Brian Geaney Pty Ltd & Anor v Close Constructions Pty Ltd

Link copied
Case Copied 37 min read

SUPREME COURT OF QUEENSLAND

CITATION:                  Brian Geaney Pty Ltd & Anor v Close Constructions      Pty Ltd & Ors [2003] QSC 393

PARTIES:  BRIAN GEANEY PTY LTD ACN 010 651 546

(First Plaintiff)

and

THE PROPRIETORS 102 DENHAM STREET,            BUILDING UNITS PLAN NUMBER 100002

(Second Plaintiff)

v   

CLOSE CONSTRUCTIONS PTY LTD
  ACN 010 963 407   
  (First Defendant)
  and
  PAUL CRUICE ARCHITECT PTY LTD
  ACN 018 188 100
(Second Defendant)
  and
  CYRIL CASWELL
  (Third Defendant)

FILE NO:  S478 of 2002

DIVISION:  Trial Division

DELIVERED ON:         21 September 2003

DELIVERED AT:          Rockhampton

HEARING DATES:       28-29 November 2002, 24-28 March 2003, 16 June           2003, 23 June 2003 and 13-15 August 2003

JUDGE:   Dutney J

ORDERS:1.        Judgement for the plaintiffs against the   first, second and third defendants in the sum   of $18,000.00; 

2.        Judgement for the first plaintiff against   the first defendant in the further sum of   $51,529.00;

3.        The first defendant to indemnify the   second defendant in respect of the judgement   against the second defendant in the sum of   $3,600.00;

4.        The third defendant to indemnify the   second defendant in respect of the judgement   against the second defendant in the sum of   $7,200.00.

CATCHWORDS:           BUILDING AND ENGINEERING CONTRACTS - BREACH – COST OF RECTIFICATION WORKS  – where First Plaintiff entered into a design and construct contract with First Defendant – whether breach of implied conditions that the building would be constructed with the skill, care and competence of an ordinary builder and in accordance with good building practice

NEGLIGENCE – STANDARD OF CARE – REASONABLE FORESEEABILITY OF DAMAGE – APPORTIONMENT OF RESPONSIBILITY – where stud frame construction of building converted into a masonry construction – where First, Second and Third Defendants aware of this fact – whether First Defendant’s failure to advise First Plaintiff of consequences of not installing control joints negligent

ARCHITECTS, ENGINEERS AND SURVEYORS – ARCHITECTS – where architect designed a building to suit First Plaintiff’s business – where design was for a stud frame form of  construction – where architect became aware a different building material was being used – where architect’s retainer was to achieve council building approval - where First Defendant anticipated drawings with sufficient detail to build from – whether lack of detail on drawings had a causal connection with loss suffered by plaintiff – whether Second Defendant negligent in not seeking modification of engineer’s footing and slab plan to suit new building material

ARCHITECTS, ENGINEERS AND SURVEYORS – ENGINEERS – where engineer produced inter alia a footings and slab design  - where engineer became aware a new building material was being used – whether failure to alter design to suit new building material negligent – where engineer certified various parts of the works on the building 

Haines v Bendall (1991) 172 CLR 60, followed

Voli v Inglewood Shire Council (1963) 110 CLR 74, followed

COUNSEL:PO Land for the Plaintiff (28-29 November 2002, 24-28 March 2003, 16 June 2003, 23 June 2003

IR Perkins for the Plaintiff (13-15 August 2003)

MB Smith for the First…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Brian Geaney Pty Ltd & Anor v Close Constructions Pty Ltd and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2003] QSC 393
Decision Date

CaseChat Overview and Summary

The plaintiffs, Brian Geaney Pty Ltd and The Proprietors 102 Denham Street, Building Units Plan Number 100002, filed suit against the defendants, Close Constructions Pty Ltd, Paul Cruice Architect Pty Ltd, and Cyril Caswell, alleging breach of contract and negligence in the construction of a building. The defendants were found liable for various defects in the building, including inadequate lateral support, lack of control joints, and insufficient foundation design. The court held that the defendants breached their contractual and tortious duties by not constructing the building with the required skill, care, and competence, and in accordance with good building practice. The plaintiffs were awarded damages for the cost of rectification works, diminution in value of the building, and disruption to the plaintiffs' business due to the defects. The court also ordered the first defendant to indemnify the second defendant for a portion of the judgment against the second defendant, and the third defendant to indemnify the second defendant for the remaining portion. The final orders included judgments against the defendants for the specified sums, along with the indemnity orders.

Orders

Orders of the court

Full text does not contain this section.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.