DISTRICT COURT OF QUEENSLAND
CITATION:
Citimax Henderson Pty Ltd v Cobblestone Constructions Pty Ltd & Anor [2018] QDC 154
PARTIES:
CITIMAX HENDERSON PTY LTD (ACN 616 130 806)
(Plaintiff)v
COBBLE STONE CONSTRUCTIONS PTY LTD (ACN 611 123 016)
(First Defendant)And
ADAM WILLIAM SCOTT ALLEN
(Second Defendant)FILE NO/S:
1276/18
DIVISION:
Civil
PROCEEDING:
Application
ORIGINATING COURT:
Brisbane
DELIVERED ON:
10 August 2018
DELIVERED AT:
Brisbane
HEARING DATE:
30 July 2018 and 3 August 2018
JUDGE:
Williamson QC DCJ
ORDER:
1. By 4pm on 24 August 2018, the defendants file and serve a further amended defence consistent with these reasons for judgment.
2. The parties have liberty to apply with respect to costs.
CATCHWORDS:
COURT PRACTICE AND PROCEDURE – QUEENSLAND CIVIL PROCEDURE – LEAVE TO WITHDRAW ADMISSIONS – where defendants bring application for leave to withdraw admissions – where defendants bring application for leave to withdraw deemed admissions – whether there is a genuine dispute about matters admitted or deemed to be admitted – whether leave to withdraw admissions should be granted in the circumstances
CASES:
Hanson Construction Materials P/L v Norlis & Ors [2010] QSC 34
COUNSEL:
Ms Hoiberg for the plaintiff/respondent
Mr Kipps for the defendants/applicants
SOLICITORS:
Allens for the plaintiff/respondent
Irish Bentley Lawyers for the defendants/applicants
Introduction
Citimax Henderson Pty Ltd wishes to redevelop land in which it has an interest at Everton Hills. For this purpose, it entered into a construction contract with a civil earthworks contractor, Cobblestone Constructions Pty Ltd. Mr Allen is the sole director of Cobblestone Constructions. Citimax Henderson commenced these proceedings to sue for recovery of money alleged to be owing to it under a progress certificate issued under the contract between it and Cobblestone Constructions. The debt is denied by Cobblestone Constructions. A Claim and Statement of Claim was filed in this Court on 6 April 2018. A Notice of Intention to Defend and Defence and Counterclaim were filed on behalf of the defendants on 11 May 2018. The defence filed was characterised by Mr Kipps, counsel for the Defendants, as a holding defence.
On 31 May 2018, the defendants filed an Amended Defence and Counterclaim. They accept that this document seeks to withdraw admissions made in the holding defence for which leave is required under r.188 of the Uniform Civil Procedure Rules 1999 (‘UCPR’). This is an application by the defendants for leave under r.188. Citimax Henderson has cross-applied to strike out those aspects of the Amended Defence and Counterclaim that seek to withdraw admissions.
For the reasons that follow, I direct the defendants file and serve a Further Amended Defence and Counterclaim consistent with these reasons. I will allow 14 days for this to occur. The parties have liberty to apply with respect to costs.
Rule 188 and relevant principles
Rule 188 of the UCPR provides that a party may withdraw an admission in a pleading only with the Court’s leave. Leave to withdraw is not obtained for…
Keep reading for free
Create a free CaseChat account to read Citimax Henderson Pty Ltd v Cobblestone Constructions Pty Lt... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2018] QDC 154
- Decision Date
CaseChat Overview and Summary
The primary legal issue before the court was whether there existed a genuine dispute about the matters that had been admitted or deemed to be admitted by the defendant. The court had to determine if the defendant had a valid reason to withdraw these admissions and whether, in the circumstances, it was just for the defendant to be granted leave to withdraw them. The court had to balance the principle of finality in litigation against the need for fairness and justice in individual cases.
The court found that there was no genuine dispute about the matters admitted or deemed to be admitted by the defendant. It considered that the defendant's reasons for seeking to withdraw the admissions were not compelling and that the application was an attempt to relitigate issues that had already been determined. The court held that it was not just for the defendant to be granted leave to withdraw the admissions. The court ordered that the defendant must file and serve a further amended defence by a specified date, consistent with the reasons for judgment. Additionally, the parties were granted liberty to apply with respect to costs.
Orders
Orders of the court
1. By 4pm on 24 August 2018, the defendants file and serve a further amended defence consistent with these reasons for judgment.
2. The parties have liberty to apply with respect to costs.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.