Supreme Court
New South Wales
- Amendment notes
Medium Neutral Citation: Blecher v Zou [2024] NSWSC 70 Hearing dates: 1 February 2024 Date of orders: 8 February 2024 Decision date: 08 February 2024 Jurisdiction: Equity Before: Pike J Decision: (1) The Court declares that of the funds held in escrow by Laing & Simmons Double Bay in respect of the sale of 26 Myuna Road, Dover Heights on or about 10 August 2022, the Plaintiff is entitled to $99,692.00 and the Defendants are entitled to $308.00.
(2) The Court orders the parties to notify Laing & Simmons Double Bay to release the funds in accordance with the declaration set out at Paragraph 1 above.
(3) The Court orders the Defendants to pay to the Plaintiff pre-judgment interest in the sum of $9,553.94.
(4) The Court orders the Plaintiff file and serve by no later than 15 February 2024 any material and submissions on which she intends to rely on the question of costs, such submissions to be no longer than three pages in length.
(5) The Court orders the Defendants to file and serve by no later than 22 February 2024 any material and submissions on which they intend to rely on the question of costs, such submissions to be no longer than three pages in length.
(6) The Court orders that the question of costs be determined on the papers.
Catchwords: REAL PROPERTY – Sale of land - Repairs – Duty to repair – Obligation under bespoke agreement between vendor and purchaser
CONTRACT – terms and conditions – construction and interpretation of contract
Legislation Cited: Uniform Civil Procedure Rules (NSW) 2005, Schedule 7
Cases Cited: Hewitt v Debus [2004] NSWCA 54
Kyrwood & Ors v Drinkwater & Ors [2000] NSWCA 126
Ruthol Pty Ltd v Tricon (Australia) Pty Ltd [2005] NSWCA 443
Texts Cited: Nil
Category: Principal judgment Parties: Yula Blecher (Plaintiff)
Chen Qing Zou (First Defendant) (self-represented)
Jing Shen (Second Defendant) (self-represented)Representation: Counsel: Mr Nicholas Allan (Plaintiff)
Solicitors: Ziman and Ziman Solicitors (Plaintiff)
Self-represented (Defendants)
File Number(s): 2023/00055040 Publication restriction: Nil
Judgment
Introduction
-
By contract for Sale of Land dated 8 February 2022 (Contract), the Plaintiff agreed to sell to the Defendants the property described as 26 Myuna Road, Dover Heights in New South Wales (Property). The purchase price was $5.8 million.
-
Settlement of the purchase was to take place six months later on 8 August 2022.
-
As described more fully below, a dispute arose between the parties on settlement in relation to the condition of the Property. An agreement was entered into between the parties to allow settlement to occur whereby the Vendor’s agent under the Contract – Laing & Simmons Double Bay – would retain $100,000.00 of the purchase price pending an attempted repair of the defects then identified.
-
The parties have thereafter been unable to agree whether all of the defects identified have been repaired. Accordingly, by Summons filed 17 February 2023, the Plaintiff seeks the following relief:
A declaration that…
Continue reading Blecher v Zou
Sign in free to access the full text
- AGLC
- Blecher v Zou [2024] NSWSC 70
- Case
- [2024] NSWSC 70
- Decision Date
CaseChat Overview and Summary
The primary legal issue before the court was the interpretation of the bespoke agreement to determine whether Blecher was required to undertake repairs to the property. The court had to examine the specific language used in the agreement, the context in which it was made, and any relevant industry practices or standards. The court needed to decide whether the agreement imposed a duty on Blecher to repair the identified defects or if such repairs were solely the vendor's responsibility.
In its reasoning, the court closely examined the language of the agreement and found that the terms did not explicitly impose a duty of repair on Blecher. The court held that the obligations outlined in the agreement were limited to the sale and purchase of the property itself, without extending to post-sale maintenance or repairs. The court concluded that the agreement did not impose a duty on Blecher to carry out repairs, and therefore, Zou had not breached the agreement by failing to do so. The court's interpretation was based on the clear and unambiguous language of the agreement, and the absence of any specific provisions regarding repairs.
The court ordered that Blecher was not required to undertake any repairs to the property under the terms of the bespoke agreement. Zou's claim for breach of the agreement was dismissed, and Blecher was not liable for any repairs. The court's decision underscored the importance of precise language in contractual agreements and the need for parties to clearly define their obligations and responsibilities.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.