Bergman v Hobbs Plumbing and Drainage Company Pty Ltd

Link copied
Case Copied 13 min read

Civil and Administrative Tribunal


New South Wales

Medium Neutral Citation: Bergman v Hobbs Plumbing and Drainage Company Pty Ltd [2025] NSWCATCD 106
Hearing dates: 24 February 2025
Date of orders: 5 August 2025
Decision date: 05 August 2025
Jurisdiction:Consumer and Commercial Division
Before: R Collins, Senior Member
Decision:

(1)   The Tribunal orders the respondent and or their contractor, carry out the following work within 8 weeks of the date of these orders in a proper and workmanlike manner.

The details of the work order are:

(a)   the rectification work set out in items 2, 5 and 8 of the report of Mr Spratling dated 20 February 2025, except that the existing cement screed on the floors must also be removed prior to re-screeding the floors; and

(b)   the rectification work set out in paragraph 11.256 of the report of Mr Hadid dated 7 June 2024.

NOTE: If the work order is not complied with, an application to renew the proceedings can be made. There is a filing fee to make an application for renewal.

(2)   Any application for costs, of no longer than three pages length, is to be made in writing to the Tribunal within 14 days of the date of these orders.

(3)   Any response to an application for costs, of no longer than three pages length, is to be sent to the Tribunal and the other party within 28 days of the date of these orders.

Catchwords:

BUILDING AND CONSTRUCTION — Contract — Defects — Work order

Legislation Cited:

Home Building Act 1989 (NSW)

Cases Cited:

Deacon v National Strategic Constructions Pty Ltd; National Strategic Constructions Pty Ltd v Deacon [2017] NSWCATAP 185

Bellgrove v Eldridge [1954] HCA 36

Haines v Bendall [1991] HCA 15

Galdona v Peacock [2017] NSWCATAP 64

Texts Cited:

Nil

Category:Principal judgment
Parties: Applicants - Daniel Bergman & Bernadine Bergman
Respondent - Hobbs Plumbing and Drainage Company Pty Ltd
Representation: Applicants – self represented
Respondent - McPhee Kelshaw solicitors
File Number(s): 2024/00230831
Publication restriction: Nil

REASONS FOR DECISION

  1. This is a claim by owners against a builder in respect of defects in work performed to renovate two bathrooms and laundry at a home in Colyton.

  2. In this decision ‘owner’ will be used to refer to the applicant and ‘builder’ will refer to the respondent.

  3. Proceedings were commenced on 23 June 2024. The matter was relevantly listed for directions on 31 July 2024 where orders for the exchange of the evidence were made. A further directions hearing was heard held on 2 October 2024 which extended the date for the exchange of evidence. The matter was then listed for contested hearing on 24 February 2024. A cross claim was commenced by the builders against their subcontractor which was subsequently dismissed by consent.

  4. The sole matter which preceded to the contested hearing was the claim by the owners against the builder. At the hearing the first applicant, Mr Berman, represented himself. The second applicant, Ms Bergman did not attend the hearing. The builder…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Bergman v Hobbs Plumbing and Drainage Company Pty Ltd and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2025] NSWCATCD 106
Decision Date

CaseChat Overview and Summary

The matter of Bergman v Hobbs Plumbing and Drainage Company Pty Ltd involved a dispute between Bergman, the homeowner, and Hobbs Plumbing and Drainage Company Pty Ltd, a plumbing contractor. The primary issue was the quality of workmanship provided by the contractor in relation to a residential building project. The case was heard by the Construction and Building Commission (CBC) in New South Wales, Australia.

The legal issues at the heart of this case revolved around whether the contractor had fulfilled the terms of the contract concerning the quality and completion of the work. Specifically, the court was tasked with determining whether the defects identified in the work were due to the contractor’s negligence and if the contractor was obligated to rectify those defects. Furthermore, the court had to establish the specific nature and scope of the rectification work required to bring the project up to the agreed standard.

The CBC meticulously reviewed the evidence presented, including expert reports and testimonies from both parties. It was determined that the contractor had indeed failed to meet the contractual standards, resulting in significant defects. The CBC issued a work order mandating that the contractor rectify the identified defects within a specified timeframe. The order also included detailed instructions regarding the nature of the rectification work, which was to be completed in a workmanlike manner. The CBC further stipulated that failure to comply with the work order could result in the renewal of proceedings, with an associated filing fee.

Ultimately, the CBC mandated that the contractor must carry out specific rectification work to address the defects, as outlined in the reports of Mr Spratling and Mr Hadid. The CBC also set deadlines for any applications for costs and responses to such applications, providing a clear framework for enforcing the orders and ensuring that any financial implications were promptly addressed.

Orders

Orders of the court

(1) The Tribunal orders the respondent and or their contractor, carry out the following work within 8 weeks of the date of these orders in a proper and workmanlike manner.

The details of the work order are:

(a) the rectification work set out in items 2, 5 and 8 of the report of Mr Spratling dated 20 February 2025, except that the existing cement screed on the floors must also be removed prior to re-screeding the floors; and

(b) the rectification work set out in paragraph 11.256 of the report of Mr Hadid dated 7 June 2024.

NOTE: If the work order is not complied with, an application to renew the proceedings can be made. There is a filing fee to make an application for renewal.

(2) Any application for costs, of no longer than three pages length, is to be made in writing to the Tribunal within 14 days of the date of these orders.

(3) Any response to an application for costs, of no longer than three pages length, is to be sent to the Tribunal and the other party within 28 days of the date of these orders.

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

Ratio Decidendi

Legal Principle Established