CITATION: Biseja v NSI Group [2006] NSWSC 835 HEARING DATE(S): 04/08/2006
JUDGMENT DATE :
4 August 2006JURISDICTION: Equity JUDGMENT OF: McDougall J at [1] EX TEMPORE JUDGMENT DATE: 08/04/2006 DECISION: See para [29] of judgment CATCHWORDS: BUILDING AND CONSTRUCTION - where adjudicator found that project management services were "related goods or services" under the Building and Construction Industry Security of Payment Act 1999 - where project management fee might be discharged by transfer in specie of real estate - whether s 7(2)(c) of Act applicable - whether consideration was to be calculated by the value of services - whether open to adjudicator to reach factual conclusion - whether reviewable error - application of Brodyn v Davenport (2004) 61 NSWLR 421 LEGISLATION CITED: Building and Construction Industry Security of Payment Act 1999 CASES CITED: Brodyn Pty Limited v Davenport (2004) 61 NSWLR 421 PARTIES: Biseja Pty Limited (Plaintiff)
NSI Group Pty Limited (Defendant)FILE NUMBER(S): SC 2969/06 COUNSEL: F C Corsaro SC (Plaintiff)
G A Moore/F P Hicks (Defendant)SOLICITORS: L Capolupo & Co (Plaintiff)
William Cotsis & Associates (Defendant)
IN THE SUPREME COURT
OF NEW SOUTH WALES
EQUITY DIVISION
McDOUGALL J
Friday 4 August 2006 Ex tempore (revised 7 August 2006)
2969/06 BISEJA PTY LIMITED v NSI GROUP PTY LIMITED
JUDGMENT
1 HIS HONOUR: The plaintiff (Biseja) carried out a number of property development projects in the region north of Sydney from about 2001 to 2005. The builder on at least three of those projects was the defendant (NSI). At least at the commencement of that business relationship, Mr Malcolm Downie of Biseja and Mr Emade Semaan of NSI were brothers in law.
2 This dispute relates to a project known as the North Entrance Stage 2 Project. NSI's case is that it agreed with Biseja to perform the building work at cost and agreed separately to provide project management services for a fee of 10 percent of the cost of the building works. NSI says further that it was agreed between it and Biseja that the fee could be satisfied by the transfer of three units in the completed development.
3 The factual background suggests that somewhat similar arrangements had been entered into between NSI and Biseja in relation to something called the Swansea Project and something called the North Entrance Stage 1 Project. It is, in any event, NSI's case that this was so.
4 Biseja and NSI fell into dispute in relation to the North Entrance Stage 2 Project and NSI made a claim on Biseja for payment of the Stage 2 project management fee. Whatever else may be in dispute in these proceedings (and it would appear that much is) it is, I think, common ground that the project management services that NSI claims to have provided to Biseja on the North Entrance Stage 2 Project would be "related goods and services" for the purposes of the Building and Construction Industry Security of Payment Act 1999 (the Act). NSI’s claim was a payment claim…
Continue reading Biseja v NSI Group
Sign in free to access the full text
- AGLC
- Biseja v NSI Group [2006] NSWSC 835
- Case
- [2006] NSWSC 835
- Decision Date
CaseChat Overview and Summary
The court examined the legislative intent and the scope of section 7(2)(c) of the Act, noting that the adjudicator's determination was based on factual findings that the project management services were not related goods or services under the Act. The court considered whether these findings were reasonable and supported by the evidence, applying the principles set out in Brodyn v Davenport. It found that the adjudicator's conclusion was within the bounds of the statutory power, as the court was not permitted to substitute its own view of the evidence for that of the adjudicator. The court also noted that the adjudicator's error, if any, was not a reviewable error as it did not concern a question of law or jurisdiction but rather a question of fact.
The court ultimately held that the adjudicator's decision was not subject to review and dismissed the application for review. The reasoning focused on the distinction between errors of law and errors of fact, with the court affirming that it was not open to it to substitute its view of the evidence for that of the adjudicator. The application was dismissed with costs to be paid by the applicant.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.