CITATION: Building Insurers' Guarantee Corporation v Touma [2010] NSWSC 4 HEARING DATE(S): 26 November 2009
JUDGMENT DATE :
13 January 2010JUDGMENT OF: Harrison J DECISION: Order that the first defendant's defence filed on 29 January 2009 be struck out with costs. CATCHWORDS: PRACTICE AND PROCEDURE – UCPR 12.7(2) – application to strike out defence where not conducted with due despatch – where defendant has failed to attend to orders for discovery – where plaintiff a stranger to the commercial transaction between the defendant and a third party from which the litigation arises - where proceedings effectively stalled until discovery completed – defence struck out LEGISLATION CITED: Civil Liability Act 2002
Civil Procedure Act 2005
Environmental Planning and Assessment Act 1979
Home Building Act 1989
Uniform Civil Procedure RulesCATEGORY: Procedural and other rulings CASES CITED: Aon Risk Services Australia Ltd v Australian National University [2009] HCA 27; (2009) 239 CLR 175
Micallef v ICI Australia Operations Pty Ltd [2001] NSWCA 274
Stollznow v Calvert [1980] 2 NSWLR 749PARTIES: Building Insurers' Guarantee Corporation (Plaintiff)
Daniel Touma (First Defendant/Cross Claimant)
Gold Holdings Pty Ltd (Second Defendant)
Summing Up Services Pty Ltd t/as A L Wood Engineer (Third Defendant/First Cross Defendant)
Burwood City Council (Second Cross Defendant)FILE NUMBER(S): SC 10984/2006 SOLICITORS: Mills Oakley Lawyers (Plaintiff)
DLA Phillips Fox (Second Cross Defendant)
IN THE SUPREME COURT
OF NEW SOUTH WALES
COMMON LAW DIVISIONHARRISON J
13 January 2010
JUDGMENT10984/2006 Building Insurers' Guarantee Corporation v Daniel Touma & Ors
1 HIS HONOUR: The plaintiff seeks an order by notice of motion filed on 18 September 2009 that Mr Touma's defence filed on 29 January 2009 be struck out pursuant to Uniform Civil Procedure Rule 12.7(2), because he has not conducted his defence with due despatch.
Background
2 In 1997 Mr Touma was a builder. In association with the second defendant he contracted, on or about 28 August that year, to construct 26 villas on land in Tangarra Street, Croydon Park. The third defendant allegedly provided design, supervision and periodic inspection and certification services with respect to the engineering components of the works. The fourth defendant is said to have inspected and certified the works pursuant to the Environmental Planning and Assessment Act 1979.
3 The second defendant owned the property and the villas that were constructed upon it. On approximately 11 August 1999 the Owners Corporation of Strata Plan 60805 became the owner of the common property. The plaintiff alleges that Mr Touma and the second defendant constructed the villas in a defective way that gave rise to a claim by the Owners Corporation against them for the costs of rectifying the defective work. When Mr Touma's insurer, HIH Casualty and General Insurance Ltd, failed in now well known circumstances, the plaintiff was called upon to indemnify the Owners Corporation as the beneficiary under a policy of insurance issued by HIH for the claims made upon its insured. This took the form of a claim by the Owners…
Keep reading for free
Create a free CaseChat account to read Building Insurers' Guarantee Corporation v Touma and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2010] NSWSC 4
- Decision Date
CaseChat Overview and Summary
The primary legal issue before the court was whether to grant the plaintiff's application to strike out the defendant's defence under UCPR 12.7(2) due to the defendant's failure to conduct the defence with due despatch. The court needed to consider whether the defendant's delay in attending to orders for discovery and the resultant stalling of the proceedings warranted the striking out of the defence. Additionally, the court needed to determine the relevance of the plaintiff's status as a stranger to the commercial transaction between the defendant and a third party.
The court found that the defendant's failure to comply with orders for discovery and the resultant delay in the proceedings justified the striking out of the defence. The court emphasised that the plaintiff, as a stranger to the commercial transaction, was entitled to efficient progress in the litigation. The court noted that the proceedings had effectively been stalled until the discovery was completed, which was not the fault of the plaintiff. Consequently, the court held that the defendant's failure to conduct the defence with due despatch warranted the striking out of the defence under UCPR 12.7(2).
The court ordered that the defendant's defence be struck out, allowing the plaintiff to proceed with the enforcement of the guarantee. The court further directed the defendant to comply with the orders for discovery and to ensure that the proceedings progressed without further delay.
Orders
Orders of the court
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi