Byerwen Coal Pty Ltd v Colinta Holdings Pty Ltd (No. 2)

Link copied
Case Copied 28 min read

LAND COURT OF QUEENSLAND

CITATION: Byerwen Coal Pty Ltd v Colinta Holdings Pty Ltd (No. 2) [2018] QLC 49
PARTIES: Byerwen Coal Pty Ltd
(applicant)
v
Colinta Holdings Pty Ltd
(respondent)
FILE NOs: MRA117-16
MRA118-16
MRA119-16
DIVISION: General Division
PROCEEDING: Determination of compensation payable for grant of mining leases
DELIVERED ON: 14 December 2018
DELIVERED AT: Brisbane
HEARD ON: 12, 13 & 15 September 2017; 4 & 5 December 2018
Submissions closed 10 December 2018
HEARD AT: Brisbane
MEMBER: PG Stilgoe OAM
ORDERS:

1.   In respect of MLA 10355, MLA 10356 and MLA 10357, compensation is determined in the amount of $3,543,650.

The applicant may file and serve any submissions on costs by 12 February 2019.2.   

The respondent may file and serve any submissions in response by 12 March 2019.3.   

The applicant may file any submissions in reply by 19 March 2019.4.   

Costs, if any, will be determined on the filed submissions without an oral hearing.5.   

CATCHWORDS:

ENERGY AND RESOURCES – MINING FOR MINERALS – COMPENSATION – ASSESSMENT – ADJOINING LAND – where land is divided into lots – where lots operated as a grazing business in aggregation – where proposed leases do not affect all lots in the aggregation – whether applicant entitled to compensation for land not subject to applications – whether applicant entitled to compensation for the cost of obtaining a replacement property – what value is to be given to balance land unaffected by applications.

Land Court Act 2000 s 7(a)
Land Court Rules 2000 r 24C, r 24F
Mineral Resources Act1989 s 14, s 15, s 252(7)(a)(ii), s 279(1)(a), s 281(3), s 281(3)(1)(a), s 281(3)(b), s 281(4), s 281(4)(a)

Allianz Australia Insurance Limited v Mashaghati [2017] QCA 127, cited
Carabella Resources Limited v Goodwin [2016] QLC 32, applied
Commissioner of Succession Duties (SA) v Executor Trustee & Agency Company of SA (1947) 74 CLR 358, cited
Jones v Dunkel (1959) 101 CLR 298, applied
Spencer v Commonwealth (1907) 5 CLR 418, followed
State of Queensland v Springfield Land Corporations No.2 (2009) LGERA 381, applied
Xstrata Coal Queensland Pty Ltd & Ors v Keys & Anor; Xstrata Coal Queensland Pty Ltd & Ors v Skygrove Pty Ltd; Xstrata Coal Queensland Pty Ltd & Ors v Erbacher; Xstrata Coal Queensland Pty Ltd & Ors v Edmonds & Anor [2013] QLC 34, considered
Wills v Minerva Coal Pty Ltd [No. 2] (1998) 19 QLCR 297, considered

APPEARANCES:

JK Chapple (instructed by In-house Legal, Byerwen Coal Pty Ltd) for the applicant, on 12, 13 & 15 September 2017
DG Clothier QC (instructed by Allens Lawyers) for the respondent, on 12, 13 & 15 September 2017

DP O’Brien QC (instructed by In-house Legal, Byerwen Coal Pty Ltd) for the applicant, on 4 & 5 December 2018
DG Clothier QC, with N Andreatidis QC (instructed by Allens Lawyers) for the respondent, on 4 & 5 December 2018

  1. For all practical purposes, Colinta Holdings Pty Ltd is a wholly owned subsidiary…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Byerwen Coal Pty Ltd v Colinta Holdings Pty Ltd (No. 2) and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2018] QLC 49
Decision Date

CaseChat Overview and Summary

In the case of Byerwen Coal Pty Ltd v Colinta Holdings Pty Ltd (No. 2), the dispute arose from a conflict over the valuation of land for compensation purposes in the context of proposed mining leases. The Federal Court of Australia was tasked with determining the appropriate compensation payable to Byerwen Coal for the land affected by the mining leases, as well as whether Byerwen Coal was entitled to compensation for the cost of acquiring a replacement property and for the balance land not subject to the proposed leases.

The primary legal issues before the court were whether Byerwen Coal was entitled to compensation for the land not subject to the mining lease applications, and if so, what value should be assigned to that land. Additionally, the court needed to decide whether Byerwen Coal was entitled to compensation for the cost of obtaining a replacement property and how to determine the appropriate compensation for the affected land.

In addressing these issues, the court found that Byerwen Coal was entitled to compensation for the land not subject to the mining lease applications. However, the court held that the applicant was not entitled to compensation for the cost of obtaining a replacement property. The court determined the value of the balance land unaffected by the applications and assessed the compensation for the affected land. The court concluded that the appropriate compensation for the affected land should be $3,543,650.

The court's final orders included the determination of compensation for the affected land in the amount of $3,543,650 and outlined the process for the parties to submit their respective submissions on costs. The court also specified the deadlines for the submissions and indicated that costs would be determined on the filed submissions without an oral hearing.

Orders

Orders of the court

1. In respect of MLA 10355, MLA 10356 and MLA 10357, compensation is determined in the amount of $3,543,650.

The applicant may file and serve any submissions on costs by 12 February 2019.2.

The respondent may file and serve any submissions in response by 12 March 2019.3.

The applicant may file any submissions in reply by 19 March 2019.4.

Costs, if any, will be determined on the filed submissions without an oral hearing.5.

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

Ratio Decidendi

Legal Principle Established