Cecchi v Taylor t/as Jag Constructions (formerly J.E.T Building and Renovation Services)

Link copied
Case Copied 16 min read

QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL


CITATION: 

Cecchi v Taylor t/as Jag Constructions (formerly J.E.T. Building and Renovation Services) [2021] QCAT 355

PARTIES: SARA CECCHI

(applicant)

v

JOEL EMMERSON TAYLOR T/AS JAG CONSTRUCTIONS FORMERLY J.E.T. BUILDING AND RENOVATION SERVICES

(respondent)

APPLICATION NO/S:

BDL103-20

MATTER TYPE:

Building matters

DELIVERED ON:

20 October 2021

HEARING DATE:

On the papers

HEARD AT:

Brisbane

DECISION OF:

Member Gardiner

ORDERS:

1.       Joel Emmerson Taylor is to pay to Sara Cecchi the amount of THIRTY-FIVE THOUSAND TWO HUNDRED AND EIGHTY DOLLARS AND EIGHTY CENTS ($35,280.80) within 28 days of this decision.

CATCHWORDS:

APPEARANCES & REPRESENTATION:

CONTRACTS – BUILDING, ENGINEERING AND RELATED CONTRACTS – PERFORMANCE OF WORK – REMEDIES FOR BREACH OF CONTRACT – DAMAGES – MEASURE OF – where builder performed unlicensed building work – defective work - where homeowner was home owner and owner/builder – effect of unlicensed building work on assessment of damages.

Electronic Transactions (Queensland) Act 2001 (Qld), s 14

Queensland Building and Construction Commission Act 1991 (Qld), s 42, s 77, Schedule 1B, Schedule 2

Queensland Civil and Administrative Tribunal Act 2009 (Qld), s 48

Bellgrove v Eldridge (1954) 90 CLR 613

BP Refinery (Westernport) Pty Ltd v Hastings Shire Council (1977) 180 CLR 266

Cook's Construction P/L v SFS 007.298.633 P/L (formerly trading as Stork Food Systems Australasia P/L) [2009] QCA 75

Robinson v Harman (1848) 1 Ex 850

Thompson v Shen and Kao [2017] QCAT 33

Ventura v Svirac [1961] WAR 63

Yongwoo Park v Betaland Pty Ltd [2017] QCAT 228

This matter was heard and determined on the papers pursuant to s 32 of the Queensland Civil and Administrative Tribunal Act 2009 (Qld)

REASONS FOR DECISION

  1. Ms Cecchi advertised online for a building contractor to undertake building works at her home in early April 2019.

  2. Mr Taylor responded, and Ms Cecchi engaged Mr Taylor to undertake the works.  Mr Taylor was to build a new deck and pergola and to remove soil to make way for a new retaining wall and concrete slab.  Ms Cecchi says that the works are incomplete and claims damages for the cost of completing the contract with.

Background

  1. Mr Taylor submitted a quote to Ms Cecchi dated 12 April 2019 for $32,025.00 to undertake the renovation works.  This quote sets out the work Mr Taylor was to undertake for Ms Cecchi and details the payment schedule. 

  2. Mr Taylor and Ms Cecchi agreed on further oral variation to that quote in May 2019.  The existence of this variation is documented in emails between the parties dated 20 May 2019.  No details of the work identified in the variation is provided by Ms Cecchi and no invoice for the variations is produced by Ms Cecchi. In her originating application, Ms Cecchi says the agreed variation amount was $8,975.00.

  3. However, the emails from Mr Taylor (also on 20 May 2019) request payment for the variation and an agreement by Ms Cecchi to cover the cost of materials for the variation. Ms Cecchi’s bank records show that on 21…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Cecchi v Taylor t/as Jag Constructions (formerly J.E.T Build... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2021] QCAT 355
Decision Date

CaseChat Overview and Summary

In this matter, Sara Cecchi brought an application against Joel Emmerson Taylor t/as Jag Constructions (formerly J.E.T. Building and Renovation Services) for damages for incomplete building work. The matter was heard and determined on the papers pursuant to s 32 of the Queensland Civil and Administrative Tribunal Act 2009 (Qld). The issues for determination were whether Mr Taylor was an unlicensed builder, whether Mr Taylor had breached the contract by failing to complete the building works, and if so, the appropriate remedy. The Tribunal found that Mr Taylor was an unlicensed builder and that he had breached the contract by failing to complete the building works. The appropriate remedy was the return of the monies paid to Mr Taylor for materials never delivered and progress payments made, plus the costs of the proceedings. The Tribunal ordered that Joel Emmerson Taylor is to pay to Sara Cecchi the amount of THIRTY-FIVE THOUSAND TWO HUNDRED AND EIGHTY DOLLARS AND EIGHTY CENTS ($35,280.80) within 28 days of this decision. This amount includes the refund of the monies paid to Mr Taylor and the costs of the proceedings. The Tribunal found that the claim for the cost of completing the contract was not substantiated by the evidence. The Tribunal also found that Mr Taylor as an unlicensed builder is disentitled to receive payment for his work and Ms Cecchi as a homeowner, is entitled to recover the monies she paid to him.