Beno Excavations Pty Ltd v Harlech Enterprises Pty Ltd

Link copied
Case Copied 26 min read

SUPREME COURT OF THE AUSTRALIAN CAPITAL TERRITORY

Case Title:

Beno Excavations Pty Ltd v Harlech Enterprises Pty Ltd

Citation:

[2021] ACTSC 166

Hearing Dates:

20 and 22 July 2021

DecisionDate:

23 July 2021

Before:

Mossop J

Decision:

See [65]

Catchwords:

BUILDING AND CONSTRUCTION – SECURITY OF PAYMENT – Building and Construction Industry (Security of Payment) Act 2009 (ACT) – Challenge to adjudicator’s decision – application for extension of time for prerogative relief – application for extension of time for leave to appeal – delay in commencing proceedings – issue estoppel – claim for prerogative relief has sufficient prospects – extension of time for prerogative relief granted

Legislation Cited:

Building and Construction Industry (Security of Payment) Act 2009 (ACT), ss 15(4)(b), 24, 43

Court Procedure Rules 2006 (ACT), rr 3557, 5072

Cases Cited:

AE & E Australia Pty Ltd v Stowe Australia Pty Ltd [2010] QSC 135

Canberra Drilling Rigs Pty Ltd v Haides Pty Ltd [2019] ACTCA 15; 14 ACTLR 95
Cardinal Project Services Pty Ltd v Hanave Pty Ltd [2010] NSWSC 1367
Director of Public Prosecutions (ACT) v Martin [2014] ACTSC 104; 9 ACTLR 1
Dualcorp Pty Ltd v Remo Constructions Pty Ltd [2009] NSWCA 69; 74 NSWLR 190

J Hutchinson Pty Ltd v Galform Pty Ltd & Ors [2008] QSC 205

Parties:

Beno Excavations Pty Ltd t/as Benex Pipelines (Plaintiff)

Harlech Enterprises Pty Ltd atf Harlech Family Trust (First Defendant)

Jonathan H Sive (Second Defendant)

Representation:

Counsel

J Moffett (Plaintiff)

A Greinke (First Defendant)

Solicitors

BAL Lawyers (Plaintiff)

Mills Oakley (First Defendant)

File Number:

SC 206 of 2021

MOSSOP J:

Introduction

  1. The plaintiff has sought an extension of time in which to file an application for prerogative relief and an application for an extension of time and for leave to appeal under s 43 of the Building and Construction Industry (Security of Payment) Act 2009 (ACT) (SOP Act). Both applications challenge a decision of an adjudicator, the second defendant.

  1. The reason that the extensions of time are necessary is that the solicitors for the plaintiff failed to pay attention to the relevant limitation periods. Under s 43 of the SOP Act, an application must be filed within 28 days: rule 5072 of the Court Procedure Rules 2006 (ACT). Further time may be allowed by the court. An application for prerogative relief needs to be filed within 60 days: rule 3557. The court has power to extend time “only in special circumstances”: rule 3557(4).

  1. The adjudication decision was made on 17 March 2021. 28 days after that date was 14 April 2021. 60 days after that date was 16 May 2021. The originating application was filed on 20 May 2021. Therefore, the extension of time is 36 days for the purposes of s 43 of the SOP Act and four days for the purposes of the claim for prerogative relief.

  1. The adjudicator, Jonathan Sive, is the second defendant in the proceedings. He entered a submitting appearance. References in these proceedings to the defendant are references…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Beno Excavations Pty Ltd v Harlech Enterprises Pty Ltd and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2021] ACTSC 166
Decision Date

CaseChat Overview and Summary

In the Supreme Court of the Australian Capital Territory, Beno Excavations Pty Ltd sought an extension of time to file an application for prerogative relief and an extension of time and leave to appeal under s 43 of the Building and Construction Industry (Security of Payment) Act 2009 (ACT). The applications challenged a decision of an adjudicator, Jonathan Sive. The reason for the extensions of time was that the solicitors for the plaintiff had failed to pay attention to the relevant limitation periods. The adjudication decision was made on 17 March 2021. The originating application was filed on 20 May 2021. The court was required to decide whether special circumstances existed to allow an extension of time. In this case, the reason for the delay in commencing proceedings was because of the failure on the part of the plaintiff’s solicitors to consider the issue of limitation periods, to give advice to the plaintiff in relation to those limitation periods or to take any steps to protect their client’s interests in relation to the operation of those limitation periods. The explanation for the delay was unsatisfactory, but it was one for which the plaintiff’s solicitors bore responsibility rather than the plaintiff itself. The prejudice to the defendant would arise out of the costs involved in taking steps to enforce the adjudication decision and the potential that there would now be a liability for an order by way of restitution for monies received as a result of the garnishee order and a longer than necessary delay in resolving any challenge to the adjudication decision. The merits of the claim were reasonably arguable as it was reasonably arguable that the approach taken by the adjudicator to the operation of s 24(4) and issue estoppel was one which coloured the whole of the adjudicator’s approach to the issues between the parties. The court decided that special circumstances existed and hence the threshold for an extension of time under the rules was established. The existence of special circumstances did not of itself compel the granting of the application but did meet the threshold provided for in the rule for an extension of time. The court decided that it was appropriate to grant an extension of time in relation to the claim for prerogative relief as the prospects of the claim appeared to be sufficient in the circumstances to warrant the grant of an extension of time for the limited period required. However, the court decided that it was not so satisfied in relation to the claim for an extension of time in which to bring the s 43 appeal as the extension of time required was longer and a grant of leave to appeal under the relevant limb of s 43 of the SOP Act required a conclusion to be reached that there was a manifest error of law on the face of the adjudication decision, a conclusion which the court could not reach at present based upon the arguments advanced to date.

Orders

Orders of the court

Full text does not contain this section.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.