Land and Environment Court
New South Wales
Medium Neutral Citation: Callaghan v Beverley [2020] NSWLEC 1117 Hearing dates: 30 January 2020 Date of orders: 30 January 2020 Decision date: 30 January 2020 Jurisdiction: Class 2 Before: Douglas AC Decision: The Orders of the Court are:
(1) Within 60 days of these orders, the respondents shall contract an arborist, with all appropriate insurances, to reduction prune one branch of the Fig, which extends over the applicants’ roof in a south – westerly direction, back to an appropriate junction within the canopy, such that the pruning complies with AS4573:2007 (Pruning of Amenity Trees).
(2) Council shall develop a level 2 inspection strategy (based on ISA Tree Risk Assessment Qualification format) and a pruning strategy for the Fig tree (particularly in regard to branches overhanging the adjacent nature strip), and implement it for a period of five year from the date of these orders. This strategy shall entail inspections completed annually, plus after major storms, and they shall be undertaken at Council’s expense. Any tree pruning recommended from these inspections shall be subject to standard Council application requirements, and fees, and any such works are to be completed at the applicants’ and or respondents’ expense.
(3) All pruning shall comply with AS4573:2007 (Pruning of Amenity trees).
(4) All pruning and inspections shall be completed by arborists with a minimum Arboriculture qualification of AQF level 3.
(5) All tree works shall comply with the Safe Work Australia ‘Guide to Managing Risks of Tree Trimming and Removal Work, 2016.
(6) The cost burden for the pruning in Order 1 shall be shared equally between the parties. Upon completion of this work, the respondent shall supply the applicant with a copy of the paid invoice, and the applicant shall reimburse the respondent for 50% of this cost, within 21 days.
(7) The applicant shall provide access for completion of this pruning upon receipt of at least 48 hours written notice of the date and approximate starting time of the works.Catchwords: TREES (DISPUTES BETWEEN NEIGHBOURS) – damage from falling branches – apprehension of injury Legislation Cited: Environmental Planning and Assessment Act 1979
Trees (Disputes Between Neighbours) Act 2006
Uniform Civil Procedures Rules 2005Cases Cited: Barker v Kryiakides [2007] NSWLEC 292
Black v Johnson (No 2) [2007] NSWLEC 513
Makita (Australia) Pty Ltd v Sprowles (2001) NSWLR 705; [2001] NSWCA 305
McPherson v Lake [2017] NSWLEC 1081
Owners Corporation Strata Plan 56927 v Horner [2012] NSWLEC 1146
Robson v Leischke (2008) 72 NSWLR 98; [2008] NSWLEC 152
Smith & Hannaford v Zhang & Zhou [2011] NSWLEC 29
Yang v Scerri [2007] NSWLEC 592Texts Cited: AS4573:2007 (Pruning of Amenity Trees)
Kiama Development Control Plan 2012
Safe Work Australia ‘Guide to Managing Risks of Tree Trimming and Removal Work’, 2016
State Environmental Planning Policy (Vegetation in Non-Rural Areas) 2017Category: Principal judgment Parties: Bernard Callaghan (Applicant)
Robyn Beverley (First Respondent)
Kiama Municipal Council (Second Respondent)Representation: Counsel:
B Callaghan (Litigant in Person) (Applicant)
R Beverley (Litigant…
Continue reading Callaghan v Beverley
Sign in free to access the full text
- AGLC
- Callaghan v Beverley [2020] NSWLEC 1117
- Case
- [2020] NSWLEC 1117
- Decision Date
CaseChat Overview and Summary
The central legal issue before the court was whether the applicants had demonstrated a sufficient risk to their safety or property that warranted the intervention of the court under the statutory framework. The court had to consider the evidence provided by the parties, including expert evidence from arborists, to assess the potential hazards posed by the Fig tree. The court also needed to evaluate whether the proposed orders for pruning and ongoing maintenance were necessary and reasonable measures to mitigate any identified risks.
In its reasoning, the court found that the applicants had established a risk to their safety and property due to the overhanging branch of the Fig tree. The court acknowledged the potential for significant damage to the applicants' property if the branch were to fall. The court considered the statutory framework and the expert evidence presented, and concluded that the proposed orders were appropriate and proportionate to the identified risks. The court ordered the respondents to prune the overhanging branch and implement a maintenance strategy, with specific requirements for the qualifications of the arborists and compliance with safety standards. The court also directed that the cost of the initial pruning work be shared equally between the parties.
The orders of the court included specific directions for the pruning of the Fig tree branch, the development and implementation of a maintenance strategy, and the qualifications and standards for the arborists involved. The court mandated that the respondents contract an appropriately qualified arborist to prune the branch and that the council develop a level 2 inspection strategy for the tree. The court further stipulated that all tree works must comply with safety guidelines and that the cost of the initial pruning be shared equally between the parties. The applicants were also required to provide access for the completion of the pruning upon receiving notice from the respondents.
Orders
Orders of the court
The Orders of the Court are:
(1) Within 60 days of these orders, the respondents shall contract an arborist, with all appropriate insurances, to reduction prune one branch of the Fig, which extends over the applicants’ roof in a south – westerly direction, back to an appropriate junction within the canopy, such that the pruning complies with AS4573:2007 (Pruning of Amenity Trees).
(2) Council shall develop a level 2 inspection strategy (based on ISA Tree Risk Assessment Qualification format) and a pruning strategy for the Fig tree (particularly in regard to branches overhanging the adjacent nature strip), and implement it for a period of five year from the date of these orders. This strategy shall entail inspections completed annually, plus after major storms, and they shall be undertaken at Council’s expense. Any tree pruning recommended from these inspections shall be subject to standard Council application requirements, and fees, and any such works are to be completed at the applicants’ and or respondents’ expense.
(3) All pruning shall comply with AS4573:2007 (Pruning of Amenity trees).
(4) All pruning and inspections shall be completed by arborists with a minimum Arboriculture qualification of AQF level 3.
(5) All tree works shall comply with the Safe Work Australia ‘Guide to Managing Risks of Tree Trimming and Removal Work, 2016.
(6) The cost burden for the pruning in Order 1 shall be shared equally between the parties. Upon completion of this work, the respondent shall supply the applicant with a copy of the paid invoice, and the applicant shall reimburse the respondent for 50% of this cost, within 21 days.
(7) The applicant shall provide access for completion of this pruning upon receipt of at least 48 hours written notice of the date and approximate starting time of the works.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.