JURISDICTION : SUPREME COURT OF WESTERN AUSTRALIA
IN CHAMBERS
CITATION: BLUEWATERS POWER 2 PTY LTD -v- AUSTRALIAN ENERGY MARKET OPERATOR LTD [2017] WASC 98
CORAM: LE MIERE J
HEARD: 7 MARCH 2017
DELIVERED : 13 APRIL 2017
FILE NO/S: CIV 1252 of 2017
BETWEEN: BLUEWATERS POWER 2 PTY LTD
Plaintiff
AND
AUSTRALIAN ENERGY MARKET OPERATOR LTD
First DefendantAUSTRALIAN ENERGY MARKET OPERATOR LTD IN ITS CAPACITY AS SYSTEM MANAGEMENT
Second Defendant
Catchwords:
Wholesale electricity sales contract - Proper construction - Whether Outage Plan can be submitted in respect of an outage that has already commenced - Turns on own facts
Legislation:
Electricity Industry (Wholesale Energy Market) Regulations 2004 (WA), reg 2, reg 5, reg 6(2), reg 6(6)
Electricity Industry Act 2004 (WA), s 122, s 123
Interpretation Act 1984 (WA), s 42, s 43(1) - (5), s 43(7) - (9), s 44, s 48, s 48A, s 50(1), s 53, s 55, s 56, s 58, s 59, s 75, s 76, pt VIII
Result:
Action dismissed
Category: B
Representation:
Counsel:
Plaintiff: Mr C G Colvin SC & Mr R G Lilly
First Defendant : Mr C A Moore SC & Mr N M Bender
Second Defendant : Mr C A Moore SC & Mr N M Bender
Solicitors:
Plaintiff: Johnson Winter & Slattery
First Defendant : Holman Fenwick Willan
Second Defendant : Holman Fenwick Willan
Case(s) referred to in judgment(s):
Alcan (NT) Alumina Pty Ltd v Commissioner of Territory Revenue [2009] HCA 41; (2009) 239 CLR 27
Certain Lloyd's Underwriters Subscribing to Contract No IH00AAQS v Cross (2012) 248 CLR 378
NBN Co Ltd v Pipe Networks Pty Ltd (2015) 295 FLR 256
News Ltd v Australian Rugby Football League Ltd (1996) 64 FCR 410
Wellington Capital Ltd v Australian Securities and Investments Commission (2014) 254 CLR 288
LE MIERE J:
Summary
The issue in this case is the construction of the Wholesale Electricity Market Rules (Market Rules). The Wholesale Electricity Market covers wholesale electricity sales within the South West Interconnected System (SWIS) between sellers (generators) and buyers (retailers and large users). The SWIS is the primary electricity grid in Western Australia. It supplies the bulk of the south west region. The plaintiff, Bluewaters, owns and operates a coal fired baseload power generating unit in Collie (BW2 Facility) which is capable of producing up to 217 MW of electricity for delivery into the SWIS. The defendant, AEMO, is the operator of the Wholesale Electricity Market and acts as System Management under the Market Rules. The primary function of AEMO as System Management is to ensure that the SWIS operates in a secure and reliable manner.
On 13 January 2017 the BW2 Facility suffered a trip (Trip Event) and has been out of service since. It will be necessary for Bluewaters to undertake substantial repairs to the facility before it can be brought back into service. The repairs are likely to take four to six months. The Market Rules distinguish between three types of outages: a Planned…
Keep reading for free
Create a free CaseChat account to read Bluewaters Power 2 Pty Ltd v Australian Energy Market Operat... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2017] WASC 98
- Decision Date
CaseChat Overview and Summary
The Court considered the language of the contract and relevant precedent. It was established that the contract did not explicitly prohibit the submission of an Outage Plan after an outage had commenced. However, the Court noted that the contract's purpose was to facilitate the planning and management of electricity supply and demand. The Court held that the contract must be construed in a manner that aligns with this purpose, and that the Outage Plan mechanism was intended to provide advance notice to enable effective planning. The Court concluded that submitting an Outage Plan post-commencement could undermine the contract's purpose and the market's stability. Therefore, the Outage Plan could not be submitted in respect of an outage that had already commenced.
The Court's decision was grounded in the contract's purpose and the factual context of the case. The Court held that the contract did not allow for Outage Plans to be submitted after an outage had commenced. The Court's reasoning was that such a submission could disrupt the market's stability and planning process. The Court did not find in favour of Bluewaters Power 2 Pty Ltd and dismissed their claim against the Australian Energy Market Operator Ltd.
Orders
Orders of the court
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi