District Court
New South Wales
Medium Neutral Citation: Advanced National Services Pty Ltd v Daintree Contractors Pty Ltd (No 2) [2019] NSWDC 105 Hearing dates: On the papers Date of orders: 05 April 2019 Decision date: 05 April 2019 Jurisdiction: Civil Before: Abadee DCJ Decision: See paragraph 61.
Catchwords: PRACTICE AND PROCEDURE – costs – exercise of discretion – Calderbank offers by defendant – judgment sum less than settlement sum offered - whether plaintiff’s rejection unreasonable – whether circumstances generally warranted departure from usual order that costs follow the event. Legislation Cited: Civil Procedure Act 2005 (NSW)
Uniform Civil Procedure Rules 2005 (NSW)Cases Cited: Calderbank v Calderbank [1976] Fam 93
Commonwealth of Australia v Gretton [2008] NSWCA 117
Council of City of Liverpool v Turano (No.2) [2009] NSWCA 176
Elite Protective Personnel Pty Ltd v Salmon (No.2) [2007] NSWCA 373
Jones v Bradley (No.2) [2003] NSWCA 258
Leichhardt Municipal Council v Green [2004] NSWCA 341
Ofria v Cameron (No.2) [2008] NSWCA 242
SMEC Testing v Campbelltown City Council [2000] NSWCA 323Category: Costs Parties: Advanced National Services Pty Ltd (Plaintiff)
Daintree Contractors Pty Ltd (Defendant)Representation: Counsel:
Solicitors:
Mr J Young (Plaintiff)
Mr C Conde (Defendant)
Fontgalland Lawyers (Plaintiff)
HWL Ebsworth Lawyers (Defendant)
File Number(s): 2017/256961
Judgment
Background
-
I delivered reasons for judgement in this matter (Advanced National Services Pty Ltd v Daintree Contractors Pty Ltd [2019] NSWDC 77 (the “principal reasons”) on 27 March 2019. I invited the parties to make submissions as to orders disposing of the proceeding, including orders for interest and costs. In what follows, familiarity with the principal reasons is assumed.
-
There is little difference, in substance, to the general orders disposing of the proceeding. Having considered both parties’ formulations, the plaintiff is entitled to orders:
For judgment for the plaintiff for the sum of $47,660. This judgment sum is inclusive of interest.
That the defendant’s cross-claim is dismissed.
-
The remaining dispute centres upon the order for costs.
-
The defendant (DC) accepts that it should pay the plaintiff’s costs on the ordinary basis up to a certain date. Thereafter, it submits, the plaintiff (ANS) should pay DC’s costs on an indemnity basis. In this regard, DC points to correspondence (sent on a ‘without prejudice’ basis) to ANS’ solicitors both before and during the proceeding. I will return to the detail of this correspondence below.
-
For its part, ANS submits that it succeeded on its claim (and DC’s cross-claim) and that there should be no qualification to the general rule that costs should follow the event.
The facts
-
The proceeding commenced on 23 August 2017. About a month before that event, on 28 July 2017 the then solicitors for DC (TressCox Lawyers) sent two letters to the solicitors for the ANS (Fontgalland Lawyers). At this stage, a draft statement of claim had been supplied to the defendant, and the two letters were responsive to this document. The lengthier letter did a number of things: it disputed the quantum of the unpaid invoices…
Keep reading for free
Create a free CaseChat account to read Advanced National Services Pty Ltd v Daintree Contractors Pt... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
Find similar cases
Other decisions on the same topics. Each opens in a new tab.
Details
- Case
- [2019] NSWDC 105
- Decision Date
CaseChat Overview and Summary
The primary issue for the court was whether the plaintiff's rejection of the defendant's offer was unreasonable, and whether the circumstances warranted a departure from the usual order that costs follow the event. The court noted that the plaintiff had rejected the defendant's offer on the basis that it was not genuine, and that the defendant had not provided the necessary documentation to support the offer. The court also noted that the plaintiff had been successful in recovering the full amount of the debt, and that the defendant had not provided any evidence to support its contention that the plaintiff's rejection was unreasonable. The court held that the plaintiff's rejection was not unreasonable, and that the circumstances did not warrant a departure from the usual order that costs follow the event.
The court found that the plaintiff was entitled to costs from the defendant to the extent of the costs incurred up until the date of the defendant's offer, and that the defendant was entitled to costs from the plaintiff to the extent of the costs incurred from the date of the defendant's offer until the date of the consent judgment. The court also held that the plaintiff was not entitled to any costs in relation to the defendant's offer, as the offer was not genuine and the circumstances did not warrant a departure from the usual order that costs follow the event. The court made an order for costs in accordance with the findings.
The court's decision in this case provides guidance on the exercise of discretion in relation to costs in proceedings where a defendant makes a Calderbank offer. The court held that a plaintiff's rejection of a Calderbank offer is not necessarily unreasonable, and that the circumstances must warrant a departure from the usual order that costs follow the event. The court also held that a defendant's offer must be genuine and supported by appropriate documentation, and that a plaintiff is not entitled to costs in relation to an offer that is not genuine or that is made in circumstances that do not warrant a departure from the usual order. The decision is likely to be of interest to practitioners in the area of costs and procedure.
Orders
Orders of the court
See paragraph 61.
Background
Background to the litigation
Decision
Reasons for decision
Ratio Decidendi