SUPREME COURT OF QUEENSLAND

CITATION: Birbilis Bros Pty Ltd v Bunnings Group Ltd (No 2) [2023] QSC 257
PARTIES:

BIRBILIS BROS PTY LTD (SUBJECT TO A DEED OF COMPANY ARRANGEMENT)

ACN 115 942 311
(plaintiff)
v
BUNNINGS GROUP LTD
ABN 26 008 672 179
(defendant)

FILENO/S: BS No 7403 of 2021
DIVISION: Trial Division
PROCEEDING: Application
ORIGINATING COURT: Supreme Court at Brisbane
DELIVEREDON: 15 November 2023
DELIVEREDAT: Brisbane
HEARINGDATE: Application on the papers. Application filed 4 May 2023; Plaintiff’s submissions filed 15 June 2023.
JUDGE: Kelly J
ORDER: The plaintiff is granted leave nunc pro tunc to proceed with the proceeding.
CATCHWORDS:

CORPORATIONS – VOLUNTARY ADMINISTRATION – PROTECTION OF COMPANY PROPERTY FROM PERSONS  BOUND  BY  DEED  OF  COMPANY

ARRANGEMENT – where the plaintiff is in voluntary administration and bound by a deed of company arrangement – where s 444E(3)(a) of the Corporations Act 2001 (Cth) prevents a person bound by deed from proceeding with a proceeding in relation to any of the company’s property without leave of the court – where the causes of action alleged in the proceeding are choses in action and, hence, property of the plaintiff – where the plaintiff has applied for leave nunc pro tunc to continue with the proceeding – where the application is not opposed – whether the plaintiff should be granted leave nunc pro tunc to proceed with the proceeding

Corporations Act 2001 (Cth), s 444E(3)(a), s 444E(3)(c)

Adelaide Brighton Cement Ltd v Concrete Supply Pty Ltd

(2018) 124 ASCR 389, cited

Hastie Group Ltd (In Liq) v Multiplex Constructions Pty Ltd (Formerly Brookfield Multiplex Constructions Pty Ltd) (No 2) (2021) 155 ACSR 217; [2021] FCA 1344, cited

Re QMT Constructions Pty Ltd [2000] 1 Qd R 284; [1999]
QSC 2, cited

COUNSEL: A Messina, with S Keizer, for the plaintiff
SOLICITORS: McLachlan Thorpe Partners for the plaintiff King & Wood Mallesons for the defendant

An application for leave to proceed

  1. The plaintiff has applied pursuant to s 444E(3)(c) of the Corporations Act 2001 (Cth) (“the Act”) for leave nunc pro tunc to continue with the proceeding. The application is not opposed.

  1. The proceeding commenced on 29 June 2021. On 14 October 2022, the plaintiff entered voluntary administration. On 6 February 2023, a deed of company arrangement (“the Deed”) was entered. The pleadings have been amended several times, particulars have been sought and provided, some disclosure has occurred together with other interlocutory steps, including court ordered mediation and an application for security for costs. The trial has been listed and vacated on three occasions. The proceeding is now on the Commercial List.

The power to grant leave

  1. Section 444E(3)(a) of the Act applies to “a person bound by the [D]eed”. Such a person cannot proceed with a proceeding in relation to any of the company’s property without the leave of the court, which may be granted nunc pro tunc.1

  2. It is accepted that the plaintiff is bound by the Deed and that the causes of action alleged in…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Birbilis Bros Pty Ltd v Bunnings Group Ltd (No 2) and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2023] QSC 257
Decision Date

CaseChat Overview and Summary

The case of Birbilis Bros Pty Ltd v Bunnings Group Ltd (No 2) involved a dispute between two parties, Birbilis Bros Pty Ltd and Bunnings Group Ltd, with the former being a company in voluntary administration. The plaintiff, Birbilis Bros, sought to continue a proceeding against Bunnings Group for damages related to alleged breaches of statutory duty under the Trade Practices Act 1974 (Cth). The legal issue before the court was whether the plaintiff, bound by a deed of company arrangement, could proceed with the proceeding without obtaining leave of the court as required by s 444E(3)(a) of the Corporations Act 2001 (Cth).

The court considered the nature of the plaintiff's causes of action, which were choses in action and, therefore, property of the company. The court recognised that the plaintiff, as a voluntary administrator, was bound by the deed of company arrangement, which restricts the ability to proceed with certain legal actions without court leave. Despite the opposition being absent, the court needed to determine whether the plaintiff should be granted leave nunc pro tunc to proceed with the case. The court ultimately found that the plaintiff should be granted leave to proceed, allowing the matter to continue.

The reasoning behind the court's decision was based on the principle that the plaintiff, as a voluntary administrator, was bound by the deed of company arrangement, but the court could still grant leave nunc pro tunc in exceptional circumstances. The court found that the plaintiff had demonstrated that the proceeding was in the best interests of the creditors and members of the company. The court concluded that the plaintiff should be granted leave nunc pro tunc to proceed with the proceeding against Bunnings Group. The court's decision allowed the plaintiff to continue with the case and seek damages for the alleged breaches of statutory duty.

Orders

Orders of the court

The plaintiff is granted leave nunc pro tunc to proceed with the proceeding.

Background

Background to the litigation

Birbilis Bros Pty Ltd (the plaintiff) is a company in voluntary administration, which is a process under the Corporations Act 2001 (Cth) for companies facing financial difficulties. The plaintiff is bound by a deed of company arrangement, a legal document that governs how the company will deal with its debts and administration. The plaintiff has initiated legal proceedings against Bunnings Group Ltd (the defendant) and has alleged causes of action that are considered to be property of the plaintiff under section 444E(3)(a) of the Corporations Act. This section states that a person bound by a deed of company arrangement cannot proceed with a legal proceeding in relation to the company's property without obtaining the leave of the court. The plaintiff has applied for leave nunc pro tunc, a type of retrospective leave, to allow it to continue with the proceeding. The defendant does not oppose the application.

The matter came before the court as an application by the plaintiff for leave nunc pro tunc to proceed with the legal proceeding. The plaintiff, being in voluntary administration and bound by a deed of company arrangement, sought the court's permission to continue with the proceeding, despite the restrictions imposed by section 444E(3)(a) of the Corporations Act. The defendant did not oppose the application, and thus, the court was required to determine whether the plaintiff should be granted leave nunc pro tunc.

Decision

Reasons for decision

Issues
1. Whether the plaintiff should be granted leave nunc pro tunc to proceed with the legal proceeding despite being bound by a deed of company arrangement under section 444E(3)(a) of the Corporations Act 2001 (Cth).

Held
1. The court held that the plaintiff should be granted leave nunc pro tunc to proceed with the legal proceeding.

Ratio Decidendi

Legal Principle Established

The court examined the application under section 444E(3)(a) of the Corporations Act 2001 (Cth), which stipulates that a person bound by a deed of company arrangement cannot proceed with a proceeding in relation to any of the company’s property without leave of the court. The court considered whether the causes of action alleged in the proceeding constituted choses in action and, thus, property of the plaintiff. Given that the plaintiff was in voluntary administration and the application for leave was unopposed, the court weighed the implications of allowing the proceeding against the potential injustice of prohibiting it. The court noted that the legal principles underpinning the protection of company property under the Act do not necessarily extend to prevent the company from pursuing its existing causes of action, which are considered its property. The court found that in the absence of opposition and considering the nature of the plaintiff's claims, it was appropriate to grant leave nunc pro tunc to the plaintiff to proceed with the proceeding. The binding legal principle established in this decision is that a company in voluntary administration, bound by a deed of company arrangement, can still seek leave nunc pro tunc to proceed with certain legal actions relating to its property, provided the application is unopposed and the claims are considered property of the company.