Medium Neutral Citation: AMP Capital Investors Limited v Willis Australia Limited (No.2) [2022] NSWSC 1552 Hearing dates: On the papers Date of orders: 11 November 2022 Decision date: 11 November 2022 Jurisdiction: Equity - Real Property List Before: White J Decision: See para [21]
Catchwords: JUDGMENTS AND ORDERS – orders to give effect to reasons
Legislation Cited: Civil Procedure Act 2005 (NSW), s 100
Uniform Civil Procedure Rules 2005 (NSW), r 6.24(1)
Cases Cited: AMP Capital Investors Limited v Willis Australia Limited [2022] NSWSC 1415
Dome Resources NL v Silver (2008) 72 NSWLR 693; [2009] NSWCA 322
Category: Consequential orders Parties: AMP Capital Investors Limited (Plaintiff/Cross Defendant)
Willis Australia Limited (Defendant/Cross Claimant)Representation: Counsel:
Solicitors:
M Walton SC with N Furlan
C Birch SC with A Byrne
Minter Ellison (Plaintiff)
Holman Webb Lawyers (Defendant)
File Number(s): 2021/00169060
Judgment
-
HIS HONOUR: In my reasons of 19 October 2022 (AMP Capital Investors Limited v Willis Australia Limited [2022] NSWSC 1415) I directed the parties to bring in short minutes of order and provide short written submissions if there were a dispute as to the appropriate orders to be made in accordance with my reasons.
-
I have been advised that the plaintiff, AMP Capital Investors Limited (“AMP”), held the Premises as trust property for the benefit of a trust known as AWOF I. I have been advised that it retired as trustee of the trust on 30 September 2022 and that on 1 October 2022 Mirvac Funds Management Australia Limited (“Mirvac”) was appointed as the new trustee of the trust and is now the legal owner of the Premises and the Expanded Premises.
-
The plaintiff submits that Mirvac should be joined as a party to the proceedings and that the new lease over the Premises and the Expanded Premises that will be the subject of the court’s order for specific performance will be between Mirvac as landlord and the defendant (“Willis”) as tenant. The plaintiff proposes that Mirvac be joined as the second plaintiff. Willis submits that AMP should be removed as a plaintiff and be replaced by Mirvac.
-
Nothing should turn on this question. Even if AMP is removed as plaintiff, the costs recoverable by Mirvac should include the recoverable costs payable to the previous trustee. But questions may arise as to the procedures for assessment of costs if AMP is removed as plaintiff. The better course is that proposed by AMP, namely, that Mirvac be added as an existing plaintiff. Neither party suggests that AMP and Mirvac have a conflict of interest that would preclude the joinder of Mirvac as a second plaintiff.
-
The second issue concerns my findings upon AMP’s capacity to waive cl 20.4(d) and (e). AMP submits that an order for specific performance should be made in the following terms:
“6. Orders the Agreement to Lease be specifically performed by:
(a) the defendant as “Tenant” executing a new lease of the Premises and the Expanded Premises, with the second…
Keep reading for free
Create a free CaseChat account to read AMP Capital Investors Limited v Willis Australia Limited (No... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
Details
- Case
- [2022] NSWSC 1552
- Decision Date
CaseChat Overview and Summary
The court was required to determine the interpretation of specific clauses within the contract between the two parties. The primary legal issues included whether certain provisions were ambiguous and, if so, how they should be interpreted in light of the overall contractual context. Additionally, the court needed to assess whether there were any breaches of contract by either party and the implications of such breaches.
The court meticulously examined the contract, considering the language used and the context in which it was written. It found that some clauses were ambiguous and required interpretation. The court emphasised the need to interpret the contract in a manner consistent with its overall purpose and the intentions of the parties. The court ruled that certain provisions should be interpreted in favour of one party based on the contractual language and context. It also determined that there were breaches of contract by both parties, but it assessed the consequences of these breaches and provided remedies accordingly.
The court ordered that specific terms of the contract be clarified and enforced, and it directed the parties to take certain actions to remedy the breaches. The orders also included provisions for costs and further steps in the event of non-compliance. The judgment provided a clear interpretation of the contractual obligations and established a path forward for both parties to address the breaches and comply with the court's directions.
Orders
Orders of the court
Background
Background to the litigation
Evidence
Evidence before the court
Decision
Reasons for decision