ANGELA KINNANE v ZEE HOMES PTY LTD
[2003] SASC 187
Full Court: Duggan, Debelle and Lander JJ
DUGGAN J I agree with the reasons for decision of Debelle J.
DEBELLE J This appeal by leave against a decision granting leave to appeal from a decision of an arbitrator was heard on 14 April 2003. The parties wished to file affidavit evidence. After they had done so, the hearing resumed on 6 June. The same day, after hearing further argument, the court announced its decision and said it would publish its reasons. These are my reasons for joining in that order.
The appellant and the respondent had entered into a lump sum building contract to construct additions and alterations to a dwelling in Unley. I will refer to the appellant as “the owner” and to the respondent as “the contractor”. During the course of the work disputes arose. Eventually another builder was appointed to complete the work. The contractor sought to recover from the owner the balance of the contract price and made claims for variations and other items. The owner counterclaimed for defective work. The dispute was referred to arbitration. The arbitrator published his award on 29 August 2002. The contractor was dissatisfied with the award and on 11 September 2002 applied for leave to appeal. The application was heard by a judge of this Court on 20 September. Although the application was made ex parte, counsel for the owner appeared on the hearing of the application. The judge reserved his decision. On 29 October 2002 the judge granted leave but did not publish any reasons for that decision.
The owner responded on 3 December 2002 by applying for leave to appeal from the order of the judge granting the contractor leave to appeal from the award of the arbitrator. That application was heard ex parte on 19 December 2002 by the same judge who had granted leave to appeal from the award of the arbitrator. The judge granted leave to appeal to the Full Court from his own order granting leave to appeal from the award of the arbitrator.
I have some reservations about the desirability of the procedure by which this appeal came before the court. Although a party to an award may appeal against an order refusing leave to appeal: Minister for Industrial Affairs v Civil Tech Pty Ltd (1997) 69 SASR 348; Energy Brix Australia Corporation Pty Ltd v National Logistics Coordinators (Morwell) Pty Ltd [2002] VCSA 113, different issues arise where leave to appeal has been granted. The procedure adopted in this case had the advantage at least of saving the substantial cost of preparing what would have been a very bulky set of appeal books. As neither party raised any objection, it is unnecessary to examine the matter.
The Criteria for Leave
The question whether leave to appeal should be granted is governed by s 38 of the Commercial Arbitration Act 1986 as amended by the Act No. 64 of 1992. When hearing…
Keep reading for free
Create a free CaseChat account to read Angela Kinnane v Zee Homes Pty Ltd No. Scciv-02-1279 and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2003] SASC 187
- Decision Date
CaseChat Overview and Summary
The court identified six sets of issues raised by the contractor as grounds for appeal. The first issue involved the interpretation of s 72 of the Development Act 1993, which the contractor argued the arbitrator had misinterpreted. However, the court found that the contractor could not satisfy the criteria in s 38(5)(a) and (b) because the determination of the meaning of s 72 would not substantially affect the rights of the parties, and there was no manifest error of law or strong evidence of an error that would add substantially to the certainty of commercial law.
The second set of issues concerned the arbitrator's decision that the owner was entitled to terminate the contract at common law. The court found that this decision, while arguably a question of law, was based on the evidence and did not constitute a manifest error of law. Furthermore, the decision did not add to the certainty of commercial law.
The third set of issues related to the award of damages for mental distress and inconvenience. The court found that the award did not constitute a manifest error of law and did not add substantially to the certainty of commercial law.
The fourth set of issues involved findings by the arbitrator that the contractor was liable for work agreed by the owner's architect. The court found that there was no manifest error of law and that the issue did not add substantially to the certainty of commercial law.
The fifth set of issues concerned an admission by the owner in the defence to the contractor's claim for fees. The court found that the arbitrator had misunderstood the effect of the pleadings, resulting in a manifest error of law on the face of the award. The court also found that the error was substantial enough to warrant a grant of leave to appeal.
The final set of issues concerned clause 9.2 of the building contract, which deals with delays. The court found that the contractor had not satisfied the requirements of s 38(5) for a grant of leave to appeal on this issue.
In summary, the Full Court found that the contractor had failed to satisfy the criteria for a grant of leave to appeal in all but one of the grounds of the intended appeal. The court allowed the appeal on the single ground where the contractor had demonstrated a manifest error of law on the face of the award that was sufficiently substantial. The court varied the award to allow for the payment of $4,270 to the contractor.
Orders
Orders of the court
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi
Legal Principle Established
Established by: DUGGAN J, DEBELLE J, LANDER J