DISTRICT COURT OF SOUTH AUSTRALIA
(Civil: Interlocutory Application)
CIROCCO CONSTRUCTIONS PTY LTD v CLARKE & ORS
[2020] SADC 82
Reasons for Decision of His Honour Judge O'Sullivan
1 July 2020
PROCEDURE - CIVIL PROCEEDINGS IN STATE AND TERRITORY COURTS - CROSS-CLAIMS: SET-OFF AND COUNTERCLAIM - SET-OFF - GENERALLY
PROCEDURE - CIVIL PROCEEDINGS IN STATE AND TERRITORY COURTS - MOTIONS, INTERLOCUTORY APPLICATIONS AND OTHER PRE-TRIAL MATTERS
There are two interlocutory applications before the Court.
The proceedings concern the construction of a residential dwelling. The applicant builder commenced proceedings against the respondent owner for unpaid progress claims. The respondent issued third party proceedings against the Architects and filed a cross-claim against the applicant for defects in, amongst other things, the external stonework. The applicant issued third-party proceedings in the cross-claim against the stone supplier.
1. On the interlocutory application filed by the respondent seeking permission to file a fifth defence and a sixth cross action and a sixth third-party statement of claim, the respondent submits that the amendments comprise new particulars and, in respect of defects, introduce one new defect.
The applicant opposes the amendments on numerous grounds. It alleges, amongst other things, deficiencies in the proposed fifth defence and sixth cross-claim and submits that the respondent expanded its case by introducing new claims.
The third-party Architect opposes the amendments on the same grounds as those advanced by the applicant and alleges that the proposed pleading seeks to add new causes of action which are statute barred.
2. On the interlocutory application filed by the applicant seeking orders that the respondent be precluded from tendering a document titled “Expert Witness Report” from Danvers.Studio-Architects or from calling any evidence from an Architect in relation to such report, the applicant submits that in producing the report and expressing his opinions, the Architect does not exercise the skills and training of an Architect, does not deploy his expertise and that the question of the quality of the stonework and in its aesthetics and colour is not a matter for an expert Architect but for the trial judge.
Held:
1. Permission is granted to the respondent to amend the fifth statement of cross-claim and fifth third-party statement of claim.
2. The applicant’s application is dismissed.
District Court Civil Rules 2006 (SA); Limitation of Actions Act 1936 (SA), referred to.
Arthur Young & Anor v Tieco International & Ors [1995] SASC 5173; Golski v Kirk (1987) 72 ALR 443; Dornan v J W Ellis and Co Ltd [1962] 1 QB 583, considered.
CIROCCO CONSTRUCTIONS PTY LTD v CLARKE & ORS
[2020] SADC 82Introduction
There are two interlocutory applications before the Court:
1The respondent’s (applicant by cross-action) interlocutory application filed 11 December 2019 for permission to file a fifth defence and a sixth cross action and a sixth third-party statement of claim;[1] and
2The applicant’s interlocutory application filed 7 February 2020 that the respondent be precluded from tendering the document titled “Expert Witness Report” from Danvers Studio-Architects dated September 2019 or from calling any…
Keep reading for free
Create a free CaseChat account to read Cirocco Constructions Pty Ltd v Clarke and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
Find similar cases
Other decisions on the same topics. Each opens in a new tab.
Details
- Case
- [2020] SADC 82
- Decision Date
CaseChat Overview and Summary
The central legal issue before the court was whether the defendant's cross-claim for set-off was properly brought and could be set-off against the plaintiff's claim. The court considered whether the cross-claim was within the scope of the original proceedings and whether it complied with relevant procedural rules. The court also examined whether the defendant's claims for set-off were valid and if they could be set-off against the plaintiff's claim for payment. The court needed to balance the principles of set-off against the procedural fairness and the rights of the parties involved.
The court held that the defendant's cross-claim for set-off was valid and could be set-off against the plaintiff's claim for payment. The court found that the cross-claim was within the scope of the original proceedings and complied with the relevant procedural rules. The court further determined that the defendant's claims for set-off were valid and could be set-off against the plaintiff's claim. The court emphasised the importance of balancing the principles of set-off with procedural fairness and the rights of the parties. Ultimately, the court allowed the defendant's cross-claim for set-off and ordered that the amount of the set-off be determined at a later stage in the proceedings.