Supreme Court
New South Wales
Medium Neutral Citation: Building Partners Pty Ltd v AEA Constructions Pty Ltd [2018] NSWSC 1033 Hearing dates: On the papers Date of orders: 04 July 2018 Decision date: 04 July 2018 Jurisdiction: Common Law Before: Fagan J Decision: The plaintiff’s costs of the proceedings including the cross-claim under the orders of 22 May 2018 are to be paid on the ordinary basis up to 23 December 2016 and on the indemnity basis from 24 December 2016.
Catchwords: COSTS – party/party – bases of quantification – indemnity costs – proceedings by employer for indemnity for workers compensation benefits paid – judgment in related proceedings finding negligence of defendant causing personal injury to worker – Calderbank offer made by plaintiff – where offer open for 5 weeks – where offer involved elements of compromise – where offer rejected by defendant – whether rejection unreasonable – costs awarded on indemnity basis from date of offer Legislation Cited: Workers Compensation Act 1987 (NSW) Cases Cited: Calderbank v Calderbank [1975] 3 All ER 333
Wharekawa v AEA Constructions Pty Ltd [2018] NSWSC 684Category: Costs Parties: Building Partners Pty Ltd (plaintiff)
AEA Constructions Pty Ltd (defendant)Representation: Counsel:
Solicitors:
Mr Morris SC/Mr John Catsanos (plaintiff)
Mr John Maconachie QC/Mr Mitchell Davis (defendant)
Stephen Lee, Stephen Lee Legal (plaintiff)
Bryan McMahon, McMahons Lawyers (defendant)
File Number(s): 2016/129877
Judgment
-
The plaintiff applies for an order that the defendant pay its costs of these proceedings, including the costs of the defendant’s cross-claim against the plaintiff, from 23 December 2016 to the conclusion of the proceedings on the indemnity basis. The proceedings involved a claim by the plaintiff for indemnity pursuant to s 151Z of the Workers Compensation Act 1987 (NSW) in respect of benefits the plaintiff had paid to Raymond Wharekawa, an employee. Mr Wharekawa claimed that he had been injured, whilst working for the plaintiff, as a result of negligence of the defendant which was performing construction work on an adjoining site. Mr Wharekawa’s action was heard together with the plaintiff’s claim for indemnity, in a joint trial.
-
On 17 May 2018 I published reasons (Wharekawa v AEA Constructions Pty Ltd [2018] NSWSC 684 – “the principal judgment”) for upholding both Mr Wharekawa’s claim for damages and the plaintiff’s claim for indemnity. I dismissed the defendant’s cross-claim against the plaintiff, in which the defendant had sought contribution to any judgment against it in favour of Mr Wharekawa. On 22 May 2018 I ordered that the defendant pay the plaintiff’s costs of these proceedings including the defendant’s cross-claim. I reserved to the plaintiff that it could make application regarding the scale at which costs should be assessed. On 24 May 2018 the defendant filed the notice of motion which is now before me.
-
The basis of the plaintiff’s claim for indemnity costs is that on 23 December 2016 its solicitors sent to the defendant’s solicitors a letter of the type considered in Calderbank v Calderbank [1975] 3 All ER 333. The letter…
Keep reading for free
Create a free CaseChat account to read Building Partners Pty Ltd v AEA Constructions Pty Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
Find similar cases
Other decisions on the same topics. Each opens in a new tab.
Details
- Case
- [2018] NSWSC 1033
- Decision Date
CaseChat Overview and Summary
The court was required to determine whether the defendant's rejection of the Calderbank offer was unreasonable and, if so, whether costs should be awarded on an indemnity basis from the date of the offer. The court examined the terms of the offer, the context in which it was made, and the defendant's reasons for rejecting it. The central issue was the assessment of the reasonableness of the defendant's decision to reject the offer and its impact on the costs order.
The court found that the defendant's rejection of the Calderbank offer was unreasonable, considering the terms of the offer and the circumstances at the time. The court concluded that the defendant's reasons for rejecting the offer were insufficient to justify the rejection. Consequently, the court awarded costs on an indemnity basis from the date of the offer. This decision underscores the importance of considering the reasonableness of rejecting a Calderbank offer and its implications for cost recovery in such circumstances.
Background
Background to the litigation
Decision
Reasons for decision
Ratio Decidendi