PLANNING & ENVIRONMENT COURT OF QUEENSLAND
CITATION:
BTS Properties (Qld) Pty Ltd v Brisbane City Council & Ors [2015] QPEC 47
PARTIES:
BTS PROPERTIES (QLD) PTY LTD
(appellant)v
BRISBANE CITY COUNCIL
(respondent)and
MICHAEL O’BRIEN
(first co-respondent by election)and
CBD BRISBANE PTY LTD
(second co-respondent by election)and
FRANK RAYMOND DORRSTEIN and MARGARET JOAN DORRSTEIN
(third co-respondent by election)and
PETER BERNARD BYRNE
(fourth co-respondent by election)and
MARGARET ELIZABETH DAIGA
(sixth co-respondent by election)and
GARY GIBSON and MICHELLE GIBSON
(seventh co-respondent by election)FILE NO/S:
4099/2014
DIVISION:
Planning and Environment
PROCEEDING:
Hearing of an appeal
ORIGINATING COURT:
Planning and Environment Court of Queensland at Brisbane
DELIVERED ON:
1 October 2015
DELIVERED AT:
Brisbane
HEARING DATE:
20, 21, 24, 25, 26 and 28 August 2015
JUDGE:
R S Jones DCJ
ORDER:
1. The appeal is dismissed.
2. Any application concerning costs is to be made on or before 15 October 2015.
CATCHWORDS:
APPEAL – refusal of development application for material change of use for apartment building – City Plan 2000 – City Plan 2014 – where issues of height and bulk – where intrusion into waterway corridor – whether conflict with New Farm and Teneriffe Hill Local Plan – whether conflict with Waterway Code – whether sufficient grounds to warrant approval despite conflict
Sustainable Planning Act 2009, ss 314, 326, 493 and 495
Calvisi & Ors v Brisbane City Council & Ors (2009) QPELR 35
K Page Main Beach Pty Ltd v Gold Coast City Council & Ors (2011) QPELR 406
Purcell Family v Gold Coast City Council & Ors (2004) QPELR 521
WAW Developments Pty Ltd v Brisbane City Council [2015] QPEC 038
COUNSEL:
Mr M Williamson for the appellant
Mr B Job for the respondent
Mr A Skoien for the first co-respondent by election
Mr M Batty for the third, fourth, sixth and seventh co‑respondents by election
SOLICITORS:
MacDonnells Law for the appellant
Brisbane City Legal Practice for the respondent
Fox Certare Partners for the first co-respondent by election
Mr S Keliher of Milne Legal for the second co-respondent by election
Thynne & Macartney for the third, fourth, sixth and seventh co‑respondents by election
This proceeding was concerned with an appeal against the Brisbane City Council’s (“the Council”) refusal of a development application for a material change of use that, if approved, would have facilitated the development of a six to seven-storey apartment building in New Farm. For the reasons set out below, the orders of the Court are:
1. The appeal is dismissed.
2. Any application concerning costs is to be made on or before 15 October 2015.
Background
The subject land is situated at 9 Griffith Street, New Farm and is more properly described as Lots 5 and 6 on Registered Plan 8732. The total area of those two lots is 962m2. Broadly speaking, the lots run from Griffith Street to the Brisbane River in a trapezoidal shape in a generally south-westerly direction. The subject site is currently occupied by a…
Keep reading for free
Create a free CaseChat account to read BTS Properties (Qld) Pty Ltd v Brisbane City Council and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2015] QPEC 47
- Decision Date
CaseChat Overview and Summary
The central legal issues the court needed to resolve were whether the proposed development's height and bulk, and its impact on the waterway corridor, indeed conflicted with the relevant local plans and the Waterway Code. Additionally, the court had to assess if there were sufficient grounds to warrant approving the development despite these conflicts. The court considered the statutory framework and the principles of planning law to determine whether the council's decision was lawful and reasonable.
In dismissing the appeal, the court found that the council's decision to refuse the development application was well-founded. The proposed apartment building's height and bulk were considered excessive and inappropriate for the site, particularly given its location within the waterway corridor. The court concluded that the development would conflict with the objectives outlined in the New Farm and Teneriffe Hill Local Plan and the Waterway Code. The court held that these conflicts were significant enough to justify the council’s refusal, and there were no sufficient grounds to warrant approval despite these conflicts. Consequently, the appeal was dismissed, and any application concerning costs was to be made by 15 October 2015.
Orders
Orders of the court
1. The appeal is dismissed.
2. Any application concerning costs is to be made on or before 15 October 2015.