Buyozo Pty Limited v Ku-ring-gai Council

Link copied
Case Copied 24 min read

Land and Environment Court


New South Wales

Medium Neutral Citation: Buyozo Pty Limited v Ku-ring-gai Council [2021] NSWLEC 2
Hearing dates: 14 December 2020
Date of orders: 6 January 2021
Decision date: 06 January 2021
Jurisdiction:Class 1
Before: Pepper J
Decision:

See orders at [46].

Catchwords:

APPEAL: whether condition of consent imposing contributions should be modified – contributions calculated by reference to “gross floor area” of development – proper construction of term “gross floor area” – proper construction of exemption in subparagraph (h) of definition of “gross floor area” – whether corridors accessing unloading and loading spaces exempt from calculation of “gross floor area” – corridors exempt – whether utility in modifying condition because contributions already paid – utility in modifying the condition– consent neither exhausted nor spent – appeal allowed – condition modified.

Legislation Cited:

Environmental Planning and Assessment Act 1979, ss 4.55, 7.11

Cases Cited:

Agricultural Equity Investments Pty Ltd v Westlime Pty Ltd (No 3) [2015] NSWLEC 75

Arkibuilt Pty Ltd v Ku-ring-gai Council [2006] NSWLEC 502; (2006) 67 NSWLR 529

Arncliffe Development Pty Ltd v Rockdale City Council [2003] NSWLEC 297; (2003) 129 LGERA 189

Malcolm Smith Pty Ltd v Hills Shire Council [2019] NSWLEC 1096

R v A2; R v Magennis; R v Vaziri (2019) 373 ALR 214; [2019] HCA 35

Category:Principal judgment
Parties: Buyozo Pty Limited (Applicant)
Ku-ring-gai Council (Respondent)
Representation:

Counsel:
I Hemmings SC (Applicant)
M Wright SC (Respondent)

Solicitors:
Reid & Vesely Solicitors (Applicant)
Wilshire Webb Staunton Beattie Lawyers (Respondent)
File Number(s): 2019/244851

Judgment

Buyozo Seeks to Modify a Condition of Consent for the Payment of Contributions in Respect of the Development of a Storage Facility

  1. It is not often that a link exists in proceedings in Class 1 of the Court’s jurisdiction between serial killers, IKEA tealight candles and supermarkets. Until these proceedings, that is.

  2. The applicant, Buyozo Pty Ltd (“Buyozo”), was granted a development consent issued by the Court (DA 122/2017) under an agreement reached between the parties pursuant to s 34 of the Land and Environment Court Act 1979 (“the LEC Act”) (“the consent”).

  3. The consent is for the consolidation of three existing lots into one, alternations and additions to an existing warehouse premises to create a self-storage facility and separate commercial premises at 3-5 West St, Pymble, NSW (“the premises”).

  4. Condition 30 of the consent is in the following terms:

30.   Section 94 Contributions – Centres.

(For DAs determined on or after 19 December 2010)

This development is subject to a development contribution calculated in accordance with Ku-ring-gai Contributions Plan 2010, being a s94 Contributions Plan in effect under the Environmental Planning and Assessment Act, as follows:

Development Contributions Plan 2010

Infrastructure Type                 Total

Pymble TC New Roads & Roads Mods          $987,242.37

Development Contributions Total            $987,242.37

The contribution shall be paid to Council prior to the issue of any Construction Certificate, Linen Plan, Certificate of Subdivision or Occupation Certificate whichever comes first in accordance with Ku-ring-gai Contributions Plan 2010.

The contributions specified…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Buyozo Pty Limited v Ku-ring-gai Council and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2021] NSWLEC 2
Decision Date

CaseChat Overview and Summary

Buyozo Pty Limited brought proceedings against Ku-ring-gai Council in the Supreme Court of New South Wales, alleging that the Council had breached its contractual obligations under a development agreement. Buyozo sought a declaration that the Council had failed to meet its obligations and to compensate the company for losses incurred as a result of the Council's actions.

The primary legal issues the court was required to determine were whether the Council had indeed breached the agreement and, if so, whether Buyozo was entitled to the relief sought. The court had to examine the terms of the development agreement, the Council's conduct in relation to the agreement, and the nature and extent of any losses suffered by Buyozo. Additionally, the court needed to consider whether the Council's actions constituted a breach of contract and whether Buyozo had a valid claim for damages.

The court held that the Council had indeed breached the development agreement by failing to fulfil certain obligations. The breach was found to be material, impacting Buyozo's ability to proceed with its planned developments. The court accepted that Buyozo had suffered losses as a direct result of the Council's failure to perform its contractual obligations. It was determined that Buyozo was entitled to compensation for these losses, and the court made a declaration that the Council had breached the agreement. The court ordered the Council to compensate Buyozo for the losses incurred, as well as to take specific steps to remedy the breach going forward.

The final orders, detailed at [46], included a declaration of breach, compensation for losses, and specific performance requirements for the Council to remedy the breach. The court also ordered the parties to negotiate in good faith to resolve any outstanding issues and directed the Council to take certain actions to ensure compliance with the development agreement.

Orders

Orders of the court

See orders at [46].

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

Ratio Decidendi

Legal Principle Established