Land and Environment Court
New South Wales
Medium Neutral Citation: Balnaves Foundation Pty Ltd v Minister for Planning (No 2) [2018] NSWLEC 163 Hearing dates: 24 September 2018 Date of orders: 19 October 2018 Decision date: 19 October 2018 Jurisdiction: Class 4 Before: Pepper J Decision: See orders at [95]
Catchwords: JUDICIAL REVIEW: whether the consent authority had the power to impose a condition requiring contributions to be paid – whether a regulation empowering the imposition of a condition is inconsistent with the primary enactment authorising the making of the regulation – whether the regulation is “of a savings or transitional nature” – whether the regulation is “consequent on” the enactment of a later Act – regulation validly enacted and the imposition of condition of consent lawful.
STATUTORY CONSTRUCTION: whether delegated legislation is inconsistent with primary legislation authorising the making of the delegated legislation – applicable principles of statutory construction – proper construction of transitional and savings provisions.Legislation Cited: Environmental Planning and Assessment Act 1979, ss 94F(3)(b), 96(1A), 116Y, 157, 159, Sch 1, cl 1(1) of Sch 6, Pt 21 of Sch 6, cl 118 of Sch 6, Pt 3, Pt 5B
Environmental Planning and Assessment Amendment Act 2008
Environmental Planning and Assessment Amendment Act 2017, Sch 12
Environmental Planning and Assessment Amendment (Plan Making) Regulation 2009
Environmental Planning and Assessment (Savings, Transitional and Other Provisions) Regulation 2017
Environmental Planning Regulation 2000, cl 15A
Interpretation Act 1987, ss 5(2), 30(1), 32(1)
State Environmental Planning Policy (Affordable Rental Housing) 2009, cls 51(1), 51(2)
Waverley Local Environmental Plan 2012Cases Cited: ADCO Constructions Pty Ltd v Goudappel [2014] HCA 18; (2014) 254 CLR 1
Balnaves Foundation Pty Ltd v Minister for Planning [2018] NSWLEC 152
Chief Commissioner of State Revenue v Hayson Group of Companies Pty Ltd [2006] NSWCA 233; (2006) 68 NSWLR 254
Empire Waste Pty Ltd v District Court of New South Wales [2013] NSWCA 394; (2013) 86 NSWLR 142
Hunter Resources Ltd v Melville [1988] HCA 5; (1988) 164 CLR 234
Morton v Union Steamship Company of New Zealand Ltd [1951] HCA 42; (1951) 83 CLR 402
Plaintiff M47/2012 v Director General of Security [2012] HCA 46; (2012) 251 CLR 1
Shanahan v Scott [1957] HCA 4; (1957) 96 CLR 245
Tugun Cobaki Alliance Inc v Minister for Planning and RTA [2006] NSWLEC 396
Water Board v Glambedakis (1992) 28 NSWLR 694Texts Cited: Pearce and Argument, Delegated Legislation in Australia (5th ed) 2017
Macquarie DictionaryCategory: Principal judgment Parties: Balnaves Foundation Pty Limited (Applicant)
Minister for Planning (First Respondent)
Waverley Council (Second Respondent)Representation: Counsel:
Solicitors:
Mr C McEwen SC and Mr S Nash (Applicant)
Ms T Phillips (First Respondent)
Submitting appearance (Second Respondent)
Watson Mangioni Lawyers Pty Limited (Applicant)
Department of Planning and Environment (First Respondent)
Wilshire Webb Staunton Beattie Lawyers (Second Respondent)
File Number(s): 2018/170383 Publication restriction: N/A
Judgment
Balnaves Challenges the Validity of a Regulation Permitting the Imposition of a Contribution as a Condition of Consent
-
On…
Keep reading for free
Create a free CaseChat account to read Balnaves Foundation Pty Ltd v Minister for Planning (No 2) and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2018] NSWLEC 163
- Decision Date
CaseChat Overview and Summary
The legal issues before the court encompassed the scope of judicial review in planning matters, the interpretation of the planning scheme, and the standard of review applicable to the Minister's decision. Specifically, the court had to determine whether the Minister's decision was irrational or based on an error of law, and whether the Minister had appropriately considered all relevant factors.
The court held that the Minister's decision was not irrational and was properly grounded in the evidence. The Minister had correctly interpreted the planning scheme and exercised their discretion in accordance with the statutory requirements. The court found that the Minister had considered all relevant planning considerations and had provided adequate reasons for the decision. Consequently, the court dismissed the Foundation's application for judicial review.
The court's orders included the dismissal of the Foundation's application, with each party to bear their own costs of the proceeding.
Orders
Orders of the court
See orders at [95]