Body Corporate for 101 Albatross Ave CTS 34250 v Advance Fire Technology Pty Ltd

Link copied
Case Copied 22 min read

QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL


CITATION:

Body Corporate for 101 Albatross Ave CTS 34250 v Advance Fire Technology Pty Ltd [2025] QCAT 461

PARTIES:

BODY CORPORATE FOR 101 ALBATROSS AVE CTS 34250

(APPLICANT)

v

ADVANCE FIRE TECHNOLOGY PTY LTD

(RESPONDENT)

APPLICATION NO/S:

BDL026-24

MATTER TYPE:

Domestic Dispute

DELIVERED ON:

18 November 2025

HEARING DATE:

On the papers

DECISION OF:

Member S M Burke

ORDERS:

The Respondent, Advance Fire Technology Pty Ltd, is to make payment to the Applicant the sum of 10,568.04 on or before 5 January 2026.

CATCHWORDS:

CONTRACTS – BUILDING, ENGINEERING AND RELATED CONTRACTS – PROFESSIONS AND TRADES – where written contract not signed by the parties – whether commercial building contract void or voidable – whether terms of the contract enforceable – in the alternative contract determined by conduct of the parties – whether claim for direct costs incurred by owner available

Queensland Building and Construction Commission Act 1991 (Qld), s 30AC, s 67A, s 67AAA, s 67E, s 67 G, Schedule 1B s 14(2), s 14(10)

Cerda v Jacob [2020] QCATA 57
PRA Electrical Pty Ltd v Perserverance Exploration Pty Ltd & Anor [2007] VSCA 310

West Roofing and Plumbing Pty Ltd v JBBK Construction Pty Ltd [2025] QCAT 416

APPEARANCES & REPRESENTATION:

This matter was heard and determined on the papers pursuant to s 32 of the Queensland Civil and Administrative Tribunal Act2009 (Qld)

REASONS FOR DECISION

  1. Pursuant to an application for a commercial building dispute filed 17 January 2024, Dr Paul Varcoe, of Unit 1 101 Albatross Avenue, Mermaid Beach, Queensland made the following claims, as representative of the Body Corporate Committee for 101 Albatross Avenue CTS 34250:

    (a)reimbursement for services that were paid for but not completed according to the Fire Safey Standards;

    (b)reimbursement for the Inspection (Audit) and Remediation Work that was required so that 101 Albatross Avenue met all safety compliancy requirements;

    (c)reimbursement for additional services performed during the period that the contracted services were not completed to the required Standards.

  2. The Respondent, Advanced Fire Technology Pty Ltd, is a unit of the Advance Group of Companies (Qld) Pty Ltd with a Queensland Building and Construction Commission (“QBCC”) licence number 745715.

  3. The dispute between the parties involved the maintenance of fire protection equipment installed at 101 Albatross Avenue, Mermaid Beach, Queensland (“the property”).

  4. In the initial application, the Applicant claimed the sum of $22,642.17, being direct costs of $12,742.09 and rectification costs of $9,900.08.

  5. The amended amount claimed by the Applicant was filed with the Applicant’s material on 2 September 2024. The amount claimed has been reduced to $10,188.54, being direct costs of $9,446.04 and repair costs for the original faulty installation of the fire panel, being $742.50.

    Compliance with Directions

  6. On 17 January 2024, the Applicant filed its application for a commercial building dispute.

  7. On 29 January 2024, the Tribunal delivered directions regarding the following:

    (a)the proper Applicant being Body Corporate 101 Albatross Ave CTS 34250 rather than Paul Varcoe;

    (b)the filing of written evidence on which the Applicant…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Body Corporate for 101 Albatross Ave CTS 34250 v Advance Fir... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details

Case
[2025] QCAT 461
Decision Date

CaseChat Overview and Summary

In the case of Body Corporate for 101 Albatross Ave CTS 34250 v Advance Fire Technology Pty Ltd, the primary issue before the court was the enforceability of an unsigned contract and the subsequent claim for direct costs incurred by the body corporate due to the Respondent’s failure to complete essential fire safety services. The Applicant alleged that the Respondent had breached a contract for fire services by not complying with Australian Standards and failing to complete necessary maintenance. The Respondent, Advance Fire Technology Pty Ltd, did not contest the provision of services but argued that the unsigned contract was not legally binding.

The court had to determine whether the unsigned contract was void or voidable, and if it was enforceable, whether the terms of the contract could be determined by the conduct of the parties. Additionally, the court needed to assess if the Applicant could claim direct costs incurred as a result of the Respondent's failure to adhere to the agreed terms. The court examined the conduct of the parties, including the provision of services and payment in line with the contract's terms, despite the lack of a formal written agreement.

The court concluded that although the contract was not formally signed, the conduct of the parties demonstrated an intention to be bound by the terms. The court held that the contract was enforceable and the Respondent was liable for the incomplete services. It found that the Applicant was entitled to claim direct costs incurred due to the Respondent's failure to perform the required fire safety services. The court ordered Advance Fire Technology Pty Ltd to pay the sum of $10,568.04 to the Applicant by 5 January 2026.

Orders

Orders of the court

The Respondent, Advance Fire Technology Pty Ltd, is to make payment to the Applicant the sum of 10,568.04 on or before 5 January 2026.

Background

Background to the litigation

Evidence

Evidence before the court

The distinction between a domestic building contract and a commercial building contract is thus very important when examining the repercussions for the parties when a contract is written but not signed or an agreement is simply not in a written form at all.Evidence provided by the Applicant The Applicant’s original claim arose from a breach of contract claiming direct costs and rectification costs in the sum of $22,642.17. The Applicant relied upon an unsigned contract which was provided by the Respondent on or about 24 April 2020. The parties did not sign the contract dated 24 April 2020 but did carry on with the provision of services and payment in accordance with the terms of the agreement. The contract related to the provision of fire services at the property commencing on an unknown date (after 24 April 2020) in 2020. The Applicant submits that there was an obligation on the Respondent to comply with the relevant Australian Standards, particularly AS1851-2012 and the Fire Safety Maintenance Schedule as advertised on the Respondent’s website. Following on from a Defect Notice from the Queensland Fire and Emergency Services issued on 22 September 2021 regarding the hydrant diesel pumpset malfunction at the property, the Applicant sought multiple solutions for the malfunction issues and eventually organized a complete fire services audit. As a result, the Applicant became aware of a series of defective issues or incomplete work carried out by the Respondent on the receipt of an independent report prepared by Dayshelf Fire Services (“Dayshelf”) on 18 January 2023. On 18 January 2023, Bright & Duggan (“B&D”), the strata administrator for the Applicant, wrote to the Respondent advising that their services to complete the servicing of the fire infrastructure were no longer required. Further on 21 March 2023, B&D set out the items of incomplete work undertaken by the Respondent despite invoices being issued for such:(a)seven fire hoses not tested since June 2021 and one not since June 2020 when the requirement was for six monthly testing;(b)eight fire hydrant landing valves not tested since June 2021 when the requirement was six monthly;(c)one twin landing valves not tested since June 2021 when the requirement was six monthly;(d)one booster valve not tested since June 2021 when the requirement was six monthly;(e)one PCP extinguisher not tested since June 2021 when the requirement was six monthly;(f)annual diesel service not done since 15 October 2021 when requirement was annually;(g)lights seem to have never been tested but on recent testing 21 failed. The requirements for testing was six monthly. Further B&D advised the Respondent that the testing of the hydrant diesel motor was not complete but rather it was logged as being “offline” despite the motor being in working, although leaking, condition. B&D stated that the contract in place was to undertake the required monthly, six monthly and annual services and from the list above the service commitment had not been fulfilled and exposed the building to a fire safety risk. A report from Dayshelf to support this was attached.

Decision

Reasons for decision

Ratio Decidendi

Legal principle established