.[1]
[1] SCR r 72.01.
The plaintiff, the City of Mitcham (“the Council”), is the relevant authority pursuant to s 34 of the Development Act 1993 (“the Development Act”) in respect of development undertaken within the area of the Council.
The first defendant, Hutchison 3G Australia Pty Ltd (“Hutchison”) is a telecommunications carrier licensed pursuant to the provisions of Part 3, Division 3 of the Telecommunications Act1997 (Cth) (“the Telco Act”).
The remaining defendants are a group of companies: CKI Utilities Development Ltd, HEI Utilities Development Ltd, CKI Utilities Holdings Ltd, HEI Utilities Holdings Ltd and CKI/HEI Utilities Distribution Ltd. Those companies together trade as ETSA Utilities. I will refer to them collectively as “ETSA”.
In the proceedings,…
Keep reading for free
Create a free CaseChat account to read City of Mitcham v Hutchison 3G Australia Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
Details
- Case
- [2005] SASC 78
- Decision Date
CaseChat Overview and Summary
The central legal issues in the case revolved around the interpretation of the Telecommunications Act 1997 (Cth) and the Telecommunications (Low-Impact Facilities) Determination 1997. Specifically, the court needed to determine whether the telecommunication facilities erected by Hutchison on stobie poles were "towers" as defined in Schedule 3 of the Telecommunications Act, and whether they constituted "low-impact facilities" exempt from development approval under the Determination. If the facilities were not low-impact, the court had to decide whether their installation constituted development requiring approval under the Development Act 1993.
The court, by a majority, concluded that the stobie poles were indeed "towers" within the meaning of Schedule 3 of the Telecommunications Act and that the facilities did not qualify as low-impact facilities under the Determination. Therefore, the erection of these poles and the installation of the telecommunication facilities constituted development that required approval under the Development Act. Justice Bleby dissented from this majority decision, holding a different view on the interpretation of the relevant legislation.
Given the majority decision, the court answered the questions posed in the case accordingly. The matter of whether the City of Mitcham was entitled to a declaration regarding the need for development approval was left to the trial judge, as it depended on facts that might emerge during the trial. The final orders of the court would thus await the outcome of the trial proceedings.
Orders
Orders of the court
Background
Background to the litigation
Evidence
Evidence before the court
Decision
Reasons for decision
Ratio Decidendi
Legal principle established
Established by: PERRY J, GRAY J
Once a position is reached that none of the installations in question are low-impact facilities, State planning laws take effect, together with such exceptions, if any, as may be available under those laws.The Council’s entitlement to a Declaration The question is whether the Council is entitled to a declaration which gives expression to the answers to the questions posed in the Cast Stated, more particularly to the effect that the replacement of the stobie poles, with the exception of the pole at the Clarence Gardens site, together with the installation of the telecommunications facilities, constitutes development which requires approval pursuant to the Development Act. The making of a declaration involves the exercise of a discretion. At least one party, Hutchison, through Mr Whitington QC, put forward a strong plea that the discretion should be exercised against the making of a declaration in favour of the Council. The Council’s entitlement to a declaration may need to be considered in light of facts other than those set out in the Case Stated which may be the subject of further evidence to be called before the trial judge. It follows that the points which Mr Whitington QC raises are better dealt with by the judge who has the carriage of the trial of the proceedings. I would therefore hold that the question whether the Council is entitled to a declaration is a matter for the trial judge to determine.Conclusion The facts contained in the Case Stated have been adequately summarised by Perry J. I will not repeat them. Nor will I set out again all the relevant legislation, although for the purpose of these reasons it will be necessary to repeat some parts of it. For the sake of convenience I will adopt the same abbreviations as Perry J has done. In order properly to understand the nature of the rights, duties and obligations of the several parties to this litigation in the circumstances which have happened, it is necessary first to understand the effect of the legislative provisions which govern their relationship and, against that background, to examine the nature and effect of the Facilities Access Agreement entered into between Hutchison and ETSA.Powers and immunities of carriers under the Telco Act Hutchison is a telecommunications carrier licensed pursuant to the provisions of Part 3, Division 3 of the Telco Act. Schedule 3 of the Telco Act describes various powers and immunities applicable to carriers. Schedule 3 is given effect by s 484 of the Telco Act. Under Schedule 3 a carrier is authorised to carry out the installation of a “facility”. By s 7 of the Telco Act “facility” is defined as meaning:“(a)Any part of the infrastructure of a telecommunications network; or(b)Any line, equipment, apparatus, tower, mast, antennae, tunnel, duct, hole, pit, pole or other structure or thing used, or for use, in or in connection with a telecommunications network.”It is not necessary for present purposes to venture into the statutory definitions of some of the terms used in that definition.