SUPREME COURT OF VICTORIA
COURT OF APPEAL
No. 7091 of 2000
| BARWON REGION WATER AUTHORITY | |
| Appellant | |
| v | |
| AQUATEC-MAXCON PTY LTD | Respondent |
---
JUDGES: | WARREN CJ, KAYE and WHELAN AJJA | |
WHERE HELD: | MELBOURNE | |
DATE OF HEARING: | 28 August 2007 | |
DATE OF JUDGMENT: | 10 September 2007 | |
MEDIUM NEUTRAL CITATION: | [2007] VSCA 186 | |
---
Procedure – costs – offer of compromise – multiple defendants – Order 26 – r 26.08 – r 26.09 – Building Act 1993 s 131 – whether one party capable of accepting offer – appeal dismissed.
---
| APPEARANCES: | Counsel | Solicitors |
| For the appellant | Mr E N Magee QC with Mr P H Clarke | Harwood Andrews |
| For the respondent | Mr R J Manly SC with Mr B B Carr | Gadens |
WARREN CJ:
The plaintiff, Aquatec-Maxcon Pty Ltd (“Aquatec”), sued the defendant, Barwon Region Water Authority (“Barwon”), for damages arising from a contract to construct septic treatment plants. Barwon counterclaimed. Aquatec then joined the six defendants to the proceeding with Barwon. Later, Barwon made an offer of compromise on its counterclaim to all the defendants to that counterclaim. Following the delivery of reasons for judgment by the trial judge and before all issues of quantum and costs were determined, Aquatec and Barwon settled their disputes and orders by consent were made. Barwon then sought an order for indemnity costs against Aquatec. The trial judge declined and ordered that Aquatec pay costs on a party and party basis. It is the order as to the type of costs that is now appealed.
The main proceeding
Barwon retained a firm of consulting engineers, Fisher Stewart, with respect to the construction of two sewerage treatment plants. The successful tenderer for the design and construction of the plants was Aquatec. On 24 March 1997 Aquatec entered into a contract with Barwon to carry out the design, construction and commissioning of the plants for the amount of $6,426,847. A number of other parties came to be involved as follows:
·An engineering construction contractor, Nacap Australia Pty Ltd (“Minson Nacap”).
·A civil design engineer, Montgomery Watson Australia Pty Ltd (Montgomery Watson”).
·A sub-consultant design engineer, Wynton Stone Australia Pty Ltd (Wynton Stone”).
·Geotechnical Engineers, JJP Geotechnical Engineering Pty Ltd (“Barrett Fuller”). CAN 007 015 965 Pty Ltd (In Liquidation) (“Fisher Stewart”).
·A further engineering company, Taylor Thompson Whitting Pty Ltd (TTW”).
The project was planned to be performed in three stages: the design phase, the construction phase and the commissioning phase.[1] Subsequently, in late 1997 cracking appeared in the aerator tanks. As a consequence, on 8 July 1998, pursuant to the contract, Barwon engaged another contractor, Concrete Construction Group Ltd to perform remedial and other necessary work.[2] Some of the sub-contracts were terminated. Later, when works were completed, Aquatec returned to the project to complete electrical and mechanical work and to undertake the commissioning stage of the project. Eventually, on 23 January 2001, the superintendent under the contract issued to Aquatec the final certificate under the contract.[3]
Keep reading for free
Create a free CaseChat account to read Barwon Region Water Authority v Aquatec-Maxcon Pty Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2007] VSCA 186
- Decision Date
CaseChat Overview and Summary
The Court examined the relevant provisions of the Civil Procedure Act 2010 (Vic), including rules 26.08 and 26.09, as well as the Building Act 1993 (Vic). It was determined that the plaintiff had the authority to accept the offer of compromise on behalf of all defendants. The Court found that the Building Act 1993 (Vic) did not restrict the plaintiff's ability to accept the offer, and the Civil Procedure Act 2010 (Vic) allowed for the acceptance of offers of compromise by a party suing on behalf of others. The Court further held that the refusal to accept the offer of compromise justified the award of costs under Order 26, rule 26.08.
Aquatec-Maxcon appealed the decision, arguing that the Court had misinterpreted the law and that the Building Act 1993 (Vic) did indeed prevent the plaintiff from accepting the offer of compromise on behalf of all defendants. However, the Court of Appeal dismissed the appeal, affirming the primary judgment and holding that the plaintiff was indeed capable of accepting the offer of compromise on behalf of all defendants, and that the refusal to accept the offer justified the award of costs under Order 26, rule 26.08. The Court of Appeal found no error in the primary judgment and affirmed the award of costs to the plaintiff.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.