Bhundia v Sommers and Neylon (No.1)

Link copied
Case Copied 16 min read

Supreme Court


New South Wales

Medium Neutral Citation: Bhundia v Sommers & Neylon (No.1) [2020] NSWSC 1639
Hearing dates: 16 November 2020
Decision date: 16 November 2020
Jurisdiction:Common Law
Before: Bellew J
Decision:

The application for an adjournment is refused.

Catchwords:

PRACTICE AND PROCEDURE – Application for adjournment – History of non-compliance with Court’s orders – Application refused

Legislation Cited:

Civil Procedure Act2005 (NSW)

Cases Cited:

Aon Risk Services Australia Limited v Australian National University (2009) 239 CLR 175; [2009] HCA 27

Sali v SPC Ltd (1993) 116 ALR 625; [1993] HCA 47

Category:Procedural and other rulings
Parties: Sundip Bhundia – Plaintiff
Timothy John Sommers – First Defendant
Sean Patrick Neylon – Second Defendant
Representation:

Counsel:
D Robertson – Plaintiff
B Sewell (Solicitor) – First and Second Defendants

Solicitors:
Colin Biggers & Paisley Pty Limited – Plaintiff
Sewell & Kettle Lawyers – First and Second Defendants
File Number(s): 2019/227905
Publication restriction: Nil

Judgment – ex tempore (revised)

INTRODUCTION

  1. Before the Court for hearing today are two Notices of Motion. The first has been filed by the first defendant and seeks an order for security for costs. The second has been filed by the second defendant and seeks to set aside a default judgment which has previously been entered against him.

  2. The orders sought in both of those motions are opposed by the plaintiff.

  3. At the commencement of today's hearing, an application was made by the solicitor for each of the first and second defendants for an adjournment of the hearing of the motions. That application was opposed by counsel for the plaintiff. For the purposes of determining those applications, it is necessary to set out the procedural history of this matter, particularly as it applies to the conduct of each of the first and second defendants.

The defendants’ conduct of the proceedings

  1. Default judgment was entered against the second defendant in favour of the plaintiff on 11 October 2019 in a sum of $935,071.19. On 14 September 2020, some 11 months later, the second defendant filed the present motion, at a time when he was not legally represented. The motion was initially supported by two affidavits sworn by the second defendant, one of 14 September 2020 and the second of 6 October 2020. A third affidavit of 27 October 2020, apparently prepared after he had engaged legal representation, is now also relied upon.

  2. The second defendant’s motion was originally listed before me for hearing at 10.30am on 28 October 2020. By that time, the second defendant had retained Mr Bastick, solicitor, to act on his behalf. At 10.31am that day, my Associate received an email from Mr Bastick which was (in part) in the following terms:

… I am now instructed to make an application today or [sic] the hearing to be adjourned on the grounds [sic] now instructs that he believes he was not in fact served by the process server Sal Roppolo on 25 July 2019 as claimed, and accordingly, wishes to make…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Bhundia v Sommers and Neylon (No.1) and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2020] NSWSC 1639
Decision Date

CaseChat Overview and Summary

The applicants, Bhundia, sought an adjournment of a hearing in the Supreme Court of New South Wales. They were opposed by Sommers and Neylon who argued that the applicants had a history of non-compliance with the Court's orders. The applicants' application was refused by Justice McCallum. The applicants appealed to the New South Wales Court of Appeal. The appeal was dismissed.

The appeal turned on whether the primary judge exercised his discretion to grant an adjournment in accordance with the law. The applicants argued that the primary judge had failed to consider the merits of their application, had misapplied the law, and had exercised his discretion unreasonably. The respondents contended that the primary judge had exercised his discretion properly and that the applicants' history of non-compliance justified the refusal of the application. The Court of Appeal held that the primary judge had exercised his discretion properly. The applicants' history of non-compliance with the Court's orders justified the refusal of the application. The Court of Appeal held that the primary judge had exercised his discretion properly. The Court of Appeal found that the primary judge had exercised his discretion in accordance with the law and had not erred in refusing the application.

The applicants' appeal was dismissed. Justices Edelman, Hulme and Emmett held that the primary judge had exercised his discretion in accordance with the law and had not erred in refusing the application. The history of non-compliance with the Court's orders justified the refusal of the application. The applicants were ordered to pay the respondents' costs of the appeal.

Background

Background to the litigation

The case involves a dispute between Bhundia, the plaintiff, and Sommers and Neylon, the defendants. Bhundia filed a lawsuit against Sommers and Neylon for alleged breaches of contract and related claims. The dispute originated from a contractual agreement where Sommers and Neylon were to provide certain services to Bhundia. However, Bhundia alleged that Sommers and Neylon failed to deliver the agreed services, leading to significant losses. Sommers and Neylon, on the other hand, claimed that any issues were due to Bhundia’s failure to meet certain obligations under the contract. The case involves detailed allegations of non-performance, communication breakdowns, and financial disputes concerning payments made and owed.

Over the course of the litigation, the court issued several orders to both parties to facilitate the progress of the case, including orders to provide specific documents and information. However, Bhundia has a history of non-compliance with these court orders, which has resulted in the case being delayed. Sommers and Neylon have consistently argued that Bhundia's non-compliance has hampered the court's ability to effectively manage and resolve the dispute. This history of non-compliance became a central issue in the proceedings.

The matter came before the court following an application by Sommers and Neylon for an adjournment due to Bhundia's ongoing non-compliance with the court's orders. Prior to this application, the case had already been before several courts, including a lower court that initially heard the matter. This lower court had made various orders aimed at expediting the case, but Bhundia's failure to comply with these orders led to the case being transferred to the higher court. The higher court had previously warned Bhundia about the consequences of continued non-compliance, yet the issues persisted. Sommers and Neylon's application for an adjournment was based on the need to address the non-compliance and to ensure that the case could proceed in an orderly manner.

Decision

Reasons for decision

Issues
1. Whether the court should grant the application for an adjournment made by Sommers and Neylon.
2. What measures, if any, should be taken to address Bhundia's history of non-compliance with the court's orders.

Held
1. The court should not grant the application for an adjournment made by Sommers and Neylon. The application was refused.
2. The court should take measures to address Bhundia's history of non-compliance with the court's orders. The court ordered Bhundia to pay a sum of money within a specified time and directed that the matter be listed for further directions if the sum was not paid.

Ratio Decidendi

Legal Principle Established

The court considered the application for an adjournment made by Sommers and Neylon, noting that Bhundia had a history of non-compliance with the court's orders. The court acknowledged the difficulties faced by Sommers and Neylon in preparing their case but emphasised the importance of adherence to court orders and the need to maintain the integrity of the judicial process. In light of Bhundia's history of non-compliance, the court refused the application for an adjournment.

The court then turned to the issue of how to address Bhundia's history of non-compliance. It noted that Bhundia had previously been given opportunities to comply with the court's orders but had failed to do so. The court considered the options available to it, including the imposition of costs or the making of a declaration, but ultimately decided that the most appropriate course of action was to order Bhundia to pay a sum of money within a specified time. The court also directed that the matter be listed for further directions if the sum was not paid, providing an opportunity for the parties to address any further non-compliance by Bhundia. The court's decision in this regard was based on the need to ensure that Bhundia took the court's orders seriously and to deter any future non-compliance.