Boughton v Masterton Homes Pty Ltd

Link copied
Case Copied 9 min read

Supreme Court


New South Wales

Medium Neutral Citation: Boughton v Masterton Homes Pty Ltd [2022] NSWSC 1556
Hearing dates: 4 November 2022
Date of orders: 4 November 2022
Decision date: 04 November 2022
Jurisdiction:Equity - Technology and Construction List
Before: Rees J
Decision:

Refuse leave to issue cross-claim.

Catchwords:

CIVIL PROCEDURE – cross-claims – application by builder to file cross-claim against engineer – principles at [15]-[16] – engineering problem identified from outset – defendant identified engineer as concurrent wrongdoer two years’ earlier – inadequate explanation for delay – granting leave would result in substantial delay – leave refused.

Legislation Cited:

Home Building Act 1989 (NSW)

Cases Cited:

Aon Risk Services Pty Ltd v Australian National University (2009) 239 CLR 175; [2009] HCA 27

Rush v Nationwide News Pty Ltd (No 2) [2018] FCA 550; (2018) 359 ALR 564

Tamaya Resources Ltd (in liq) v Deloitte Touche Tohmatsu (a firm) [2015] FCA 1098

Category:Procedural rulings
Parties: Bruce Boughton (First Plaintiff//Respondent)
Marianela Ferreiro (Second Plaintiff/Respondent)
Masterton Homes Pty Ltd (Defendant/Applicant)
Representation:

Counsel:
Mr S Sykes (Plaintiffs/Respondents)
Mr A Hourigan (Defendant/Applicant)

Solicitors:
William Cotsis & Associates (Plaintiffs/Respondents)
Clyde & Co Lawyers (Defendant/Respondent)
File Number(s): 2020/218709

EX TEMPORE Judgment

  1. HER HONOUR: This is an application by the defendant, Masterton Homes Pty Ltd, for leave to file and serve a Technology and Construction List Cross-Claim Statement against structural engineer, Rafeletos Zanuttini Pty Ltd.

  2. The application for leave is opposed by the plaintiffs, Bruce Boughton and Marianella Ferreiro, who commissioned Masterton Homes to build their home. This application comes very late in the piece.

Procedural history

  1. In December 2013, the plaintiffs entered into a building contract with Masterton Homes to build their home for some $290,000. The building was completed in about November 2014.

  2. In August 2019, the plaintiffs commenced proceedings in the NSW Civil and Administrative Tribunal (NCAT) in respect of alleged building defects. The main defect was said to be defects in the concrete floor slab. Mr Boughton prepared an affidavit in support of the claim in February 2020 and, from February to July 2020, the plaintiffs obtained expert reports from a surveyor, geotechnical engineer, structural engineer and expert builder. In July 2020, NCAT made an order transferring the proceedings to this Court, as the quantum of the plaintiffs' claim was then thought to exceed the jurisdictional limit of the Tribunal.

  3. On 8 October 2020, the plaintiffs filed a Summons and a Technology and Construction List Statement, which identified that a key issue in dispute was a suggested defect in the concrete floor slab which was such that the plaintiffs' home required demolition and rebuilding. On 5 November 2020, the defendant filed its Technology and Construction List Response, which denied that the works were defective but also pleaded (at [11]): (emphasis added)

In answer to the whole of the Plaintiffs claim, if contrary to its Contentions in this List Response, the Defendant is found to be liable to the Plaintiffs (which is denied), then:

a. the Plaintiffs’ claim…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Boughton v Masterton Homes Pty Ltd and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2022] NSWSC 1556
Decision Date

CaseChat Overview and Summary

In the case of Boughton v Masterton Homes Pty Ltd, the plaintiff sought to hold the builder responsible for defects in a residential property, while the builder sought to bring a cross-claim against the engineer for the same defects. The dispute was heard in the Supreme Court of Queensland. The builder applied for leave to file a cross-claim against the engineer, arguing that the defects were a result of the engineer's design and advice. The plaintiff opposed the application, arguing that the builder had unreasonably delayed in bringing the cross-claim and that granting leave would cause substantial delay to the proceedings.

The court considered whether to exercise its discretion to grant leave for the builder to file a cross-claim against the engineer. The court noted that the builder had identified the engineer as a potential concurrent wrongdoer two years earlier, but had not taken any steps to bring a cross-claim until after the plaintiff had filed their statement of claim. The court also considered the principles set out in previous cases, which emphasised the importance of bringing cross-claims promptly and providing adequate explanation for any delay. The court found that the builder's explanation for the delay was inadequate and that granting leave would result in substantial delay to the proceedings. The court therefore refused the builder's application for leave to file a cross-claim.

The court held that the principles set out in previous cases regarding cross-claims applied to this case. The court found that the builder had failed to provide an adequate explanation for the delay in bringing the cross-claim and that granting leave would result in substantial delay to the proceedings. The court noted that the delay had already caused prejudice to the plaintiff, who had not had the opportunity to defend against the potential cross-claim. The court therefore refused the builder's application for leave to file a cross-claim against the engineer. The court's decision was based on the specific circumstances of the case, including the delay in bringing the cross-claim and the lack of adequate explanation for that delay.

Orders

Orders of the court

Full text does not contain this section.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.