SUPREME COURT OF QUEENSLAND

CITATION:

Artesian Hospitality Pty Ltd v Tsuen Fung Holdings Pty Ltd [2021] QSC 288

PARTIES:

ARTESIAN HOSPITALITY PTY LTD
ACN 623 276 184

(applicant)

v
TSUEN FUNG HOLDINGS PTY LTD
ACN 106 616 031

(respondent)

FILE NO:

BS 10306 of 2021

DIVISION:

Trial

PROCEEDING:

Originating Application

ORIGINATING COURT:

Supreme Court at Brisbane

DELIVERED ON:

17 November 2021

DELIVERED AT:

Brisbane

HEARING DATE:

8 October 2021

JUDGE:

Flanagan J

ORDER:

1.     The amended originating application is dismissed. 

2.     I will hear the parties as to costs.

CATCHWORDS:

CONTRACTS – GENERAL CONTRACTUAL PRINCIPLES – FORMATION OF CONTRACTUAL RELATIONS – AGREEMENTS CONTEMPLATING EXECUTION OF FORMAL DOCUMENT – WHERE CONCLUDED CONTRACT – where the parties executed a Heads of Agreement requiring them to use reasonable endeavours to proceed to execute a lease on the basis of the terms set out in the Heads of Agreement – where the Heads of Agreement came to an end if the parties could not agree a lease in accordance with the Heads of Agreement by a certain date – whether, on its proper construction, the Heads of Agreement was an agreement for lease that left scope only for negotiation regarding the form, but not the substance, of the lease terms, or whether it was merely an agreement to negotiate a lease

CONTRACTS – GENERAL CONTRACTUAL PRINCIPLES – DISCHARGE, BREACH AND DEFENCES TO ACTION FOR BREACH – PERFORMANCE – where the parties were required to use reasonable endeavours to proceed to execute a lease on the basis of terms set out in a Heads of Agreement – where the parties exchanged several drafts of a lease – where the applicant wanted the express inclusion of a certain obligation on the respondent in the lease – where the respondent consistently opposed that express inclusion – where the parties convened a telephone conference to discuss the relevant clause – where the applicant submits that the parties reached agreement on the clause during the telephone conference – where the respondent denies that such agreement occurred – whether the parties satisfied the obligation to use reasonable endeavours – whether the parties agreed on the final terms of the lease – whether the respondent should be ordered to specifically perform the Heads of Agreement by entering into the lease which the applicant submits was agreed to

Cypjayne Pty Ltd v Babcock & Brown International Pty Ltd (2011) 282 ALR 152; [2011] NSWCA 173, cited
Electricity Generation Corporation v Woodside Energy Ltd (2014) 251 CLR 640; [2014] HCA 7, cited
Expectation Pty Ltd v Pinnacle VRB Ltd [2002] WASCA 160, cited
G R Securities Pty Ltd v Baulkham Hills Private Hospital Pty Ltd
(1986) 40 NSWLR 631, cited
Mount Bruce Mining Pty Ltd v Wright Prospecting Pty Ltd (2015) 256 CLR 104; [2015] HCA 37, cited

COUNSEL:

R R Ivessa, with D E Fawcett, for the applicant

R J Douglas QC, with J K Meredith, for the respondent

SOLICITORS:

McCullough Robertson Lawyers for…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Artesian Hospitality Pty Ltd v Tsuen Fung Holdings Pty Ltd and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details

Case
[2021] QSC 288
Decision Date

CaseChat Overview and Summary

In the case of Artesian Hospitality Pty Ltd v Tsuen Fung Holdings Pty Ltd, the dispute centered around the interpretation and execution of a Heads of Agreement for the lease of premises located at 297-299 Brunswick Street, Fortitude Valley. The applicant sought an order for specific performance of the Heads of Agreement, which required the parties to use reasonable endeavours to proceed to execute a lease based on the terms outlined in the Heads of Agreement. The respondent, however, terminated the Heads of Agreement and refused to execute the lease, leading to the applicant's application for specific performance. The court was tasked with determining whether the Heads of Agreement constituted a binding agreement for lease, leaving only the form of the lease to be negotiated, or whether it was merely an agreement to negotiate the lease terms.

The primary legal issues revolved around the interpretation of the Heads of Agreement and the obligations of the parties under it. Specifically, the court had to decide whether the Heads of Agreement was an enforceable agreement that left only the form of the lease to be negotiated, or if it merely set out an agreement to negotiate a lease. Additionally, the court needed to assess whether the parties satisfied their obligation to use reasonable endeavours to execute a lease and whether they had agreed on the final terms of the lease, particularly regarding a specific clause that the applicant sought to include.

The court found that the Heads of Agreement was not an agreement for lease but rather an agreement to negotiate the lease terms. The court concluded that the obligation to use reasonable endeavours did not mean that the parties were required to reach an agreement on all terms. The court also found that the parties did not agree on the final terms of the lease, particularly regarding the specific clause that the applicant wanted to include. The court dismissed the application for specific performance and ordered that the costs of the proceeding would be heard separately.

The court's decision highlights the importance of clearly defining the obligations and expectations of the parties in a Heads of Agreement to avoid future disputes. The court's interpretation of the Heads of Agreement and the obligations of the parties provides guidance to parties entering into similar agreements in the future.

Orders

Orders of the court

1. The amended originating application is dismissed.

2. I will hear the parties as to costs.

Background

Background to the litigation

By order of Kelly J on 8 September 2021, the proceeding has been brought on for early trial. The evidence-in-chief was by way of affidavit with limited cross‑examinationof four deponents. For the reasons which follow, the application should be dismissed. My primary finding is that the Agreement, which was binding on the parties, was lawfully terminated by the respondent on 1 September 2021.Relevant background Va Duong Moc (Mr Moc) is the registered proprietor of two lots located at 297-299 Brunswick Street, Fortitude Valley (Property). The Property is leased to the respondent until 30 June 2039. The Property was significantly damaged by fire in 2020 and has since been unoccupied. Until recently, part of the Property comprising some of the ground floor and the first floor (Premises) was sublet by the respondent to NHJ Enterprises (Aust) Pty Ltd (NHJ). Tich Hin Moc, known as Jac Moc, is a son of Mr Moc. Mr Moc authorised Jac Moc to act on behalf of the respondent in negotiating with the applicant. Ellem Warren Lawyers acted for the respondent, initially through Ashleigh Boyce and, subsequently, through David Carrick and Chelsea Lee. Matthew Keegan is the managing director, sole director, company secretary and sole shareholder of the applicant. The applicant is part of the Artesian Hospitality Group, which operates four restaurants and four clubs. Joel McAndrew, a solicitor, is a director of McAndrew Law and is contracted to act as the applicant’s general counsel. On 19 May 2021, Mr Keegan contacted Jac Moc by text message, introducing himself and enquiring about leasing the Premises. Jac Moc emailed Mr Keegan a copy of the lease between the respondent and NHJ. On 25 May 2021, Jac Moc met Mr Keegan at the Premises. Others in attendance at this meeting included Jac Moc’s brother, Dich Hin Moc, who is known as James Moc. The Premises had been largely cleared of debris but remained a damaged shell as a result of the fire, with no internal walls except for the brick-built toilet block. Mr Keegan accepts that, during this meeting, Jac Moc informed him that the tenancy downstairs was linked by one lease with the upstairs part of the Premises and that any lease would therefore be for both the downstairs and upstairs sections. Jac Moc expressed his preference that the Premises operate as a nightclub. He told Mr Keegan that the respondent’s insurer would return the Premises to “what it was” (meaning its pre-fire state) and offered to introduce Mr Keegan to the builder. Mr Keegan stated that he would submit an offer but that he would need 30 days for due diligence and that, if he was happy, he would proceed. On 26 May 2021, Mr Keegan emailed Jac Moc a letter of offer to lease the Premises. The letter was headed “Without Prejudice and Subject to Lessee Final Approval”.[1] The letter of offer contained the following paragraph:“The information contained in this Lease Proposal is not a binding Lease between the Lessor and the Lessee. The Lessee reserves the right to withdraw from and terminate negotiations at any time prior to execution of formal Lease documents by both the Lessor and the Lessee and satisfaction of the other requirements (e.g. payment of the deposit, provision of certificates of currency for insurance and the bank guarantee).”[2][1]Affidavit of T H Moc sworn 16 September 2021, CD-14, exhibit page 60 (Second Moc Affidavit).[2]Second Moc Affidavit, exhibit page 63.

Evidence

Evidence before the court

Decision

Reasons for decision