Board of Professional Engineers v Hart

Link copied
Case Copied 16 min read
CITATION: Board of Professional Engineers v Hart [2013] QCAT 689
PARTIES: Board of Professional Engineers
(Applicant)
v
John Hart
(Respondent)
APPLICATION NUMBER: OCR176-11
MATTER TYPE: Occupational regulation matters
HEARING DATE: On the papers
HEARD AT: Brisbane
DECISION OF: Member McLennan
DELIVERED ON: 20 December 2013
DELIVERED AT: Brisbane
ORDERS MADE:

1.    Mr Hart is reprimanded;

2.    The penalty of $5,000 is imposed upon Mr Hart such amount to be paid in three equal monthly instalments of $1,666.66 with:

a.    the first instalment is to be paid within 3 business days of this order; and

b.    the second instalment is to be paid within 30 days of this order; and

c.    the third instalment is to be paid within 60 days of this order;

3.    Should the penalty or any part thereof not be paid by the dates stated in this order, Mr Hart’s registration is suspended until the earlier of the date the amount is paid or the day registration expires; and

4.    Each party bears its own costs.

CATCHWORDS:

Occupational regulation matter – Disciplinary proceedings – civil and structural engineering – unsatisfactory professional conduct – reprimand

Professional Engineers Act 2002

Adamson v Queensland Law Society Inc. [1990] 1 Qd R 498
Board of Professional Engineers of Queensland v Zaranis [2009] CCT ED001-09
Board of Professional Engineers of Queensland v Matiukevitch [2006] CCT K002-05
Board of Professional Engineers of Queensland v Enzo Bartilomo [2006] CCT ED008-05

APPEARANCES and REPRESENTATION (if any):

This matter was heard and determined on the papers pursuant to s.32 of the Queensland Civil and Administrative Tribunal Act 2009 (QCAT Act).

REASONS FOR DECISION

  1. This is a disciplinary proceeding brought in the Queensland Civil and Administrative Tribunal (Tribunal) by the Board of Professional Engineers of Queensland (the Applicant) against Mr John Hart (the Respondent) who at all material times was a registered professional engineer in Queensland under the Professional Engineers Act 2002 (the Act) and principal of Acame Pty Ltd (Acame).

  2. The Applicant is established under s 77 of the Act and relied upon the  following material filed in the Tribunal:

    a)    Application or referral – disciplinary proceeding filed 9 August 2011;

    b)    Affidavit of Katherine Clare Murray filed 9 August 2011;

    c)    Affidavit of Katherine Clare Murray filed 19 April 2013; and

    d)    Statement of Agreed Facts dated 23 October 2013.

  3. The Respondent relied upon the affidavit of John Hart sworn on 29 July 2013.[1]

    [1]Appendix A Statement of Agreed Facts attached to this decision: signed by the Applicant on 23 October 2013 and by the Respondent on 24 October 2013.

  4. The Respondent was registered as a professional engineer (RPEQ 7021), under the Act on 17 August 2004 and has continuously held registration since that date.  At the relevant times the Respondent was practising as a registered professional engineer in the area described as ‘civil and structural engineering’ – being areas recognised under s 7A of the Act. 

  5. The Respondent’s work, to which this proceeding relates, was work of the kind expected to be…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Board of Professional Engineers v Hart and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2013] QCAT 689
Decision Date

CaseChat Overview and Summary

In the case of Board of Professional Engineers v Hart, the Board of Professional Engineers sought disciplinary action against Mr Hart, a professional engineer. The dispute centred around Mr Hart's issuance of two Compliance Certificates for Building Design or Specification for a kit house in Burnett Heads, Queensland. The Board contended that Mr Hart's actions were unprofessional and that he should be subject to disciplinary penalties. The matter was heard and determined by the Queensland Civil and Administrative Tribunal (QCAT).

The legal issues before QCAT were whether Mr Hart's conduct warranted disciplinary action and, if so, what the appropriate penalty should be. The primary focus was on whether Mr Hart breached professional standards by issuing a Compliance Certificate without ensuring that the structural design met the required safety standards. Additionally, the court had to consider the appropriate penalty given the agreed facts and submissions from both parties.

QCAT found that Mr Hart's actions constituted professional misconduct. The Tribunal was satisfied that Mr Hart issued the Compliance Certificates without properly verifying that the structural design complied with the necessary regulations. This was particularly concerning given the urgency and the potential safety risks involved. The court took into account the agreed facts, the joint submissions, and the acknowledgment by Mr Hart that his certification and accompanying letter were not appropriate. Consequently, QCAT determined that a formal reprimand was the appropriate disciplinary measure.

In conclusion, QCAT issued a formal reprimand against Mr Hart for his professional misconduct in issuing the Compliance Certificates without adequate verification. This decision serves as a reminder of the importance of adhering to professional standards and the potential consequences of failing to do so.

Orders

Orders of the court

Full text does not contain this section.

Background

Background to the litigation

For the purpose of this proceeding, the parties filed a Statement of Agreed Facts[2] which constitutes the factual matrix. Joint Submissions of the Applicant and the Respondent[3] in relation to penalty were filed. By consent and in reliance on these documents, the parties sought orders of the Tribunal. The parties consented to this matter being determined on the papers.[2]Appendix A Statement of Agreed Facts attached to this decision: signed by the Applicant on 23 October 2013 and by the Respondent on 24 October 2013.[3]Appendix B Joint Submissions of the Applicant and the Respondent attached to this decision: signed by the Applicant on 23 October 2013 and by the Respondent on 24 October 2013.Facts On the basis of the Statement of Agreed Facts I find that: On or about 18 June 2009, the Respondent performed professional engineering services by issuing a Compliance Certificate for Building Design or Specification (First Design Certificate) in relation to the structural design drawings (sheets) 1 – 9 of the Building (First Drawings) for the purposes of s 10 of the Building Act 1975 (BAct) and/or s 46 of the Building Regulation 2006 (Regulation). On a date unknown, but understood to be in June 2009, Ms Vickie Williams engaged an unnamed Builder to erect a steel framed kit house supplied by Stone Homes at 31 Duffey Street, Burnett Heads, near Bundaberg in Queensland (Building). The Respondent asserted that in or about October 2009, he was asked by Stone Homes to upgrade the design of the Building to achieve compliance with terrain category 2 region C loading conditions. He was further informed by Stone Homes that urgent remedial action needed to be considered and that Stone Homes would supply additional trusses and hold downs at a later date. The Respondent undertook the certification of the Building to facilitate the owner of the property pending completion of proper remediation works. A review of the Building and design was undertaken and, as a result of the review, the Respondent wrote a letter relating to the Building dated 23 September 2009 addressed “To Whom It May Concern”. In that letter, the Respondent advised methods to improve the purlin capacity to a structurally acceptable level to support the calculated loads. On about 22 October 2009, the Respondent performed professional engineering services by issuing a Compliance Certificate for Building Design or Specification (Second Design Certificate) in relation to the structural design drawings (sheets 1 – 20) (Second Drawings) for the purposes of s 10 of the BAct and/or s 46 of the Regulation. By issuing the First Design Certificate and pursuant to s 46 of the Regulation, the Respondent certified that the Building Design or Specification set out in the Certificate, if installed or carried out under the Certificate, would comply with the Building Assessment provisions including the BAct. The Respondent recognises and accepts that the aforesaid certification and letter were not appropriate.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.