SUPREME COURT OF QUEENSLAND
CITATION:
ACN 096 278 483 Pty Ltd v Vercorp Pty Ltd & Anor; Vercorp Pty Ltd v ACN 096 278 483 Pty Ltd [2011] QCA 189
PARTIES:
In Appeal No 12847 of 2010:
ACN 096 278 483 PTY LTD as trustee of the WILLIAMS FAMILY TRUST
(appellant)
v
VERCORP PTY LTD
ACN 010 198 268
(first respondent)
HEGIRA LIMITED
ACN 008 610 357
(second respondent)In Appeal No 12868 of 2010:
VERCORP PTY LTD
ACN 010 198 268
(appellant)
v
ACN 096 278 483 PTY LTD as trustee of the WILLIAMS FAMILY TRUST
(respondent)FILE NO/S:
Appeal No 12847 of 2010
Appeal No 12868 of 2010
SC No 6442 of 2004DIVISION:
Court of Appeal
PROCEEDING:
General Civil Appeals
ORIGINATING COURT:
Supreme Court at Brisbane
DELIVERED ON:
9 August 2011
DELIVERED AT:
Brisbane
HEARING DATE:
7 April 2011
JUDGES:
Fraser and White JJA and Atkinson J
Separate reasons for judgment of each member of the Court, each concurring as to the orders madeORDERS:
In Appeal No 12847 of 2010:
1. Dismiss the appeal.
2. Allow the cross appeal.
3. Declare that the contract between the first respondent and the appellant for the purchase by the first respondent of Lot 413 on SP133280 should be specifically performed and carried into effect.
4. Declare that the contract between the first respondent and the appellant for the purchase by the first respondent of Lot 414 on SP133280 should be specifically performed and carried into effect.
5. The parties are at liberty to apply in the trial division for any further or other orders relating to the specific performance of those contracts.
6. Order that the appellant pay the respondents’ costs of and incidental to the appeal.
7. Order that the first respondent pay the appellant’s costs of the first respondent’s cross appeal.
In Appeal No 12868 of 2010:
1. Appeal dismissed with costs.
CATCHWORDS:
CONTRACTS – GENERAL CONTRACTUAL PRINCIPLES – PARTIES – GENERAL PRINCIPLES – where Hegira and Barrier Developments “and or nominee” entered into four contracts for the sale of land which contained post settlement obligations – where Barrier Developments nominated ACN as the purchaser under the contracts – where ACN and Barrier Developments were controlled by the same director – where during pre-contractual negotiations Hegira made it clear that a nominee would only be accepted if it agreed to comply with the post settlement obligations – where ACN paid further deposits in consideration of extensions of the finance approval dates and the balance purchase price – whether, objectively viewed, ACN intended to bind itself to the contracts, including the post settlement obligations
CONVEYANCING – BREACH OF CONTRACT FOR SALE AND REMEDIES – PURCHASER’S REMEDIES – SPECIFIC PERFORMANCE – GENERAL PRINCIPLES – where the contracts for sale included liquidated damages clauses and options for Hegira to repurchase the land in the event of breach of the post settlement obligations – where Hegira (and Vercorp as Hegira’s assignee) commenced proceedings in the District Court for damages pursuant to…
Keep reading for free
Create a free CaseChat account to read ACN 096 278 483 Pty Ltd v Vercorp Pty Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2011] QCA 189
- Decision Date
CaseChat Overview and Summary
The court was required to determine several legal issues, including whether ACN intended to be bound by the contracts, including the post-settlement obligations, whether Vercorp waived its right to seek specific performance by instituting proceedings for damages, and whether ACN validly terminated the contracts under a condition precedent. Additionally, the court had to assess whether the trial judge correctly found that Vercorp did not breach its obligations under the contracts, and whether ACN properly terminated the contracts due to a failure to comply with a condition precedent.
The court held that ACN did intend to be bound by the contracts, including the post-settlement obligations, as it had made further payments in consideration of extensions and agreed to the terms during negotiations. The court also found that Vercorp did not waive its right to seek specific performance by pursuing damages, as the two remedies were not mutually exclusive. Regarding the condition precedent, the court found that the valuations were indeed a condition precedent to performance, but since ACN did not plead this condition as a basis for termination, the trial judge's finding that ACN validly terminated the contracts was upheld. Finally, the court determined that Vercorp did not breach its obligations because the determination of the price by valuation was a condition precedent to the performance of the obligation.
The court's final orders were to dismiss the appeal, allow the cross appeal, and declare that the contracts for the purchase of Lots 413 and 414 should be specifically performed. The parties were at liberty to apply for further orders relating to specific performance. Additionally, the appellant was ordered to pay the respondents’ costs of the appeal, and the first respondent was ordered to pay the appellant’s costs of its cross appeal.
Orders
Orders of the court
In Appeal No 12847 of 2010:
1. Dismiss the appeal.
2. Allow the cross appeal.
3. Declare that the contract between the first respondent and the appellant for the purchase by the first respondent of Lot 413 on SP133280 should be specifically performed and carried into effect.
4. Declare that the contract between the first respondent and the appellant for the purchase by the first respondent of Lot 414 on SP133280 should be specifically performed and carried into effect.
5. The parties are at liberty to apply in the trial division for any further or other orders relating to the specific performance of those contracts.
6. Order that the appellant pay the respondents’ costs of and incidental to the appeal.
7. Order that the first respondent pay the appellant’s costs of the first respondent’s cross appeal.
In Appeal No 12868 of 2010:
1. Appeal dismissed with costs.
Background
Background to the litigation
The matter came before the Supreme Court of Queensland as an appeal from the District Court and a cross appeal from the first respondent. The District Court had dealt with proceedings for damages under the liquidated damages clauses in the contracts, while the Supreme Court addressed issues of specific performance and alleged breaches of contract. The trial judge had made findings on the enforceability of the contracts, including the post settlement obligations, and whether there had been breaches allowing for termination. The Supreme Court's role was to review the findings and orders made by the trial judge.
Decision
Reasons for decision
1. Whether, objectively viewed, ACN intended to bind itself to the contracts, including the post settlement obligations.
2. Whether the trial judge erred in finding that Vercorp had not waived its rights to seek specific performance by instituting proceedings for damages in the District Court.
3. Whether the trial judge erred in declining to make a decree of specific performance because of allegations of misconduct in ACN’s counterclaim.
4. Whether the trial judge erred in finding that Vercorp had not breached its obligation to provide transfer documents "a reasonable time before the Settlement Date."
5. Whether the trial judge erred in finding that the valuations were a condition precedent to performance allowing either party to terminate the contracts.
6. Whether the trial judge erred in finding that ACN had validly terminated the contracts pursuant to the condition precedent.
Held
1. The court held that ACN objectively intended to bind itself to the contracts, including the post settlement obligations.
2. The court held that the trial judge did not err in finding that Vercorp had not waived its rights to seek specific performance by instituting proceedings for damages in the District Court.
3. The court held that the trial judge erred in declining to make a decree of specific performance because of allegations of misconduct in ACN’s counterclaim.
4. The court held that the trial judge did not err in finding that Vercorp had not breached its obligation to provide transfer documents "a reasonable time before the Settlement Date."
5. The court held that the trial judge did not err in finding that the valuations were a condition precedent to performance allowing either party to terminate the contracts.
6. The court held that the trial judge did not err in finding that ACN had validly terminated the contracts pursuant to the condition precedent.
Ratio Decidendi
Legal Principle Established
The court first considered whether ACN intended to bind itself to the contracts, including the post settlement obligations. The court held that the objective view was that ACN did intend to be bound by the contracts. This conclusion was based on the fact that ACN paid further deposits in consideration of extensions of the finance approval dates and the balance purchase price, and the fact that Barrier Developments and ACN were controlled by the same director.
Next, the court examined whether the trial judge erred in finding that Vercorp had not waived its rights to seek specific performance by instituting proceedings for damages in the District Court. The court found that the trial judge did not err in this regard, as the institution of proceedings for damages did not preclude Vercorp from later seeking specific performance.
The court then addressed whether the trial judge erred in declining to make a decree of specific performance because of allegations of misconduct in ACN’s counterclaim. The court found that the trial judge did err in this regard. The allegations of misconduct had not been substantiated and it did not appear that they would be pursued. Therefore, the court held that the trial judge should not have declined to make a decree of specific performance on this basis.
The court next considered whether the trial judge erred in finding that Vercorp had not breached its obligation to provide transfer documents "a reasonable time before the Settlement Date." The court held that the trial judge did not err in this regard, as the determination of the price by valuation was a condition precedent to the performance of the obligation, and Vercorp had provided the transfer documents and valuation at about midday on the day of settlement.
The court then examined whether the trial judge erred in finding that the valuations were a condition precedent to performance allowing either party to terminate the contracts. The court held that the trial judge did not err in this regard, as the contracts explicitly provided that the valuations were a condition precedent.
Finally, the court considered whether the trial judge erred in finding that ACN had validly terminated the contracts pursuant to the condition precedent. The court held that the trial judge did not err in this regard, as the contracts allowed either party to terminate if the condition precedent was not met. The court found that ACN had validly terminated the contracts because Vercorp had failed to provide the valuations on the agreed date. The court noted that while ACN did not rely on the condition precedent as a basis for terminating the contracts in its pleadings, the court could consider the condition precedent as it was a matter of law and not pleading. The binding legal principle established by the decision is that a party can validly terminate a contract pursuant to a condition precedent even if it does not specifically plead the condition precedent in its defence or counterclaim, provided the condition precedent is clearly set out in the contract.