[2013] QDC 218
DISTRICT COURT OF QUEENSLAND
CIVIL JURISDICTION
JUDGE ROBIN QC
No 2370 of 2011
ASAP PLASTERERS PTY LTD Plaintiff/Applicant
and
MATRIX PROJECTS (QLD) PTY LTD
and ANOTHER Defendants/RespondentASAP PLASTERERS PTY LTD Plaintiff/Respondent
and
MATRIX PROJECTS (QLD) PTY LTD
and ANOTHER Defendants/ApplicantBRISBANE
4.17 PM, MONDAY, 20 MAY 2013
ORDER
HIS HONOUR: The court has cross applications before it in these two proceedings. In each the first filed was one by the first defendant under rule 674(c) seeking dismissal of the proceeding for failure of the respondent plaintiff to provide the first tranche of security for costs required by an order of the court. The cross-application is one seeking changes to that order by revoking it, varying the amount of it or allowing additional time, specifically to the 20th of August 2013 - being the date nominated by the plaintiff’s director. That last respect is the only one in which any of the applications succeeds.
The order requiring provision of security came about in extraordinary circumstances. Its date is 9 October 2012, generating a surprise in a reader that in each matter, of the $50,000 security for costs required, the first $20,000 was required “within 14 days after 12 April 2012”, further amounts of $20,000 and $10,000 being required to be secured to the registrar’s satisfaction within seven days after the filing of the request for trial date and then not less than 14 days before the first day of trial. It appears that the plaintiff was, by definition, in default in respect of the first $20,000.
On the 12th of April 2012 his Honour gave reasons for his conclusions in relation to both claims in two important respects. The first one was what security for costs, if any, ought to be provided. The second was the extent to which the plaintiff’s claims fell relevantly within the purview of the Subcontractors’ Charges Act, large components of the claims being for damages, prolongation and such matters and, as it was held, not within the Act.
In relation to security for costs, his Honour’s approach was to draw inferences unfavourable to the plaintiff’s financial soundness from its reticence in responding to invitations to disclose assets and also its being a $2 company. His Honour, with his usual thoroughness, scrutinised the cost estimates of the parties’ rival cost assessor experts, coming down somewhere in the middle. He set the parties a complex exercise for the purpose of determining the dollar amounts of each of the claims which came within the purview of the Subcontractors’ Charges Act properly. Extreme difficulty was said to have been encountered in that regard by counsel and solicitors engaged in it, and there were difficulties attributable to his Honour’s absence from the jurisdiction adding to the delay, which explains the unusual chronology here.
It’s not necessary to consider the implications of the plaintiff’s default in provision of security which on one view existed from the 26th of April 2012. It’s unlikely that the plaintiff…
Keep reading for free
Create a free CaseChat account to read ASAP Plasterers Pty Ltd v Matrix Projects (Qld) Pty Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2013] QDC 218
- Decision Date
CaseChat Overview and Summary
The central legal issues before the court were whether the plaintiff's failure to comply with the security for costs order warranted dismissal of their claims and whether there were grounds to vary the security order. The court considered the plaintiff's impecuniosity and the defendants' role in it, but found that the security order should not be entirely dispensed with. It was determined that while the plaintiff's financial difficulties might be relevant to the amount of security required, this was not the appropriate stage to address those issues.
The court decided that the defendants' applications for dismissal of the plaintiff's claims were to be dismissed, and that the deadline for the first payment of security should be extended to 20 August 2013. This decision was made to avoid potential injustices that might arise from a more stringent enforcement of the security order. The court also noted that the costs of the defendants' applications would be borne by the plaintiff, and vice versa for the plaintiff's applications.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.