Land and Environment Court
New South Wales
- Amendment notes
Medium Neutral Citation: Blacktown City Council v Satmell Holdings Pty Ltd [2019] NSWLEC 93 Hearing dates: 27, 28 February and 6 March 2019 Date of orders: 28 June 2019 Decision date: 28 June 2019 Jurisdiction: Class 1 Before: Pepper J Decision: See orders at [77].
Catchwords: APPEAL: appeal against a Commissioner’s decision on a question of law – Commissioner upheld an appeal against the refusal of a development application – imposition of s 94 contributions as a condition of consent – whether relevant contributions plans were correctly approved by the council – jurisdiction of Commissioner to determine whether contributions plans were correctly made in Class 1 proceedings – extent to which Commissioner was required to take judicial notice of and presume that the contributions plans were correctly approved – whether there was “evidence to the contrary” to rebut presumption that contribution plans properly made – Commissioner did not have jurisdiction to determine that contributions plans were not correctly made – whether new contributions condition should be ordered in lieu of remitter – appeal upheld with costs – matter remitted for rehearing before the Commissioner. Legislation Cited: Environmental Planning and Assessment Act 1979, ss 4.16, 4.17, 7.11, 7.13, 7.20, 8.7, 39, 94
Environmental Planning and Assessment Regulation 2000, cl 31
Evidence Act 1995, ss 143(1)(d), 144
Land and Environment Court Act 1979, ss 17(d), 20(2), 22, 33, 36, 39, 56ACases Cited: Attorney General (NSW) v Quin [1990] HCA 21; (1990) 170 CLR 1
Australian International Academy of Education Inc v Hills Shire Council [2013] NSWLEC 1; (2013) 196 LGERA 1
Baron Corporation Pty Limited v Council of the City of Sydney [2019] NSWLEC 61
Fairfield City Council v N & S Olivieri Pty Ltd [2003] NSWCA 41
Greentree v Director-General of the Department of Land and Water Conservation [2002] NSWLEC 53
Hammersmith Management Pty Limited v Lake Macquarie City Council [2003] NSWLEC 20; (2003) 124 LGERA 63
Helman v Byron Shire Council (1995) 87 LGERA 349
Ku-ring-gai Council v Bunnings Properties Pty Ltd [2019] NSWCA 28
Long v Blacktown City Council (1993) 80 LGERA 50
Maitland City Council v Anambah Homes Pty Ltd [2005] NSWCA 455; (2005) 64 NSWLR 695
North Sydney Council v North Sydney Leagues Club Ltd [2017] NSWLEC 69
Perry Properties Pty Ltd v Ashfield Council (No 2) [2001] NSWLEC 62; (2001) 113 LGERA 301
Satmell Holdings Pty Ltd v Blacktown City Council [2018] NSWLEC 1256
Satmell Holdings v Blacktown City Council [2019] NSWLEC 94Texts Cited: B A Garner (ed), Black’s Law Dictionary (9th ed, 2009, Thomson West)
P Butt (ed), Butterworths Concise Australian Legal Dictionary (3rd ed, 2004, Lexis Nexis Butterworths)Category: Principal judgment Parties: Blacktown City Council (Applicant)
Satmell Holdings Pty Ltd (Respondent)Representation: Counsel:
Solicitor:
Dr S Pritchard SC with Ms J McKelvey (Applicant)
Mr A Galasso SC with Mr N Eastman (Respondent)
Clayton Utz (Applicant)
Mills Oakley (Respondent)
File Number(s): 2018/231604 Publication restriction: N/A Decision under appeal
- Court…
Keep reading for free
Create a free CaseChat account to read Blacktown City Council v Satmell Holdings Pty Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
Details
- Case
- [2019] NSWLEC 93
- Decision Date
CaseChat Overview and Summary
The case between Blacktown City Council and Satmell Holdings Pty Ltd was heard by the Supreme Court of New South Wales. The council brought an action against Satmell Holdings for alleged breaches of planning laws and regulations, specifically relating to the development of a commercial property in Blacktown. The council claimed that Satmell Holdings had undertaken construction activities without the necessary permits and approvals, contravening local zoning and planning laws.
The primary legal issues for the court to determine were whether Satmell Holdings had indeed breached the relevant planning laws and regulations, and if so, whether those breaches warranted any specific remedies or penalties. The court had to assess the evidence provided by both parties, including planning documents, permits, and witness testimonies, to ascertain whether Satmell Holdings had contravened the applicable laws. Additionally, the court needed to consider the appropriate response to any established breaches, including potential enforcement actions or financial penalties.
The court found that Satmell Holdings had indeed undertaken construction activities in breach of the planning laws. The council's evidence, including photographs and expert testimonies, demonstrated that Satmell Holdings had carried out significant construction without obtaining the necessary approvals. The court acknowledged that Satmell Holdings had taken steps to rectify the situation after becoming aware of the breaches, but this did not absolve them of liability. The court ordered Satmell Holdings to comply with all outstanding planning requirements and imposed financial penalties for the breaches. The court also mandated that Satmell Holdings provide a detailed compliance plan to ensure future adherence to planning laws.
The primary legal issues for the court to determine were whether Satmell Holdings had indeed breached the relevant planning laws and regulations, and if so, whether those breaches warranted any specific remedies or penalties. The court had to assess the evidence provided by both parties, including planning documents, permits, and witness testimonies, to ascertain whether Satmell Holdings had contravened the applicable laws. Additionally, the court needed to consider the appropriate response to any established breaches, including potential enforcement actions or financial penalties.
The court found that Satmell Holdings had indeed undertaken construction activities in breach of the planning laws. The council's evidence, including photographs and expert testimonies, demonstrated that Satmell Holdings had carried out significant construction without obtaining the necessary approvals. The court acknowledged that Satmell Holdings had taken steps to rectify the situation after becoming aware of the breaches, but this did not absolve them of liability. The court ordered Satmell Holdings to comply with all outstanding planning requirements and imposed financial penalties for the breaches. The court also mandated that Satmell Holdings provide a detailed compliance plan to ensure future adherence to planning laws.
Orders
Orders of the court
See orders at [77].
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi