Federal Court of Australia
Citadel Group Limited, in the matter of Citadel Group Limited [2020] FCA 1580
File number(s): VID 683 of 2020 Judgment of: BEACH J Date of judgment: 29 October 2020 Date of publication of reasons: 30 October 2020 Catchwords: CORPORATIONS – members’ scheme of arrangement – first court hearing – order sought under s 411(1) of the Corporations Act 2001 (Cth) –performance risk – break fee – exclusivity arrangements – employee incentive arrangements – exercise of discretion – order made for convening of meeting Legislation: Corporations Act 2001 (Cth) ss 254T, 260A, 411, 412 and 602
Corporations (Coronavirus Economic Response) Determination (No.3) 2020 (Cth)
Corporations Regulations 2001 (Cth) reg 5.1.01 and Sch 8
Federal Court (Corporations) Rules 2000 (Cth) rr 2.15 and 3.4; form 6
Cases cited: Re Amcor [2019] FCA 346
Re Foundation Healthcare Ltd (2002) 42 ACSR 252
Re Healthscope (2019) 139 ACSR 608
Re Legend Corporation Limited [2019] FCA 1249
Re Skilled (2015) 113 ACSR 525
Division: General Division Registry: Victoria National Practice Area: Commercial and Corporations Sub-area: Corporations and Corporate Insolvency Number of paragraphs: 89 Date of hearing: 29 October 2020 Counsel for the Plaintiff Mr PD Crutchfield QC with Mr B Holmes Solicitor for the Plaintiff Gadens Counsel for the Intervener: Mr M Oakes SC Solicitor for the Intervener: Clayton Utz ORDERS
VID 683 of 2020 IN THE MATTER OF CITADEL GROUP LIMITED
BETWEEN: THE CITADEL GROUP LIMITED (ACN 127 151 026)
Plaintiff
order made by:
BEACH J
DATE OF ORDER:
29 OCTOBER 2020
OTHER MATTERS:
1.The Court notes that the Australian Securities and Investments Commission (ASIC) was provided with at least 14 days’ notice of the hearing of this application.
2.The Court is satisfied that ASIC has had a reasonable opportunity to:
(a)examine the terms of the proposed scheme of arrangement to which the application relates and a draft explanatory statement relating to that arrangement; and
(b)make submissions to the Court in relation to the proposed scheme of arrangement and the draft explanatory statement.
3.The Court notes the letter from ASIC to the Directors of The Citadel Group Limited dated 28 October 2020 at Annexure JPR-2 to the affidavit of Jolyon Percival Rogers dated 29 October 2020.
THE COURT ORDERS THAT:
1.Pursuant to s 411(1) of the Corporations Act 2001 (Cth) (Act), the Plaintiff convene and hold a meeting of its shareholders (Scheme Meeting):
(a)for the purpose of considering, and, if thought fit, agreeing (with or without modification), to the scheme of arrangement (Scheme) proposed to be made between the Plaintiff and its shareholders (Citadel Shareholders), the terms of which are set out in Annexure A to these orders; and
(b)to be held on Tuesday 1 December 2020 at 11.00 am (AEDT) and to be conducted electronically through an online platform (which is to be accessed in accordance with the instructions included in the Notice of Meeting to be sent to shareholders in accordance with order 2 below) in accordance with the provisions of Part 2 of the Corporations (Coronavirus Economic…
Keep reading for free
Create a free CaseChat account to read Citadel Group Limited, in the matter of Citadel Group Limite... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
Details
- Case
- [2020] FCA 1580
- Decision Date
CaseChat Overview and Summary
In determining these issues, the Court considered the nature and terms of the Scheme, the adequacy of the Scheme Booklet, the availability of an independent expert’s report, and whether the Scheme appeared on its face to be unfair or inappropriate. The Court was satisfied that the Scheme was in a conventional form for an acquisition scheme, that there was no reason why it should not be approved if considered and adopted by the members, and that the Scheme Booklet met the statutory requirements. The Court also noted that the Citadel shareholders would be presented with an analysis of the proposed Scheme by an independent expert, including a detailed discussion of its advantages and disadvantages. Therefore, the Court concluded that the Scheme was appropriate to be approved at the first hearing stage and that the proposed convening of the Scheme Meeting was in accordance with the relevant statutory and regulatory requirements.
Accordingly, the Court made orders pursuant to section 411(1) of the Corporations Act 2001 (Cth) for the convening of the Scheme Meeting on Tuesday 1 December 2020 at 11.00 am (AEDT) and to be conducted electronically through an online platform in accordance with the provisions of Part 2 of the Corporations (Coronavirus Economic Response) Determination (No.3) 2020. The Court also made orders for the convening of the Scheme Meeting by sending emails and hard-copy documents to the Citadel Shareholders, dispensing with certain compliance requirements, setting the voting procedure, specifying the validity and effectiveness of proxies and elections, appointing the Chair of the Scheme Meeting, and adjourning the further hearing of the Originating Process. The Court further made orders for the publication of a Notice of Hearing and the entry of orders.
Orders
Orders of the court
1. Pursuant to s 411(1) of the Corporations Act 2001 (Cth) (Act), the Plaintiff convene and hold a meeting of its shareholders (Scheme Meeting):
(a) for the purpose of considering, and, if thought fit, agreeing (with or without modification), to the scheme of arrangement (Scheme) proposed to be made between the Plaintiff and its shareholders (Citadel Shareholders), the terms of which are set out in Annexure A to these orders; and
(b) to be held on Tuesday 1 December 2020 at 11.00 am (AEDT) and to be conducted electronically through an online platform (which is to be accessed in accordance with the instructions included in the Notice of Meeting to be sent to shareholders in accordance with order 2 below) in accordance with the provisions of Part 2 of the Corporations (Coronavirus Economic Response) Determination (No.3) 2020.
2. The Scheme Meeting be convened by sending on or before Friday 30 October 2020:
(a) an email to each Citadel Shareholder who has nominated an electronic address for the purposes of receiving notices of meeting and proxy forms from the Plaintiff (Email Shareholder) (or, in the case of joint holders, to the holder whose name appears first in the Plaintiff’s register), such email to be substantially in the form of pages 978-979 of Annexure PFL-1 to the affidavit of Peter Francis Leahy sworn on 28 October 2020 (Leahy Affidavit) which contains links to:
(i) an electronic copy of a document substantially in the form of the Scheme Booklet, a draft of which is at pages 293-756 of Annexure PFL-1 to the Leahy Affidavit (which contains among other things the proposed Scheme of Arrangement at Annexure D and Notice of Scheme Meeting at Annexure G) (Scheme Booklet); and
(ii) an online portal or website that is accessible by the Email Shareholder and which enables the Email Shareholder to:
A. lodge their proxy for the Scheme Meeting and voting instructions online; and
B. make an Election in relation to the Scrip Consideration online (as those terms are defined in the Scheme Booklet);
(b) the following hard-copy documents to each Citadel Shareholder who is not an Email Shareholder (or, in the case of joint holders, to the holder whose name appears first in the Plaintiff’s register):
(i) a letter substantially in the form of pages 980-982 of Annexure PFL-1 to the Leahy Affidavit (Letter) setting out the URL which provides access to a document substantially in the form of the Scheme Booklet (which contains among other things the proposed Scheme of Arrangement at Annexure D and the Notice of Scheme Meeting at Annexure G) and which sets out instructions about how to make an Election (as defined in the Scheme Booklet) and lodge a proxy for the Scheme Meeting and voting instructions;
(ii) an Election Form in relation to the Scrip Consideration (as those terms are defined in the Scheme Booklet) substantially in the form of pages 759-760 of Annexure PFL-1 to the Leahy Affidavit (Election Form) and a reply-paid envelope for the return of the completed Election Form; and
(iii) a proxy/voting form for the Scheme Meeting (Proxy Form), substantially in the form of pages 757-758 of Annexure PFL-1 to the Leahy Affidavit.
3. The documents referred to in order 2(b) be sent:
(a) in the case of Citadel Shareholders whose registered address is within Australia, by prepaid ordinary post addressed to the relevant addresses recorded in the Plaintiff’s register; and
(b) in the case of Citadel Shareholders whose registered address is outside Australia, by airmail or international courier service addressed to the relevant addresses recorded in the Plaintiff’s register.
4. Compliance with r 2.15 of the Federal Court (Corporations) Rules 2000 (Cth) (Rules) be dispensed with, except in so far as that rule applies r 75-15(2) of the Insolvency Practice Rules (Corporations) 2016 (Cth).
5. Voting on the resolution to approve the Scheme is to be conducted by way of a poll.
6. A proxy in respect of the Scheme Meeting will be valid and effective if, and only if, a Proxy Form is completed and delivered in accordance with its terms or a proxy is lodged online in accordance with the instructions on the online portal or website referred to in order 2(a)(ii), and received by the Plaintiff by 11.00 am (AEDT, being Melbourne time) on 29 November 2020.
7. An Election (as defined in the Scheme Booklet) will be valid and effective if, and only if, an Election Form is completed, delivered and received by the Plaintiff in accordance with its terms or a valid election is made online in accordance with the instructions on the online portal or website referred to in order 2(a)(ii), by 5.00 pm (AEDT, being Melbourne time) on 24 November 2020.
8. Mr Peter Francis Leahy or failing him Mr Robert Ian Alexander, be Chair of the Scheme Meeting.
9. The Chair of the Scheme Meeting shall have the power to adjourn the meeting to such time, date and place as he considers appropriate.
10. Compliance with r 3.4 and Form 6 of the Rules is dispensed with.
11. The Plaintiff publish a Notice of Hearing in The Australian newspaper, in substantially the form that appears at Annexure B hereto, not later than 5 days prior to the date fixed for the hearing of any application to approve the Scheme.
12. The further hearing of the Originating Process is adjourned to the Honourable Justice Beach at 9.30 am (AEDT, being Melbourne time) on Monday, 7 December 2020 or as soon thereafter as the business of the Court allows.
Note: Entry of orders is dealt with in Rule 39.32 of the Federal Court Rules 2011.
[The order entered is available on the Commonwealth Courts Portal, which attaches the Scheme]
Background
Background to the litigation
Evidence
Evidence before the court
Decision
Reasons for decision
Ratio Decidendi