JURISDICTION : STATE ADMINISTRATIVE TRIBUNAL
STREAM: COMMERCIAL & CIVIL
ACT: CONSTRUCTION CONTRACTS ACT 2004 (WA)
CITATION: ALL ROOFS PTY LTD and SOUTHGATE CORPORATION PTY LTD [2012] WASAT 178
MEMBER: MS NATASHA OWEN-CONWAY (MEMBER)
HEARD: 4 MAY 2012
DELIVERED : 22 AUGUST 2012
FILE NO/S: CC 313 of 2012
BETWEEN: ALL ROOFS PTY LTD
Applicant
AND
SOUTHGATE CORPORATION PTY LTD
Respondent
Catchwords:
Construction Contracts Act 2004 (WA) Payment claim Payment dispute Claim arising under construction contract Payment due under construction contract Contract of variation No variation or no oral variation term in original contract Consideration and certainty for valid contract of variation Alleged contract of variation not for extra work or work 'outside the contract' No consideration for variation of contract Claim in estoppel or unjust enrichment is not a claim under the construction contract
Legislation:
Construction Contracts Act 2004 (WA), s 3, s 6, s 25, s 26, s 31(2)(a), s 31(2)(a)(ii), s 34(2), s 46(1)
State Administrative Tribunal Act 2004 (WA), s 17
Result:
Application for review dismissed
Category: B
Representation:
Counsel:
Applicant: Mr S Brown
Respondent: Mr R Shaw
Solicitors:
Applicant: Contract Intelligence Pty Ltd
Respondent: Lavan Legal
Case(s) referred to in decision(s):
Branir v Owston Nominees Pty Ltd (No 2) [2001] FCA 1833
Computer Services Pty Ltd v Digital Equipment Corp (Aust) Pty Ltd (1988) 5 BPR 11,110
David Securities Pty Ltd v Commonwealth Bank of Australia ; (1992) 175 CLR 353
David Securities Pty Ltd v Commonwealth Bank of Australia [1992] HCA 48 ; (1992) 175 CLR 353
Equuiscorp Pty Ltd v Haxton, Bassat and Cunningham Warehouse Pty Ltd [2012] HCA 7
GEC Marconi Systems Pty Limited v BHP Information Technology Pty Limited [2003] FCA 50
Marine & Civil Bauer Joint Venture and Leighton Kumagai Joint Venture [2005] WASAT 269
Pavey & Matthews Pty Ltd v Paul [1987] HCA 5; (1987) 162 CLR 221
Roscola v Thomas (1842) 3 QB 234
Update Constructions Pty Ltd v Rozelle Child Care Centre Ltd (1990) 20 NSWLR 251
REASONS FOR DECISION OF THE TRIBUNAL:
Summary of Tribunal's decision
All Roofs Pty Ltd made an application for adjudication of a 'payment dispute', pursuant to the Construction Contracts Act 2004 (WA), against Southgate Corporation Pty Ltd. All Roofs Pty Ltd claimed that there had been a delay in the performance of the contract works caused by a direction by, or on behalf of, Southgate Corporation Pty Ltd, as to the manner in which the performance of the contract works were scheduled, and that All Roofs Pty Ltd was entitled to payment of reasonable costs arising from that delay pursuant to the contract between the parties.
Alternatively, All Roofs Pty Ltd asserted that there was a variation to the contract between the parties and that it was entitled, pursuant to that contract of variation, to payment of 'fair and reasonable costs' associated with a variation to the scheduled performance of the contract works, in…
Keep reading for free
Create a free CaseChat account to read All Roofs Pty Ltd and Southgate Corporation Pty Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
Find similar cases
Other decisions on the same topics. Each opens in a new tab.
Details
- Case
- [2012] WASAT 178
- Decision Date
CaseChat Overview and Summary
The court examined whether the alleged variation was enforceable under the Construction Contracts Act 2004 (WA). The claimant argued that despite the absence of a formal written variation, an oral agreement constituted a valid contract variation. The court considered the principles governing contract variations, particularly the requirement for consideration and certainty. It held that for a variation to be valid, there must be clear evidence of an agreement supported by consideration. The court further noted that the claimant's reliance on estoppel or unjust enrichment did not constitute a claim under the construction contract as required by the Act.
The court concluded that the claimant's argument for a contract variation lacked the necessary consideration and certainty. The absence of a written variation or a clause permitting oral variations in the original contract meant that no enforceable variation existed. Consequently, the claimant's claim for additional payment based on an alleged variation was not substantiated. The court dismissed the claim, reinforcing the importance of clear contractual terms regarding variations and the necessity of evidence supporting any purported changes to the original agreement.
Background
Background to the litigation
Decision
Reasons for decision
Ratio Decidendi